Your results are here!! for" Project Management Professional (PMP) Practice Test 5 "
0 of 65 questions answered correctly
Your time:
Time has elapsed
Your Final Score is : 0
You have attempted : 0
Number of Correct Questions : 0 and scored 0
Number of Incorrect Questions : 0 and Negative marks 0
Average score
Your score
Project Management Professional (PMP)
You have attempted: 0
Number of Correct Questions: 0 and scored 0
Number of Incorrect Questions: 0 and Negative marks 0
You can review your answers by clicking view questions. Important Note : Open Reference Documentation Links in New Tab (Right Click and Open in New Tab).
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
Answered
Review
Question 1 of 65
1. Question
Ryan is a Project Manager of a manufacturing project. Hurricane alert may delay the shipments of the of the main components of the project that would affect the project schedule. What should the Project Manager do next?
Correct
In this situation, the risk has triggered and it has not yet occurred. So option A is ruled out. Option B is also ruled out here, as in this scenario the risk has triggered for natural calamity. Option C is close but, the question states that Project schedule will get impacted, if such risk occurs, so in this kind of scenario, the review of Risk Management Plan may not be the ideal choice. By considering elimination rule, D becomes the best answer because the question has keywords like “hurricane alert”. Further, the project manager has to do a comprehensive identification considering a broad range of sources of risk to ensure that as many uncertainties as possible that might affect project objectives have been identified, as well as Identify Risks process should take input from a range of project stakeholders to ensure that all perspectives are represented and considered. By this way the Project Manager can identify all risks that also includes this hurricane risk and accept actively and assign contingency plan with trigger conditions. The plan can be updated because all risk processes are iterative. So among all options provided, D is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 445.
Incorrect
In this situation, the risk has triggered and it has not yet occurred. So option A is ruled out. Option B is also ruled out here, as in this scenario the risk has triggered for natural calamity. Option C is close but, the question states that Project schedule will get impacted, if such risk occurs, so in this kind of scenario, the review of Risk Management Plan may not be the ideal choice. By considering elimination rule, D becomes the best answer because the question has keywords like “hurricane alert”. Further, the project manager has to do a comprehensive identification considering a broad range of sources of risk to ensure that as many uncertainties as possible that might affect project objectives have been identified, as well as Identify Risks process should take input from a range of project stakeholders to ensure that all perspectives are represented and considered. By this way the Project Manager can identify all risks that also includes this hurricane risk and accept actively and assign contingency plan with trigger conditions. The plan can be updated because all risk processes are iterative. So among all options provided, D is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 445.
Unattempted
In this situation, the risk has triggered and it has not yet occurred. So option A is ruled out. Option B is also ruled out here, as in this scenario the risk has triggered for natural calamity. Option C is close but, the question states that Project schedule will get impacted, if such risk occurs, so in this kind of scenario, the review of Risk Management Plan may not be the ideal choice. By considering elimination rule, D becomes the best answer because the question has keywords like “hurricane alert”. Further, the project manager has to do a comprehensive identification considering a broad range of sources of risk to ensure that as many uncertainties as possible that might affect project objectives have been identified, as well as Identify Risks process should take input from a range of project stakeholders to ensure that all perspectives are represented and considered. By this way the Project Manager can identify all risks that also includes this hurricane risk and accept actively and assign contingency plan with trigger conditions. The plan can be updated because all risk processes are iterative. So among all options provided, D is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 445.
Question 2 of 65
2. Question
During the mid of the project, the project manager is trying to assess whether the project level communications that are getting distributed to the stakeholders across different countries are aligned to the Project Management Plan.
What needs to be reviewed in this scenario?
Correct
The Question states that the Project Manager is involved in Monitor Stakeholder Engagement process. He needs to assess whether the distribution of Project Communications is in line to the Project Management Plan (i.e. Communication Management Plan and Stakeholder Engagement Plan in this scenario). Though A and C are input to the Monitor Stakeholder Engagement process, but it cannot give all information. Option D is ruled out because Stakeholder Engagement Assessment Matrix is a tool for assessing Stakeholder engagement. Project Communications( Output of Manage Communications process) is a valid input for Monitor Stakeholder Engagement process. Project communications include all project level communications that has been distributed to all stakeholders as defined in the Communication Management Plan and Stakeholder Engagement Plan. So, considering all options, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 532.
Incorrect
The Question states that the Project Manager is involved in Monitor Stakeholder Engagement process. He needs to assess whether the distribution of Project Communications is in line to the Project Management Plan (i.e. Communication Management Plan and Stakeholder Engagement Plan in this scenario). Though A and C are input to the Monitor Stakeholder Engagement process, but it cannot give all information. Option D is ruled out because Stakeholder Engagement Assessment Matrix is a tool for assessing Stakeholder engagement. Project Communications( Output of Manage Communications process) is a valid input for Monitor Stakeholder Engagement process. Project communications include all project level communications that has been distributed to all stakeholders as defined in the Communication Management Plan and Stakeholder Engagement Plan. So, considering all options, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 532.
Unattempted
The Question states that the Project Manager is involved in Monitor Stakeholder Engagement process. He needs to assess whether the distribution of Project Communications is in line to the Project Management Plan (i.e. Communication Management Plan and Stakeholder Engagement Plan in this scenario). Though A and C are input to the Monitor Stakeholder Engagement process, but it cannot give all information. Option D is ruled out because Stakeholder Engagement Assessment Matrix is a tool for assessing Stakeholder engagement. Project Communications( Output of Manage Communications process) is a valid input for Monitor Stakeholder Engagement process. Project communications include all project level communications that has been distributed to all stakeholders as defined in the Communication Management Plan and Stakeholder Engagement Plan. So, considering all options, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 532.
Question 3 of 65
3. Question
Customer has formally approved the result of last sprint review meeting. The project has just moved to closing and the project manager is trying to determine the dates in which all significant events in the project has been accomplished so far. What needs to be reviewed here?
Correct
The question states that the project manager is trying to determine the final dates on which the project milestones has been accomplished so far. For this, the Milestone list needs to be reviewed which is also a valid input for the Closing process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 124,186.
Incorrect
The question states that the project manager is trying to determine the final dates on which the project milestones has been accomplished so far. For this, the Milestone list needs to be reviewed which is also a valid input for the Closing process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 124,186.
Unattempted
The question states that the project manager is trying to determine the final dates on which the project milestones has been accomplished so far. For this, the Milestone list needs to be reviewed which is also a valid input for the Closing process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 124,186.
Question 4 of 65
4. Question
Working software is the primary measure of progress. This principle is religiously followed by which of the following life cycle approaches?
Correct
Working Software is the primary measure of progress is one of the twelve Agile Principles.
Agile Practice Guide – Project Management Institute Inc., 2017, Page(s) – 98.
Incorrect
Working Software is the primary measure of progress is one of the twelve Agile Principles.
Agile Practice Guide – Project Management Institute Inc., 2017, Page(s) – 98.
Unattempted
Working Software is the primary measure of progress is one of the twelve Agile Principles.
Agile Practice Guide – Project Management Institute Inc., 2017, Page(s) – 98.
Question 5 of 65
5. Question
The Business Case documents the business need and cost benefit analysis that justify the project. During closing, the accuracy of the Business Case gets documented in which of the following documents?
Correct
Lessons Learned register is updated as key output for Close Project or Phase process. It includes final information on phase or project closure. The accuracy of the business case is also documented in Lessons Learned Register as a part of the process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 127.
Incorrect
Lessons Learned register is updated as key output for Close Project or Phase process. It includes final information on phase or project closure. The accuracy of the business case is also documented in Lessons Learned Register as a part of the process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 127.
Unattempted
Lessons Learned register is updated as key output for Close Project or Phase process. It includes final information on phase or project closure. The accuracy of the business case is also documented in Lessons Learned Register as a part of the process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 127.
Question 6 of 65
6. Question
Ryan is a Project Manager of a Software development project that involves work on DevOps and RPA technology. Since there is scarcity of in house resources, the Project Management team has decided to outsource the work to a suitable vendor.
What tool can be used to gather necessary information on specific seller capabilities?
Correct
As the scenario states, the Project Management team is involved in planning. Market research, also a tool for Plan Procurement Management process includes examination of industry and specific seller capabilities.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 473.
Incorrect
As the scenario states, the Project Management team is involved in planning. Market research, also a tool for Plan Procurement Management process includes examination of industry and specific seller capabilities.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 473.
Unattempted
As the scenario states, the Project Management team is involved in planning. Market research, also a tool for Plan Procurement Management process includes examination of industry and specific seller capabilities.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 473.
Question 7 of 65
7. Question
You are the owner of a company whose organization structure type is Organic. Your company has been awarded a small project with limited budget.
Which of the following processes may be eliminated in such a project?
Correct
Availability of budget and time is a key factor that determines the need for the Perform Quantitative Risk Analysis process. A small project with a limited budget may decide to do away with this process if the project management team decides that quantitative statements about risk and impacts are not needed.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 429.
Incorrect
Availability of budget and time is a key factor that determines the need for the Perform Quantitative Risk Analysis process. A small project with a limited budget may decide to do away with this process if the project management team decides that quantitative statements about risk and impacts are not needed.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 429.
Unattempted
Availability of budget and time is a key factor that determines the need for the Perform Quantitative Risk Analysis process. A small project with a limited budget may decide to do away with this process if the project management team decides that quantitative statements about risk and impacts are not needed.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 429.
Question 8 of 65
8. Question
Which of the following is not true in regard to Cost Estimates?
