You have already completed the Test before. Hence you can not start it again.
Test is loading...
You must sign in or sign up to start the Test.
You have to finish following quiz, to start this Test:
Your results are here!! for" Project Management Professional (PMP) Practice Test 6 "
0 of 75 questions answered correctly
Your time:
Time has elapsed
Your Final Score is : 0
You have attempted : 0
Number of Correct Questions : 0 and scored 0
Number of Incorrect Questions : 0 and Negative marks 0
Average score
Your score
Project Management Professional (PMP)
You have attempted: 0
Number of Correct Questions: 0 and scored 0
Number of Incorrect Questions: 0 and Negative marks 0
You can review your answers by clicking view questions. Important Note : Open Reference Documentation Links in New Tab (Right Click and Open in New Tab).
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
Answered
Review
Question 1 of 75
1. Question
During Execution, a newly joined team member wants to review the detailed description of the scope of the work assigned to him.
Which document should team member review?
Correct
Here in this scenario, Team member wants to review the description of scope of work assigned to him, which means he has to review work package level information. Some may get confused between option B and D, Activity Lists may relate the work package, but they do not contain the detailed description of the work package. The WBS dictionary is a document that provides detailed deliverable, activity, and scheduling information about each component in the WBS. It also