Correct
Cost estimates, which is the main output for the Estimate Costs process generally include management reserve to cover unplanned work.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 246.
Incorrect
Cost estimates, which is the main output for the Estimate Costs process generally include management reserve to cover unplanned work.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 246.
Unattempted
Cost estimates, which is the main output for the Estimate Costs process generally include management reserve to cover unplanned work.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 246.
Question 9 of 65
9. Question
Midway through the project, the project management team decides to reassess few risks which they think are no longer valid. As a part of the which of the following processes risk reassessment is done?
Correct
Risk reassessment is performed as part of the Monitor Risks process. Such project risk reassessments should be regularly scheduled and may result in the closure of outdated risks.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 457.
(The Standard for Risk Management in Portfolios, Programs, and Projects) – Project Management Institute Inc., 2019, Page(s) – 149.
Incorrect
Risk reassessment is performed as part of the Monitor Risks process. Such project risk reassessments should be regularly scheduled and may result in the closure of outdated risks.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 457.
(The Standard for Risk Management in Portfolios, Programs, and Projects) – Project Management Institute Inc., 2019, Page(s) – 149.
Unattempted
Risk reassessment is performed as part of the Monitor Risks process. Such project risk reassessments should be regularly scheduled and may result in the closure of outdated risks.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 457.
(The Standard for Risk Management in Portfolios, Programs, and Projects) – Project Management Institute Inc., 2019, Page(s) – 149.
Question 10 of 65
10. Question
Ryan is a new project manager who has joined the software development project during the mid of execution. He is trying to determine whether the modification of any of the project documents are subject to change request.
What needs to be reviewed to fetch this necessary information?
Correct
A change request must be submitted to update any baseline or the project management plan. Project documents may or not be placed under configuration control depending on the standards outlined in the configuration management plan.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 41, 701.
Incorrect
A change request must be submitted to update any baseline or the project management plan. Project documents may or not be placed under configuration control depending on the standards outlined in the configuration management plan.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 41, 701.
Unattempted
A change request must be submitted to update any baseline or the project management plan. Project documents may or not be placed under configuration control depending on the standards outlined in the configuration management plan.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 41, 701.
Question 11 of 65
11. Question
Arun is the delivery director of new business development program. He has assigned you as the project manager and also assigned other staffs for your project. You want to know more about the project, but all you have received so far was an email from your department manager with little detail about the project. In order to learn more about the project, which of the following options would be your best course of action in this situation?
Correct
Interviews, an example of a data gathering technique of the Develop Project Charter process, can be used to obtain information on high-level requirements, assumptions or constraints, approval criteria and other information from stakeholders by talking to them directly. Although, the question never stated that you have already started the development of the project charter, in this situation, since you know nearly nothing about the project, to better understand the essence of the project, interviewing the director of new business development is the best course of action among all the given choices.
Incorrect
Interviews, an example of a data gathering technique of the Develop Project Charter process, can be used to obtain information on high-level requirements, assumptions or constraints, approval criteria and other information from stakeholders by talking to them directly. Although, the question never stated that you have already started the development of the project charter, in this situation, since you know nearly nothing about the project, to better understand the essence of the project, interviewing the director of new business development is the best course of action among all the given choices.
Unattempted
Interviews, an example of a data gathering technique of the Develop Project Charter process, can be used to obtain information on high-level requirements, assumptions or constraints, approval criteria and other information from stakeholders by talking to them directly. Although, the question never stated that you have already started the development of the project charter, in this situation, since you know nearly nothing about the project, to better understand the essence of the project, interviewing the director of new business development is the best course of action among all the given choices.
Question 12 of 65
12. Question
You are a Project Manager of an engineering project. As a Project Manager, you have confirmed the formal acceptance of all project deliverables. The report that includes summary of the project performance has been prepared. What needs to be reviewed here to fetch the stakeholders list with whom this report needs to be shared?
Correct
The situation states that the Project has entered closing stage and the Final Report is ready. Final report contains the summary of the project performance which should be shared according to what is stated in the Communication Management Plan. This information has been clearly stated in Performance Domain V: Closing – Task 4 of PMBOK outline, that states “Prepare and share the final project report according to the communication management plan in order to document and convey project performance and assist in project evaluation”.
Please see – Performance Domain V: Closing – Task 4
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 127.
Incorrect
The situation states that the Project has entered closing stage and the Final Report is ready. Final report contains the summary of the project performance which should be shared according to what is stated in the Communication Management Plan. This information has been clearly stated in Performance Domain V: Closing – Task 4 of PMBOK outline, that states “Prepare and share the final project report according to the communication management plan in order to document and convey project performance and assist in project evaluation”.
Please see – Performance Domain V: Closing – Task 4
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 127.
Unattempted
The situation states that the Project has entered closing stage and the Final Report is ready. Final report contains the summary of the project performance which should be shared according to what is stated in the Communication Management Plan. This information has been clearly stated in Performance Domain V: Closing – Task 4 of PMBOK outline, that states “Prepare and share the final project report according to the communication management plan in order to document and convey project performance and assist in project evaluation”.
Please see – Performance Domain V: Closing – Task 4
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 127.
Question 13 of 65
13. Question
In a Project status meeting of a project which is in execution, sponsor introduced a new stakeholder. In the meeting, the new person requested for few scope changes in the project.
What should the Project Manager do first?
Correct
Whenever a new member joins the project, the first thing the project manager should do is to add him in Stakeholder Register, there by formally introducing him in the project stakeholder community. Post introduction, all his request can be analyzed or taken care.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 505.
Incorrect
Whenever a new member joins the project, the first thing the project manager should do is to add him in Stakeholder Register, there by formally introducing him in the project stakeholder community. Post introduction, all his request can be analyzed or taken care.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 505.
Unattempted
Whenever a new member joins the project, the first thing the project manager should do is to add him in Stakeholder Register, there by formally introducing him in the project stakeholder community. Post introduction, all his request can be analyzed or taken care.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 505.
Question 14 of 65
14. Question
Ryan is a Project Manager of a construction project which is a part of Cost reimbursable contract. In a meeting with a seller, the seller asked him to share the payment of the cost of items prepared for the project got destroyed in recent thunder storm. What should the Project Manager do next in this situation?
Choose the best answer.
Correct
Option A and Option D are not true, as the Project Manager has to review the contract to take a decision. In case of materialistic loss due natural disaster or fire, Force majeure clause of the contract should be consulted. The clause states in case of “act of nature” situations such as fire, storm, neither parties are judged faulty. In general, it is resolved by seller receiving extension of time on the project. But in this question, seller is asking the buyer to share the cost of loss. So, in this situation, the Project Manager needs to review the “Risk of loss” clause too along with Force majeure clause. Risk of loss clause allocates the risk between the parties to a contract in the event of loss of goods and services during performance of the contract. So, among all options provided, option C is the best answer.
Rita Mulcahy 9th edition, RMC Publications, Inc.,2018, Page -531.
Incorrect
Option A and Option D are not true, as the Project Manager has to review the contract to take a decision. In case of materialistic loss due natural disaster or fire, Force majeure clause of the contract should be consulted. The clause states in case of “act of nature” situations such as fire, storm, neither parties are judged faulty. In general, it is resolved by seller receiving extension of time on the project. But in this question, seller is asking the buyer to share the cost of loss. So, in this situation, the Project Manager needs to review the “Risk of loss” clause too along with Force majeure clause. Risk of loss clause allocates the risk between the parties to a contract in the event of loss of goods and services during performance of the contract. So, among all options provided, option C is the best answer.
Rita Mulcahy 9th edition, RMC Publications, Inc.,2018, Page -531.
Unattempted
Option A and Option D are not true, as the Project Manager has to review the contract to take a decision. In case of materialistic loss due natural disaster or fire, Force majeure clause of the contract should be consulted. The clause states in case of “act of nature” situations such as fire, storm, neither parties are judged faulty. In general, it is resolved by seller receiving extension of time on the project. But in this question, seller is asking the buyer to share the cost of loss. So, in this situation, the Project Manager needs to review the “Risk of loss” clause too along with Force majeure clause. Risk of loss clause allocates the risk between the parties to a contract in the event of loss of goods and services during performance of the contract. So, among all options provided, option C is the best answer.
Rita Mulcahy 9th edition, RMC Publications, Inc.,2018, Page -531.
Question 15 of 65
15. Question
The Project team is involved in determination of the basic underlying reasons for poor stakeholder engagement for few of the key stakeholders.
Which data representation tool can be helpful in this scenario to identify the root cause of the problem by breaking down the causes of the identified problem statement in to discrete branches?
Correct
The scenario states that project team is doing RCA for identifying the reasons in relation to poor stakeholder engagement. RCA is a data analysis technique. In few occasions as stated in the above scenario, findings of RCA can be represented using Fishbone diagrams, also known as Why-Why diagram or Cause and Effect diagrams. This type of diagram breaks down the causes of the problem statement identified into discrete branches, helping to identify the main or root cause of the problem.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 293 ,533.
Incorrect
The scenario states that project team is doing RCA for identifying the reasons in relation to poor stakeholder engagement. RCA is a data analysis technique. In few occasions as stated in the above scenario, findings of RCA can be represented using Fishbone diagrams, also known as Why-Why diagram or Cause and Effect diagrams. This type of diagram breaks down the causes of the problem statement identified into discrete branches, helping to identify the main or root cause of the problem.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 293 ,533.
Unattempted
The scenario states that project team is doing RCA for identifying the reasons in relation to poor stakeholder engagement. RCA is a data analysis technique. In few occasions as stated in the above scenario, findings of RCA can be represented using Fishbone diagrams, also known as Why-Why diagram or Cause and Effect diagrams. This type of diagram breaks down the causes of the problem statement identified into discrete branches, helping to identify the main or root cause of the problem.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 293 ,533.
Question 16 of 65
16. Question
You have been appointed as an auditor for a software development project which has started a year back. Before conducting the audit, you want to review the results of previous audits.
What needs to be reviewed here?
Correct
The situation states that the project manager is planning to do audit which is part of Manage Quality process. Here, OPA, which is also an input for Manage Quality process, needs to be referred as results from previous audits are stored in OPA.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 291.
Incorrect
The situation states that the project manager is planning to do audit which is part of Manage Quality process. Here, OPA, which is also an input for Manage Quality process, needs to be referred as results from previous audits are stored in OPA.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 291.
Unattempted
The situation states that the project manager is planning to do audit which is part of Manage Quality process. Here, OPA, which is also an input for Manage Quality process, needs to be referred as results from previous audits are stored in OPA.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 291.
Question 17 of 65
17. Question
A CEO of a paint manufacturing company involves his senior leadership team to prepare a business case for authorizing a project to establish guidelines for handling toxic materials.
This business case originated as a result of: –
Correct
Establishment of proper guidelines periodically for handling toxic materials is a mandatory legal need which every manufacturer need to follow.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 78.
Incorrect
Establishment of proper guidelines periodically for handling toxic materials is a mandatory legal need which every manufacturer need to follow.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 78.
Unattempted
Establishment of proper guidelines periodically for handling toxic materials is a mandatory legal need which every manufacturer need to follow.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 78.
Question 18 of 65
18. Question
A new risk gets discovered during closing phase of the project.
What should the Project Manager do first?
Correct
A risk can get discovered at any point of time in the project, and all identified risks can be recorded to Risk Register throughout the life cycle of the project, as the process is iterative. B is not correct, because in this situation Risk has been identified, risk has not occurred. C is incorrect, as per PMI ethics it’s the responsibility of the project manager to address such situation at any point in in the project Life cycle. D is incorrect, as Risk management plan has no role here. Here, as per the question, new risk gets discovered during closing, so in this case, the Risk Register should be updated, with information in relation to new risk. Therefore, among all options provided A is the best answer.
Incorrect
A risk can get discovered at any point of time in the project, and all identified risks can be recorded to Risk Register throughout the life cycle of the project, as the process is iterative. B is not correct, because in this situation Risk has been identified, risk has not occurred. C is incorrect, as per PMI ethics it’s the responsibility of the project manager to address such situation at any point in in the project Life cycle. D is incorrect, as Risk management plan has no role here. Here, as per the question, new risk gets discovered during closing, so in this case, the Risk Register should be updated, with information in relation to new risk. Therefore, among all options provided A is the best answer.
Unattempted
A risk can get discovered at any point of time in the project, and all identified risks can be recorded to Risk Register throughout the life cycle of the project, as the process is iterative. B is not correct, because in this situation Risk has been identified, risk has not occurred. C is incorrect, as per PMI ethics it’s the responsibility of the project manager to address such situation at any point in in the project Life cycle. D is incorrect, as Risk management plan has no role here. Here, as per the question, new risk gets discovered during closing, so in this case, the Risk Register should be updated, with information in relation to new risk. Therefore, among all options provided A is the best answer.
Question 19 of 65
19. Question
You are the newly joined Project Manager of an automobile manufacturing company. Senior Management has involved you in the preparation of the Project Charter for their prestigious in-house fuel efficient car project.
What should you do to know the marketplace conditions and current industry standards?
Correct
The question states that the newly joined Project Manager has been involved in the preparation of the project charter of the company’s upcoming internal project. Here, all options are input to the Develop Project Charter process. But the question asked “for the review” of Market conditions and industry standards, which are examples of External Enterprise Environmental factors, because they are outside the control of the Project Team. So among all options provided, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 39, 78.
Incorrect
The question states that the newly joined Project Manager has been involved in the preparation of the project charter of the company’s upcoming internal project. Here, all options are input to the Develop Project Charter process. But the question asked “for the review” of Market conditions and industry standards, which are examples of External Enterprise Environmental factors, because they are outside the control of the Project Team. So among all options provided, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 39, 78.
Unattempted
The question states that the newly joined Project Manager has been involved in the preparation of the project charter of the company’s upcoming internal project. Here, all options are input to the Develop Project Charter process. But the question asked “for the review” of Market conditions and industry standards, which are examples of External Enterprise Environmental factors, because they are outside the control of the Project Team. So among all options provided, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 39, 78.
Question 20 of 65
20. Question
The Work Breakdown Structure(WBS) plays an important role in creation of scope baseline for project planning, execution, and control. The scope baseline serves as an input to many of the project processes.
Which of the following is not true?
Correct
Scope baseline is an input for Quality planning (Plan Quality Management Process), Cost budgeting (Determine Budget process), risk identification (Identify Risk process). So, options A, B, C are not right answers. Whereas Scope baseline is not an input for Planning Cost Management, and developing initial Cost Management Plan. It is later referred for cost estimation which is a part of Estimate Cost process and cost budgeting, part of Determine Budget process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 235,248,277,409.
Incorrect
Scope baseline is an input for Quality planning (Plan Quality Management Process), Cost budgeting (Determine Budget process), risk identification (Identify Risk process). So, options A, B, C are not right answers. Whereas Scope baseline is not an input for Planning Cost Management, and developing initial Cost Management Plan. It is later referred for cost estimation which is a part of Estimate Cost process and cost budgeting, part of Determine Budget process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 235,248,277,409.
Unattempted
Scope baseline is an input for Quality planning (Plan Quality Management Process), Cost budgeting (Determine Budget process), risk identification (Identify Risk process). So, options A, B, C are not right answers. Whereas Scope baseline is not an input for Planning Cost Management, and developing initial Cost Management Plan. It is later referred for cost estimation which is a part of Estimate Cost process and cost budgeting, part of Determine Budget process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 235,248,277,409.
Question 21 of 65
21. Question
Ryan is the Project Manager of Qnx organization. He has been awarded an internal project for building new payroll processing system for his company. One of the main project objectives include automation of few of the current processes that is being done manually as of today.
What is the best tool to use in this situation?
Correct
Cost-Benefit analysis is a financial analysis tool used to estimate the strengths and weaknesses of the alternatives, as automation in this case , in order to determine the best alternatives in terms of the benefits provided. It helps the Project Manager to determine if planned quality activities are cost-effective.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 282.
Incorrect
Cost-Benefit analysis is a financial analysis tool used to estimate the strengths and weaknesses of the alternatives, as automation in this case , in order to determine the best alternatives in terms of the benefits provided. It helps the Project Manager to determine if planned quality activities are cost-effective.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 282.
Unattempted
Cost-Benefit analysis is a financial analysis tool used to estimate the strengths and weaknesses of the alternatives, as automation in this case , in order to determine the best alternatives in terms of the benefits provided. It helps the Project Manager to determine if planned quality activities are cost-effective.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 282.
Question 22 of 65
22. Question
Conflict is an inevitable consequence of an organizational interactions. Which of the following practices can reduce the amount of conflict within a team?
Choose the Best answer.
Correct
Team ground rules mean the expected behavior for project team members among one another during the course of the project. Setting ground rules, group norms can definitely reduce conflict, as team needs to follow specific guidelines.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 348.
Incorrect
Team ground rules mean the expected behavior for project team members among one another during the course of the project. Setting ground rules, group norms can definitely reduce conflict, as team needs to follow specific guidelines.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 348.
Unattempted
Team ground rules mean the expected behavior for project team members among one another during the course of the project. Setting ground rules, group norms can definitely reduce conflict, as team needs to follow specific guidelines.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 348.
Question 23 of 65
23. Question
The following process may confirm the risk owners for individual project risks and is performed regularly throughout the life cycle of the project, as defined in Risk Management plan. Sometimes, it’s being conducted in Agile projects before the start of each iteration.
What process has been referred in the scenario mentioned above?
Correct
Risk owners for individual project risks may be nominated in Identify risks process and confirmed in Perform Qualitative Risk analysis process. The process is performed throughout the life cycle of the project, as defined in Risk Management Plan. Often in project with adaptive development approach, its being conducted before the iteration begins.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 411, 421.
Incorrect
Risk owners for individual project risks may be nominated in Identify risks process and confirmed in Perform Qualitative Risk analysis process. The process is performed throughout the life cycle of the project, as defined in Risk Management Plan. Often in project with adaptive development approach, its being conducted before the iteration begins.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 411, 421.
Unattempted
Risk owners for individual project risks may be nominated in Identify risks process and confirmed in Perform Qualitative Risk analysis process. The process is performed throughout the life cycle of the project, as defined in Risk Management Plan. Often in project with adaptive development approach, its being conducted before the iteration begins.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 411, 421.
Question 24 of 65
24. Question
During Phase Gate, the project performance and progress are compared to all of the following documents Except:
Correct
Phase gate is held at the end of a phase. During Phase Gate, the project performance and progress are compared to project and business documents that include: – Business Case, Benefit Management Plan, Project Charter, Project Management Plan. So, among all the options provided, Procurement Documentation is the correct choice.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 21.
Incorrect
Phase gate is held at the end of a phase. During Phase Gate, the project performance and progress are compared to project and business documents that include: – Business Case, Benefit Management Plan, Project Charter, Project Management Plan. So, among all the options provided, Procurement Documentation is the correct choice.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 21.
Unattempted
Phase gate is held at the end of a phase. During Phase Gate, the project performance and progress are compared to project and business documents that include: – Business Case, Benefit Management Plan, Project Charter, Project Management Plan. So, among all the options provided, Procurement Documentation is the correct choice.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 21.
Question 25 of 65
25. Question
Ryan is a newly joined Project Manager of a large, multi-phase software development project. In his first status review meeting, few key stakeholders raised concern on the status of the change requests raised by them, as most of their requests are either deferred or in rejected state.
What should the Project Manager do next?
Correct
The disposition of all the Change Requests are recorded in Change Log as a project document update. Since the details of all approved, deferred, and rejected change requests are stored in change log, Project Manager should review the change log first. Option A and Option D are also good options, but those should be considered after reviewing the Change log. So, among all options provided, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 120.
Incorrect
The disposition of all the Change Requests are recorded in Change Log as a project document update. Since the details of all approved, deferred, and rejected change requests are stored in change log, Project Manager should review the change log first. Option A and Option D are also good options, but those should be considered after reviewing the Change log. So, among all options provided, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 120.
Unattempted
The disposition of all the Change Requests are recorded in Change Log as a project document update. Since the details of all approved, deferred, and rejected change requests are stored in change log, Project Manager should review the change log first. Option A and Option D are also good options, but those should be considered after reviewing the Change log. So, among all options provided, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 120.
Question 26 of 65
26. Question
Ryan is a Project Manager of a large multi-year project that is being executed using agile development approach. Project Team has used bottom-up estimation technique for project work related to all near term releases and for all future releases you have created a list of work breakdown structure components above the work package level with known work content but without detailed schedule activities.
What tool or technique the project team has used in the given scenario?
Choose the Best Answer.
Correct
As per the above scenario detailed planning is available for project work that need to be executed in near term. This can be assumed because the Project team used Bottom-up estimation technique, which can only be done when work breakdown structure components are decomposed into more detail. Question also states for all future releases only planning packages are planned (Hint: The statement in the question “work breakdown structure components above the work package level with known work content but without detailed schedule activities” signifies the definition of planning packages). This confirms Project has used Rolling Wave Planning technique. As per definition, Rolling wave planning is an iterative planning process which will allow near-term activities to be planned in detail while leaving activities further out planned at a higher level. So among all options provided D is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 160,185, 721.
Incorrect
As per the above scenario detailed planning is available for project work that need to be executed in near term. This can be assumed because the Project team used Bottom-up estimation technique, which can only be done when work breakdown structure components are decomposed into more detail. Question also states for all future releases only planning packages are planned (Hint: The statement in the question “work breakdown structure components above the work package level with known work content but without detailed schedule activities” signifies the definition of planning packages). This confirms Project has used Rolling Wave Planning technique. As per definition, Rolling wave planning is an iterative planning process which will allow near-term activities to be planned in detail while leaving activities further out planned at a higher level. So among all options provided D is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 160,185, 721.
Unattempted
As per the above scenario detailed planning is available for project work that need to be executed in near term. This can be assumed because the Project team used Bottom-up estimation technique, which can only be done when work breakdown structure components are decomposed into more detail. Question also states for all future releases only planning packages are planned (Hint: The statement in the question “work breakdown structure components above the work package level with known work content but without detailed schedule activities” signifies the definition of planning packages). This confirms Project has used Rolling Wave Planning technique. As per definition, Rolling wave planning is an iterative planning process which will allow near-term activities to be planned in detail while leaving activities further out planned at a higher level. So among all options provided D is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 160,185, 721.
Question 27 of 65
27. Question
Ryan is a Project Manager of an IT project. He is currently preparing a report for senior management that would show resource requirements by time period and applied schedule reserves.
What needs to be reviewed in this scenario?
Correct
The Schedule data for the project schedule model is the collection of information for describing and controlling the schedule. It contains resource requirements by time periods, often displayed in the form of a resource histogram. It also contains alternative schedules like Best-Case or Worst-Case scenarios. As per the question stated above, best thing the project manager can do is reviewing the Schedule Data.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 220.
Incorrect
The Schedule data for the project schedule model is the collection of information for describing and controlling the schedule. It contains resource requirements by time periods, often displayed in the form of a resource histogram. It also contains alternative schedules like Best-Case or Worst-Case scenarios. As per the question stated above, best thing the project manager can do is reviewing the Schedule Data.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 220.
Unattempted
The Schedule data for the project schedule model is the collection of information for describing and controlling the schedule. It contains resource requirements by time periods, often displayed in the form of a resource histogram. It also contains alternative schedules like Best-Case or Worst-Case scenarios. As per the question stated above, best thing the project manager can do is reviewing the Schedule Data.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 220.
Question 28 of 65
28. Question
An automobile manufacturer initiated a project to build more fuel efficient cars in response to gasoline shortages. Project Initiation is complete and several experts have gathered to identify the areas required to be taken care while building the best fuel efficient car. They are comparing specifications of popular branded fuel efficient cars available in the market with their planned product.
What tools and technique has been used in this scenario?
Correct
As per given scenario, experts are involved in Benchmarking while doing planning. Benchmarking is a data gathering tool used in quality planning and requirement gathering. It involves comparing actual or planned products, processes, and practices to those of comparable organizations to identify best practices, generate ideas for improvement, and provide a basis for measuring performance.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 143.
Incorrect
As per given scenario, experts are involved in Benchmarking while doing planning. Benchmarking is a data gathering tool used in quality planning and requirement gathering. It involves comparing actual or planned products, processes, and practices to those of comparable organizations to identify best practices, generate ideas for improvement, and provide a basis for measuring performance.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 143.
Unattempted
As per given scenario, experts are involved in Benchmarking while doing planning. Benchmarking is a data gathering tool used in quality planning and requirement gathering. It involves comparing actual or planned products, processes, and practices to those of comparable organizations to identify best practices, generate ideas for improvement, and provide a basis for measuring performance.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 143.
Question 29 of 65
29. Question
Ryan is a Project Manager handling a Telecom equipment manufacturing project. During a project performance review with team, he notices the following: (a) Activity A, on the critical path, is delayed by 4 days. (b) Activity B, not on the critical path, is delayed by 9 days. (c) Activity C, on the critical path is delayed by 2 days (d) Activity D, not on the critical path, is delayed by 6 days.
In what sequence should the Project Manager and the team prioritize their efforts in addressing these delays?
Correct
Tasks on Critical path should be addressed first, else it may impact the project schedule. Here, of all choices provided, C is the most reasonable choice.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 210.
Incorrect
Tasks on Critical path should be addressed first, else it may impact the project schedule. Here, of all choices provided, C is the most reasonable choice.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 210.
Unattempted
Tasks on Critical path should be addressed first, else it may impact the project schedule. Here, of all choices provided, C is the most reasonable choice.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 210.
Question 30 of 65
30. Question
As a Project Manager, you are trying to determine project deliverables which are subject to quality review.
What needs to be reviewed here?
Correct
The Quality Management Plan, the component of Project Management Plan determines Project deliverables and processes subject to quality review. Among all the given choices, since the option Quality Management Plan is not there, Selection of option D i.e. Project Management Plan is the best choice.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 286.
*** Expect these kind of questions in exam.***
Incorrect
The Quality Management Plan, the component of Project Management Plan determines Project deliverables and processes subject to quality review. Among all the given choices, since the option Quality Management Plan is not there, Selection of option D i.e. Project Management Plan is the best choice.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 286.
*** Expect these kind of questions in exam.***
Unattempted
The Quality Management Plan, the component of Project Management Plan determines Project deliverables and processes subject to quality review. Among all the given choices, since the option Quality Management Plan is not there, Selection of option D i.e. Project Management Plan is the best choice.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 286.
*** Expect these kind of questions in exam.***
Question 31 of 65
31. Question
The Project Team along with few experts are currently involved in reviewing historical information from similar past projects that would assist them in developing parametric or analogous estimates.
What tools or technique has been applied in the given scenario?
Correct
Few may get confused with OPA, but OPA is an input, not tools or techniques. Historical information review, a technique used in Budget determination can assist in developing parametric or analogous estimates. It may include project characteristics(parameters) to develop mathematical model to predict total project costs.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 253.
Incorrect
Few may get confused with OPA, but OPA is an input, not tools or techniques. Historical information review, a technique used in Budget determination can assist in developing parametric or analogous estimates. It may include project characteristics(parameters) to develop mathematical model to predict total project costs.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 253.
Unattempted
Few may get confused with OPA, but OPA is an input, not tools or techniques. Historical information review, a technique used in Budget determination can assist in developing parametric or analogous estimates. It may include project characteristics(parameters) to develop mathematical model to predict total project costs.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 253.
Question 32 of 65
32. Question
You are a Project Manager of RPA project. During the early stage of execution, it came to your notice that, the training is required for technical team to build a quality product.
Here training is an example of: –
Correct
Sunk cost, means Cost that is incurred cannot be recovered, So D is not correct. C is an example of Cost of Non-conformance, but question talks about Cost of Conformance, so C is also incorrect. A and B are examples of Cost of Conformance, but the question states that “the training is required for technical team to build a quality product”, but appraisal costs help to assess the quality, So A is also not correct. Preventive cost is a classic example for Cost of Conformance and it helps to build a quality product. The examples for Preventive costs include, training, document process, equipment, Time to do it right. So, among all options provided B is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 283.
Incorrect
Sunk cost, means Cost that is incurred cannot be recovered, So D is not correct. C is an example of Cost of Non-conformance, but question talks about Cost of Conformance, so C is also incorrect. A and B are examples of Cost of Conformance, but the question states that “the training is required for technical team to build a quality product”, but appraisal costs help to assess the quality, So A is also not correct. Preventive cost is a classic example for Cost of Conformance and it helps to build a quality product. The examples for Preventive costs include, training, document process, equipment, Time to do it right. So, among all options provided B is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 283.
Unattempted
Sunk cost, means Cost that is incurred cannot be recovered, So D is not correct. C is an example of Cost of Non-conformance, but question talks about Cost of Conformance, so C is also incorrect. A and B are examples of Cost of Conformance, but the question states that “the training is required for technical team to build a quality product”, but appraisal costs help to assess the quality, So A is also not correct. Preventive cost is a classic example for Cost of Conformance and it helps to build a quality product. The examples for Preventive costs include, training, document process, equipment, Time to do it right. So, among all options provided B is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 283.
Question 33 of 65
33. Question
All baseline documents are approved. The Project management team is engaged in reviewing documents that guides the selection of internal and external resources necessary to complete the project work.
Which process is currently getting performed in the mentioned scenario?
Correct
The scenario states that the Acquire Resources process is getting performed and the project management team is engaged in reviewing resource and procurement management plan, so that resources can be on boarded to complete the project work. Both Resource Management Plan and Procurement Management plans are input to the Acquire Resources process, which is being reviewed in this scenario.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 328- 330.
Incorrect
The scenario states that the Acquire Resources process is getting performed and the project management team is engaged in reviewing resource and procurement management plan, so that resources can be on boarded to complete the project work. Both Resource Management Plan and Procurement Management plans are input to the Acquire Resources process, which is being reviewed in this scenario.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 328- 330.
Unattempted
The scenario states that the Acquire Resources process is getting performed and the project management team is engaged in reviewing resource and procurement management plan, so that resources can be on boarded to complete the project work. Both Resource Management Plan and Procurement Management plans are input to the Acquire Resources process, which is being reviewed in this scenario.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 328- 330.
Question 34 of 65
34. Question
In a Research and Development project, several experts have gathered in a focus group session to model the key relationships and dependencies in order to determine areas of maximum uncertainty on overall project objectives. A risk diagramming technique is being used in the given scenario and a S-curve has been produced as an output.
Which tool has been used in the given scenario?
Correct
The situation states that the experts have gathered to determine the areas of maximum uncertainty over all project objectives, which means, Perform Quantitative Risk Analysis is being performed here. Influence diagram is an example of Risk Diagramming technique that’s been used as a tool in the Perform Quantitative Risk Analysis process to address similar situations as stated above. Influence diagrams are graphical aids to decision making under uncertainty. It represents project or situations within a project as a set of entities, outcomes, and influences, together with relationships and effects between them.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 436.
Incorrect
The situation states that the experts have gathered to determine the areas of maximum uncertainty over all project objectives, which means, Perform Quantitative Risk Analysis is being performed here. Influence diagram is an example of Risk Diagramming technique that’s been used as a tool in the Perform Quantitative Risk Analysis process to address similar situations as stated above. Influence diagrams are graphical aids to decision making under uncertainty. It represents project or situations within a project as a set of entities, outcomes, and influences, together with relationships and effects between them.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 436.
Unattempted
The situation states that the experts have gathered to determine the areas of maximum uncertainty over all project objectives, which means, Perform Quantitative Risk Analysis is being performed here. Influence diagram is an example of Risk Diagramming technique that’s been used as a tool in the Perform Quantitative Risk Analysis process to address similar situations as stated above. Influence diagrams are graphical aids to decision making under uncertainty. It represents project or situations within a project as a set of entities, outcomes, and influences, together with relationships and effects between them.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 436.
Question 35 of 65
35. Question
The work of a particular work package on a niche technology is very important for the Project Manager, since CEO of the buyer company will review the verified deliverables of the same, and if he gets satisfied with the outcome, company can earn more business on similar application area. There is one experienced and expert resource, which is available from next week. Since a week delay will not impact the project schedule, the project manager adjusts the start and end date of the work package based on the availability of the experienced worker.
What risk response strategy has been applied in the given scenario?
Correct
The exploit strategy may be selected for high priority opportunities where the organization wants to ensure that the opportunity is realized. In the question, as per the scenario, by moving the work package to a date when the more experienced resource is available, thereby increasing the probability of occurrence to 100 percent, is an example for Exploit strategy.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 444.
Incorrect
The exploit strategy may be selected for high priority opportunities where the organization wants to ensure that the opportunity is realized. In the question, as per the scenario, by moving the work package to a date when the more experienced resource is available, thereby increasing the probability of occurrence to 100 percent, is an example for Exploit strategy.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 444.
Unattempted
The exploit strategy may be selected for high priority opportunities where the organization wants to ensure that the opportunity is realized. In the question, as per the scenario, by moving the work package to a date when the more experienced resource is available, thereby increasing the probability of occurrence to 100 percent, is an example for Exploit strategy.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 444.
Question 36 of 65
36. Question
In relation to performance of a recently manufactured deliverable that will go for customer inspection next week, control chart has determined two data points outside upper specification limit but within Upper control limit. Rest of the data points are within control and specification limits.
What should the Project Manager do next?
Correct
Control limits represent the performing organizations standards for quality, while specification limits represent customer’s expectations or the contractual requirements for the performance or the quality on the project. In general, most of the projects keep Control limits lower than customer specified limits for meeting customer need. As per the question, the process is stable as per quality standard of the performing organization. But it’s not acceptable from customer point of expectations. So among all options provided, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 304.
Incorrect
Control limits represent the performing organizations standards for quality, while specification limits represent customer’s expectations or the contractual requirements for the performance or the quality on the project. In general, most of the projects keep Control limits lower than customer specified limits for meeting customer need. As per the question, the process is stable as per quality standard of the performing organization. But it’s not acceptable from customer point of expectations. So among all options provided, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 304.
Unattempted
Control limits represent the performing organizations standards for quality, while specification limits represent customer’s expectations or the contractual requirements for the performance or the quality on the project. In general, most of the projects keep Control limits lower than customer specified limits for meeting customer need. As per the question, the process is stable as per quality standard of the performing organization. But it’s not acceptable from customer point of expectations. So among all options provided, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 304.
Question 37 of 65
37. Question
The Project Team is involved in developing actionable plan to interact effectively with stakeholders.
What can guide them with information regarding roles and responsibilities of the team members and other stakeholders listed in the stakeholder register?
Correct
As per the question, the project team is involved in Plan Stakeholder Engagement process, and all 4 options are input to the process. But, it’s the Resource Management Plan, which may contain information regarding roles and responsibilities of the team members and other stakeholders listed in the stakeholder register.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 518.
Incorrect
As per the question, the project team is involved in Plan Stakeholder Engagement process, and all 4 options are input to the process. But, it’s the Resource Management Plan, which may contain information regarding roles and responsibilities of the team members and other stakeholders listed in the stakeholder register.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 518.
Unattempted
As per the question, the project team is involved in Plan Stakeholder Engagement process, and all 4 options are input to the process. But, it’s the Resource Management Plan, which may contain information regarding roles and responsibilities of the team members and other stakeholders listed in the stakeholder register.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 518.
Question 38 of 65
38. Question
You are a Project Manager of the Software Development project. An external expert has been involved to review the defects found in last customer inspection. He conducted the process of translating the quality Management plan into executable quality activities and used a tool to graphically represent number of defects per deliverable, and the number of times each process became non-compliant.
What tool has been used in this scenario?
Correct
The scenario suggests that the Project Manager has involved an external auditor to review the causes of defects found in last Customer inspection. The auditor in this case conducted the Manage Quality process and used a tool for graphical representation of defects per deliverable. Histogram is the tool used for Manage Quality process for graphical representation of numeric data. It can show number of defects per deliverable, and the number of times each process became non-compliant. So among all options provided A is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 293, 304.
Incorrect
The scenario suggests that the Project Manager has involved an external auditor to review the causes of defects found in last Customer inspection. The auditor in this case conducted the Manage Quality process and used a tool for graphical representation of defects per deliverable. Histogram is the tool used for Manage Quality process for graphical representation of numeric data. It can show number of defects per deliverable, and the number of times each process became non-compliant. So among all options provided A is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 293, 304.
Unattempted
The scenario suggests that the Project Manager has involved an external auditor to review the causes of defects found in last Customer inspection. The auditor in this case conducted the Manage Quality process and used a tool for graphical representation of defects per deliverable. Histogram is the tool used for Manage Quality process for graphical representation of numeric data. It can show number of defects per deliverable, and the number of times each process became non-compliant. So among all options provided A is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 293, 304.
Question 39 of 65
39. Question
In a project that had several conflicts, most the time the Project Manager used his positional power to resolve most of the conflicts, as quick resolutions were required in most of the circumstances.
What conflict management technique has been referred in the given scenario?
Correct
As per the scenario stated above, the project manager applied Forcing approach to resolve conflicts in a quick frame of time. Forcing is the conflict resolution technique that involves pushing one’s viewpoint at the expense of others and mostly offers only win-lose solutions. In general, positional power is used to apply such strategy. So, among all options provided B is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 349.
Incorrect
As per the scenario stated above, the project manager applied Forcing approach to resolve conflicts in a quick frame of time. Forcing is the conflict resolution technique that involves pushing one’s viewpoint at the expense of others and mostly offers only win-lose solutions. In general, positional power is used to apply such strategy. So, among all options provided B is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 349.
Unattempted
As per the scenario stated above, the project manager applied Forcing approach to resolve conflicts in a quick frame of time. Forcing is the conflict resolution technique that involves pushing one’s viewpoint at the expense of others and mostly offers only win-lose solutions. In general, positional power is used to apply such strategy. So, among all options provided B is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 349.
Question 40 of 65
40. Question
During planning, the project team is using a technique to assess communication styles and identify the preferred communication method, format and content for planned communication activities.
Which process is being carried out in the given scenario?
Correct
As per the stated scenario, the Project Team, here, is applying Communications styles assessment technique which is a common Interpersonal and Team Skills technique used during planning communications. A, B, D are incorrect, because the Communications Styles Assessment techniques are not used in these processes. So, among all options provided, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 375.
Incorrect
As per the stated scenario, the Project Team, here, is applying Communications styles assessment technique which is a common Interpersonal and Team Skills technique used during planning communications. A, B, D are incorrect, because the Communications Styles Assessment techniques are not used in these processes. So, among all options provided, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 375.
Unattempted
As per the stated scenario, the Project Team, here, is applying Communications styles assessment technique which is a common Interpersonal and Team Skills technique used during planning communications. A, B, D are incorrect, because the Communications Styles Assessment techniques are not used in these processes. So, among all options provided, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 375.
Question 41 of 65
41. Question
Ryan is a Project Manager of a complex Cloud Infrastructure migration project of a leading manufacturing company. During the mid of the project, the company got merged with another manufacturing company as a result of which company name and its policies got revised. Now the project is ready to move to Business realization phase and customer has formally accepted the project outcome.
What should the Project Manager do next to start the closure process?
Correct
The question states that the project is ready to move to operation (Business Realization phase) which implies that the project manager should start the closure procedure. Since the company got merged in recent past, most likely there should be few changes in company’s OPA. On top of it, OPA is an input for Close Project/phase process which contain project closure guidelines or requirements. Organization Process Assets include the corporate policies and procedures which the project manager should follow for formal project closure.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 126.
Incorrect
The question states that the project is ready to move to operation (Business Realization phase) which implies that the project manager should start the closure procedure. Since the company got merged in recent past, most likely there should be few changes in company’s OPA. On top of it, OPA is an input for Close Project/phase process which contain project closure guidelines or requirements. Organization Process Assets include the corporate policies and procedures which the project manager should follow for formal project closure.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 126.
Unattempted
The question states that the project is ready to move to operation (Business Realization phase) which implies that the project manager should start the closure procedure. Since the company got merged in recent past, most likely there should be few changes in company’s OPA. On top of it, OPA is an input for Close Project/phase process which contain project closure guidelines or requirements. Organization Process Assets include the corporate policies and procedures which the project manager should follow for formal project closure.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 126.
Question 42 of 65
42. Question
Project team is currently involved in the analysis and review of a Change Request raised by an important stakeholder, that needs to be implemented within next 3 weeks. Project Manager asked team to check the earn value graph, Burn-down chart along with information on resource availability to estimate whether the proposed Change Request can be implemented within the proposed timeline.
What should the Project team do NEXT?
Correct
Here in this scenario, the project team is involved in Perform Integrated Change Control process of which Work Performance Report is an input. Work Performance Report include resource availability, schedule and cost data, earned value reports, and Burn-up or Burn-down charts.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 116.
Incorrect
Here in this scenario, the project team is involved in Perform Integrated Change Control process of which Work Performance Report is an input. Work Performance Report include resource availability, schedule and cost data, earned value reports, and Burn-up or Burn-down charts.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 116.
Unattempted
Here in this scenario, the project team is involved in Perform Integrated Change Control process of which Work Performance Report is an input. Work Performance Report include resource availability, schedule and cost data, earned value reports, and Burn-up or Burn-down charts.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 116.
Question 43 of 65
43. Question
Ryan is a project Manager of fixed price project. Currently, the Project team is having a meeting with few key stakeholders where approval of final scope of the work would be finalized. Stakeholders discovered that there are few work packages which are actually not required and nor these requirements are mentioned in the contract.
What went wrong in this scenario? Choose the best answer
Correct
The Project Scope Statement includes Project Scope, major deliverables, acceptance criteria and Project exclusions. As per the question, Project team is engaged in Scope baseline approval meeting, where stakeholders discovered that some out of scope requirements have been added in the Project scope. So, among all options given above, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 154.
Incorrect
The Project Scope Statement includes Project Scope, major deliverables, acceptance criteria and Project exclusions. As per the question, Project team is engaged in Scope baseline approval meeting, where stakeholders discovered that some out of scope requirements have been added in the Project scope. So, among all options given above, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 154.
Unattempted
The Project Scope Statement includes Project Scope, major deliverables, acceptance criteria and Project exclusions. As per the question, Project team is engaged in Scope baseline approval meeting, where stakeholders discovered that some out of scope requirements have been added in the Project scope. So, among all options given above, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 154.
Question 44 of 65
44. Question
The total estimated Project Cost is: –
Correct
BAC or PMB is the approved project budget that has been baselined during planning. So A and D are incorrect answers. ETC gives an approximate idea of how much money will be required to complete the remaining balance of work. So C is incorrect. The estimated project budget is your latest cost estimate or forecast , represented by EAC (Estimate At Completion). So, B is the correct answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 264,265.
Incorrect
BAC or PMB is the approved project budget that has been baselined during planning. So A and D are incorrect answers. ETC gives an approximate idea of how much money will be required to complete the remaining balance of work. So C is incorrect. The estimated project budget is your latest cost estimate or forecast , represented by EAC (Estimate At Completion). So, B is the correct answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 264,265.
Unattempted
BAC or PMB is the approved project budget that has been baselined during planning. So A and D are incorrect answers. ETC gives an approximate idea of how much money will be required to complete the remaining balance of work. So C is incorrect. The estimated project budget is your latest cost estimate or forecast , represented by EAC (Estimate At Completion). So, B is the correct answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 264,265.
Question 45 of 65
45. Question
In a project planning meeting, Project team decides to change the project management plan in order to get rid of a high probability risk.
What does this signify in relation to risk management?
Correct
The question implies that the project team is trying to get rid of a possible threat by changing the Project Management Plan, which is an example of Risk avoidance. People may get confused between option A and B. But option A looks a better answer. Further, option B talks about a known risk, which is not correct. A risk can be Known-Unknown or Unknown-Unknown. So, among all options provided A is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 443.
Incorrect
The question implies that the project team is trying to get rid of a possible threat by changing the Project Management Plan, which is an example of Risk avoidance. People may get confused between option A and B. But option A looks a better answer. Further, option B talks about a known risk, which is not correct. A risk can be Known-Unknown or Unknown-Unknown. So, among all options provided A is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 443.
Unattempted
The question implies that the project team is trying to get rid of a possible threat by changing the Project Management Plan, which is an example of Risk avoidance. People may get confused between option A and B. But option A looks a better answer. Further, option B talks about a known risk, which is not correct. A risk can be Known-Unknown or Unknown-Unknown. So, among all options provided A is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 443.
Question 46 of 65
46. Question
During planning, two team members have disagreement on addition of one of the Solution requirements in Project Scope Statement. According to one team member if the requirement gets added, it will be beneficial for the project later on. But other team member says addition of such requirement would increase ambiguity risks of the project that why, it’s better to keep it in the project exclusion list. Project Scope Statement needs to be finalized soon, so both the team members reach out to Project Manager for expert opinion. The Project manager after reviewing everything said “It’s good to see that both of you have agreed the majority of the contents of the Project Scope Statement, let’s make it final as of now. In regard to this particular requirement, let discuss with sponsor post Phase 1”.
Which of the following conflict-resolution techniques the Project Manager applied over here?
Correct
Smoothing, also known as accommodating, emphasizes areas of agreement rather than areas of difference. Here the Project Manager applied the smoothing technique.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 349.
Incorrect
Smoothing, also known as accommodating, emphasizes areas of agreement rather than areas of difference. Here the Project Manager applied the smoothing technique.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 349.
Unattempted
Smoothing, also known as accommodating, emphasizes areas of agreement rather than areas of difference. Here the Project Manager applied the smoothing technique.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 349.
Question 47 of 65
47. Question
A long awaited Research and development project is on the verge of closure. Sponsor and Global Delivery Head of the buyer organization congratulates the Project Manager of the performing organization. The team asks the Project Manager to throw a glamorous party.
Which of the following statements given below ensures that the contract can be considered as complete?
Correct
This is a classic example of tricky Closing question where hint is there in the last line of question. The question talks about contract Closure not Project Closure. So, Option B and D are not correct since those are performed during Closing. Option A talks about Validate Scope process, where project deliverables are formally accepted, but that does not ensure closure of contract. Contract closure is part of Control Procurements process where seller is provided with a formal notice that Contract is complete. So, among all the provided options, option C can be the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 499.
Incorrect
This is a classic example of tricky Closing question where hint is there in the last line of question. The question talks about contract Closure not Project Closure. So, Option B and D are not correct since those are performed during Closing. Option A talks about Validate Scope process, where project deliverables are formally accepted, but that does not ensure closure of contract. Contract closure is part of Control Procurements process where seller is provided with a formal notice that Contract is complete. So, among all the provided options, option C can be the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 499.
Unattempted
This is a classic example of tricky Closing question where hint is there in the last line of question. The question talks about contract Closure not Project Closure. So, Option B and D are not correct since those are performed during Closing. Option A talks about Validate Scope process, where project deliverables are formally accepted, but that does not ensure closure of contract. Contract closure is part of Control Procurements process where seller is provided with a formal notice that Contract is complete. So, among all the provided options, option C can be the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 499.
Question 48 of 65
48. Question
You are a project Manager of a mid-sized RPA project. The project planning is complete and the scope is well defined. The first list work packages were scheduled to be completed by the end of April, but it is now end of May, and the work has not yet started because it is taking longer than expected time to hire the technical consultants.
At this point, which of the following is not TRUE?
Correct
At this point, the project should have started, but has not. It is behind schedule, but no money has been spent yet. As a result, PV is positive but EV and AC are Zero. SV = EV – PV = – PV (Negative value of PV). CV = EV – AC = 0 SPI = EV/PV = 0/Value = 0. Some of these conditions are unusual. Normally, SPI would not equal CV, but in this case, both are equal to zero (ignoring the units of measure). Since, CV is zero, Option C is the correct answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 499.
Incorrect
At this point, the project should have started, but has not. It is behind schedule, but no money has been spent yet. As a result, PV is positive but EV and AC are Zero. SV = EV – PV = – PV (Negative value of PV). CV = EV – AC = 0 SPI = EV/PV = 0/Value = 0. Some of these conditions are unusual. Normally, SPI would not equal CV, but in this case, both are equal to zero (ignoring the units of measure). Since, CV is zero, Option C is the correct answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 499.
Unattempted
At this point, the project should have started, but has not. It is behind schedule, but no money has been spent yet. As a result, PV is positive but EV and AC are Zero. SV = EV – PV = – PV (Negative value of PV). CV = EV – AC = 0 SPI = EV/PV = 0/Value = 0. Some of these conditions are unusual. Normally, SPI would not equal CV, but in this case, both are equal to zero (ignoring the units of measure). Since, CV is zero, Option C is the correct answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 499.
Question 49 of 65
49. Question
Ryan is a project manager of a software development project which has gone behind schedule as 2 Testers has suddenly resigned and they are unreachable. Team after reviewing all Planning documents decided to introduce Automated testing instead of manual testing for few tasks on critical path. However, this decision would add two more servers in the project Infrastructure landscape and network may not have adequate capacity to handle the extra load of these two servers, which may impact the testing.
What is the type of risk mentioned in the above scenario?
Correct
Answer – A. A secondary risk arises as a direct result of implementing a risk response. Here as the question states, Team has decided to implement a planned risk response of doing automated testing. (PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 439.
Incorrect
Answer – A. A secondary risk arises as a direct result of implementing a risk response. Here as the question states, Team has decided to implement a planned risk response of doing automated testing. (PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 439.
Unattempted
Answer – A. A secondary risk arises as a direct result of implementing a risk response. Here as the question states, Team has decided to implement a planned risk response of doing automated testing. (PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 439.
Question 50 of 65
50. Question
The Project Manager of the Buyer organization is not convinced with the cost estimates provided by the perspective sellers for company’s upcoming construction project. After meeting with sponsor, the project manager decides to award the contract to one of the preferred sellers with a clause that seller has to provide all details of their legitimate direct costs that will be incurred during the life cycle of the contract for final invoice payment. The contract also states that the buyer organization will pay a fee of $ 6,000 regardless to the invoiced cost.
What type of contract has been awarded in the above scenario?
Correct
The question here talks about CPFF contract, where seller has to provide the actual invoices for payment. In addition, they get a fixed fee as their profit amount.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 472.
Incorrect
The question here talks about CPFF contract, where seller has to provide the actual invoices for payment. In addition, they get a fixed fee as their profit amount.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 472.
Unattempted
The question here talks about CPFF contract, where seller has to provide the actual invoices for payment. In addition, they get a fixed fee as their profit amount.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 472.
Question 51 of 65
51. Question
Two developers are about to start implementing two different Approved change requests, as directed by the project manager.
What tool should assist the team members to know the list of authorized tasks they need to perform?
Correct
The question states that the project manager has asked two team members to perform the Direct and Manage Project Work process. Of the options provided, project management information system (PMIS) is the only tool or technique listed. The change log and WBS are inputs to the process, while work performance data is an output. The tool, that actually team members are required to refer here is the Work Authorization system which is actually a sub-system of PMIS.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 95.
Incorrect
The question states that the project manager has asked two team members to perform the Direct and Manage Project Work process. Of the options provided, project management information system (PMIS) is the only tool or technique listed. The change log and WBS are inputs to the process, while work performance data is an output. The tool, that actually team members are required to refer here is the Work Authorization system which is actually a sub-system of PMIS.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 95.
Unattempted
The question states that the project manager has asked two team members to perform the Direct and Manage Project Work process. Of the options provided, project management information system (PMIS) is the only tool or technique listed. The change log and WBS are inputs to the process, while work performance data is an output. The tool, that actually team members are required to refer here is the Work Authorization system which is actually a sub-system of PMIS.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 95.
Question 52 of 65
52. Question
Which of the following interpersonal skills would help the Project Manager to plan communications based on the project environment as well as official environment of the organization?
Correct
Political awareness helps the project manager to plan communications based on the Project environment as well as the organization’s political environment. Political awareness concerns the recognition of power relationships, both formal and informal, and also the willingness to operate within these structures.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 376.
Incorrect
Political awareness helps the project manager to plan communications based on the Project environment as well as the organization’s political environment. Political awareness concerns the recognition of power relationships, both formal and informal, and also the willingness to operate within these structures.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 376.
Unattempted
Political awareness helps the project manager to plan communications based on the Project environment as well as the organization’s political environment. Political awareness concerns the recognition of power relationships, both formal and informal, and also the willingness to operate within these structures.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 376.
Question 53 of 65
53. Question
A Project Manager who is new to an IT organization has been awarded a project which is running behind schedule. After talking with team and reviewing all documents he found that a key resource who was working on a critical path task has suddenly gone for vacation for personal reasons. A back up plan for on-boarding a new resource is also available.
What went wrong in the situation mentioned above?
Correct
The above situation suggests that risk response was planned but never implemented. Project team already considered the above situation during planning, made necessary resource replacement plan, if such situation triggers. But the new resource was never on-boarded. The common problem in risk management is that project teams may spend a lot of time and effort in identifying, analyzing, and documenting risks and risk responses, but then no action is taken to manage those risks.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 449-450.
Incorrect
The above situation suggests that risk response was planned but never implemented. Project team already considered the above situation during planning, made necessary resource replacement plan, if such situation triggers. But the new resource was never on-boarded. The common problem in risk management is that project teams may spend a lot of time and effort in identifying, analyzing, and documenting risks and risk responses, but then no action is taken to manage those risks.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 449-450.
Unattempted
The above situation suggests that risk response was planned but never implemented. Project team already considered the above situation during planning, made necessary resource replacement plan, if such situation triggers. But the new resource was never on-boarded. The common problem in risk management is that project teams may spend a lot of time and effort in identifying, analyzing, and documenting risks and risk responses, but then no action is taken to manage those risks.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 449-450.
Question 54 of 65
54. Question
The endeavor for keeping errors out of the process is also termed as: –
Correct
Prevention is keeping errors out of the process. Prevention over Inspection is the biggest slogan of Modern Quality Management.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 274.
Incorrect
Prevention is keeping errors out of the process. Prevention over Inspection is the biggest slogan of Modern Quality Management.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 274.
Unattempted
Prevention is keeping errors out of the process. Prevention over Inspection is the biggest slogan of Modern Quality Management.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 274.
Question 55 of 65
55. Question
The Project Team has done Root Cause Analysis of all defects detected during inspection. The Project Manager used a tool to organize and group the results of Root Cause Analysis which he will present in next Senior Management review meeting.
Which of the following tools has been used by the Project Manager in the above scenario?
Correct
The scenario states that the project manager used affinity diagram to organize and group the result of RCA.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 293.
Incorrect
The scenario states that the project manager used affinity diagram to organize and group the result of RCA.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 293.
Unattempted
The scenario states that the project manager used affinity diagram to organize and group the result of RCA.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 293.
Question 56 of 65
56. Question
A key stakeholder has submitted a Change Request which will not impact project schedule. What should the Project Manager do NEXT?
Correct
The Project Manager should evaluate the other impacts of the project first. These include the impact on other project level constraints like scope, cost, quality, resource, etc. Once evaluated, CCB (if exists) can be notified to take a final decision of the Change Request.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 117.
Incorrect
The Project Manager should evaluate the other impacts of the project first. These include the impact on other project level constraints like scope, cost, quality, resource, etc. Once evaluated, CCB (if exists) can be notified to take a final decision of the Change Request.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 117.
Unattempted
The Project Manager should evaluate the other impacts of the project first. These include the impact on other project level constraints like scope, cost, quality, resource, etc. Once evaluated, CCB (if exists) can be notified to take a final decision of the Change Request.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 117.
Question 57 of 65
57. Question
In a Go/No-Go decision meeting, the members of the senior management are evaluating two Projects i.e. Project X and Project Y. Project X has net present value(NPV) of $40,000 and Project Y has an NPV of $25000. What is the opportunity cost If Project X is selected over Project Y?
Correct
The opportunity cost is the monetary value of the lost opportunity. In this case, since Project Y is not selected, the opportunity cost becomes $25000.
Refer :-PMP Exam Prep 9th edition 2018 – Rita Mulcahy.
Incorrect
The opportunity cost is the monetary value of the lost opportunity. In this case, since Project Y is not selected, the opportunity cost becomes $25000.
Refer :-PMP Exam Prep 9th edition 2018 – Rita Mulcahy.
Unattempted
The opportunity cost is the monetary value of the lost opportunity. In this case, since Project Y is not selected, the opportunity cost becomes $25000.
Refer :-PMP Exam Prep 9th edition 2018 – Rita Mulcahy.
Question 58 of 65
58. Question
Which of the following is an input for the Perform Integrated Change Control Process?
Correct
A is wrong as agreement has little to do with change control process. B and C are output for Perform Integrated Change Control Process. Work Performance Reports are valid input for the process, it contains reports related to resource requirements, schedule and cost data, earn value reports. So , among all options provided , D is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 113, 16.
Incorrect
A is wrong as agreement has little to do with change control process. B and C are output for Perform Integrated Change Control Process. Work Performance Reports are valid input for the process, it contains reports related to resource requirements, schedule and cost data, earn value reports. So , among all options provided , D is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 113, 16.
Unattempted
A is wrong as agreement has little to do with change control process. B and C are output for Perform Integrated Change Control Process. Work Performance Reports are valid input for the process, it contains reports related to resource requirements, schedule and cost data, earn value reports. So , among all options provided , D is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 113, 16.
Question 59 of 65
59. Question
Ryan is a project manager of a construction project. Project team has identified few variability risks which needs to be addressed to keep the project on track.
Which of the following processes can be used to address variability risks?
Correct
Variability risks can be addressed by using a simulation technique called Monte Carlo analysis which is performed as a part of Perform Quantitative Risk Analysis process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 399, 433.
Incorrect
Variability risks can be addressed by using a simulation technique called Monte Carlo analysis which is performed as a part of Perform Quantitative Risk Analysis process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 399, 433.
Unattempted
Variability risks can be addressed by using a simulation technique called Monte Carlo analysis which is performed as a part of Perform Quantitative Risk Analysis process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 399, 433.
Question 60 of 65
60. Question
A new Project Manager has been appointed during the early stage of planning. In his first meeting with sponsor, he understands the need of a mandatory licensed software for the project.
Which of the following documents should the project Manager review to know whether the software has already been procured?
Correct
The question states that the Project has just entered the planning phase. So option D is incorrect as Physical resource assignments are created during execution. Assumption log records the assumption and constraints available at project level, so Option C is also incorrect. Resource Management plan determines how resources would be acquired, it does not contain information of available resources. Further, since the project is at early stage of planning, Resource Management plan may not be drafted yet. So, answer is B by following elimination technique. Project Charter contains Pre-approved financial resources. Sometimes, Physical and human resources are determined in advance, even before Resource Management plan is drafted. This is also called Pre-assignment. Pre-assignment include team members or physical resources already assigned during Develop Project Charter process. So, among all the options provided, B is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 81,333.
Incorrect
The question states that the Project has just entered the planning phase. So option D is incorrect as Physical resource assignments are created during execution. Assumption log records the assumption and constraints available at project level, so Option C is also incorrect. Resource Management plan determines how resources would be acquired, it does not contain information of available resources. Further, since the project is at early stage of planning, Resource Management plan may not be drafted yet. So, answer is B by following elimination technique. Project Charter contains Pre-approved financial resources. Sometimes, Physical and human resources are determined in advance, even before Resource Management plan is drafted. This is also called Pre-assignment. Pre-assignment include team members or physical resources already assigned during Develop Project Charter process. So, among all the options provided, B is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 81,333.
Unattempted
The question states that the Project has just entered the planning phase. So option D is incorrect as Physical resource assignments are created during execution. Assumption log records the assumption and constraints available at project level, so Option C is also incorrect. Resource Management plan determines how resources would be acquired, it does not contain information of available resources. Further, since the project is at early stage of planning, Resource Management plan may not be drafted yet. So, answer is B by following elimination technique. Project Charter contains Pre-approved financial resources. Sometimes, Physical and human resources are determined in advance, even before Resource Management plan is drafted. This is also called Pre-assignment. Pre-assignment include team members or physical resources already assigned during Develop Project Charter process. So, among all the options provided, B is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 81,333.
Question 61 of 65
61. Question
During execution, one key stakeholder requests the Project Manager for a change in a work package for which work has not started yet.
What should the Project Manager do NEXT?
Correct
The scenario in the question states that Project is in Execution, which mean baselines are already created. Once baselines are created, formal change requests are required to establish any changes in the project control documents.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 115.
Incorrect
The scenario in the question states that Project is in Execution, which mean baselines are already created. Once baselines are created, formal change requests are required to establish any changes in the project control documents.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 115.
Unattempted
The scenario in the question states that Project is in Execution, which mean baselines are already created. Once baselines are created, formal change requests are required to establish any changes in the project control documents.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 115.
Question 62 of 65
62. Question
Ryan is a project manager of a Software Development project. The project is 60 percent complete, but there are still few open risks which needs to addressed. Which tool would help the project manager to fetch the information in relation to reserve available in current state?
Correct
Reserve analysis compares the amount of Contingency reserves remaining to the amount of risk remaining at any time in the project in order to determine if the remaining reserve is adequate.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 456.
Incorrect
Reserve analysis compares the amount of Contingency reserves remaining to the amount of risk remaining at any time in the project in order to determine if the remaining reserve is adequate.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 456.
Unattempted
Reserve analysis compares the amount of Contingency reserves remaining to the amount of risk remaining at any time in the project in order to determine if the remaining reserve is adequate.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 456.
Question 63 of 65
63. Question
Qtech company has appointed Ryan as a project manager of a business critical software development project. The company has recently dismissed a vendor company that consisted of 16 consultants who completed half of the work in 9 months and spent 82% of the budget of what was originally a 12 Month, $1,000,000 project. Ryan has formed a new team of 8 developers, and they are completing the rest of the work at the pace that was originally planned, and for half the price that was originally estimated for each remaining deliverable.
What is the EAC?
Correct
The scenario over here states that the initial plan is no longer valid, so formula for EAC would be summation of actual costs incurred till date and the expected cost to finish the remaining work. EAC = AC + ETC AC = 82% of the original budget = 1,000,000 * 82% = 820,000.
ETC = Half of the planned cost of the remaining work = $500,000/2 = $250,000 .
EAC = $820,000 + $250,000 = $1,070,000.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 267.
Incorrect
The scenario over here states that the initial plan is no longer valid, so formula for EAC would be summation of actual costs incurred till date and the expected cost to finish the remaining work. EAC = AC + ETC AC = 82% of the original budget = 1,000,000 * 82% = 820,000.
ETC = Half of the planned cost of the remaining work = $500,000/2 = $250,000 .
EAC = $820,000 + $250,000 = $1,070,000.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 267.
Unattempted
The scenario over here states that the initial plan is no longer valid, so formula for EAC would be summation of actual costs incurred till date and the expected cost to finish the remaining work. EAC = AC + ETC AC = 82% of the original budget = 1,000,000 * 82% = 820,000.
ETC = Half of the planned cost of the remaining work = $500,000/2 = $250,000 .
EAC = $820,000 + $250,000 = $1,070,000.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 267.
Question 64 of 65
64. Question
The document that formally authorizes the Project has been created and approved. A new Project Manager has been appointed and a list of Key-stakeholders has also been identified as a part of the process. What should be done NEXT?
Correct
Here the question talks about Task 8 of Domain 1, which states “Inform stakeholders of the approved project charter to ensure a common understanding of the key deliverables, milestones, and their roles and responsibilities.” The project charter includes high-level information, such as project objectives, milestones, and the roles and responsibilities of key stakeholders and its approval should be communicated to all the stakeholders before project planning starts.
Please see – Process Domain I: Initiation – Task 9
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 53,81
Incorrect
Here the question talks about Task 8 of Domain 1, which states “Inform stakeholders of the approved project charter to ensure a common understanding of the key deliverables, milestones, and their roles and responsibilities.” The project charter includes high-level information, such as project objectives, milestones, and the roles and responsibilities of key stakeholders and its approval should be communicated to all the stakeholders before project planning starts.
Please see – Process Domain I: Initiation – Task 9
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 53,81
Unattempted
Here the question talks about Task 8 of Domain 1, which states “Inform stakeholders of the approved project charter to ensure a common understanding of the key deliverables, milestones, and their roles and responsibilities.” The project charter includes high-level information, such as project objectives, milestones, and the roles and responsibilities of key stakeholders and its approval should be communicated to all the stakeholders before project planning starts.
Please see – Process Domain I: Initiation – Task 9
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 53,81
Question 65 of 65
65. Question
Phase 1 of the project has been successfully completed. During planning stage of phase 2, Project Manager and team along with few key stakeholders are trying to do assessment of the type and quantities of raw materials necessary to perform and complete project work.
Which of the following tools and technique cannot be used as a part of this process?
Correct
The question states that the project team is involved in Estimate Activity Resources process, where they are estimating the type and quantities of physical resources required to complete project work. Physical resources or team resources cannot be estimated at activity level, using three-point estimation.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 321.
Incorrect
The question states that the project team is involved in Estimate Activity Resources process, where they are estimating the type and quantities of physical resources required to complete project work. Physical resources or team resources cannot be estimated at activity level, using three-point estimation.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 321.
Unattempted
The question states that the project team is involved in Estimate Activity Resources process, where they are estimating the type and quantities of physical resources required to complete project work. Physical resources or team resources cannot be estimated at activity level, using three-point estimation.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 321.
X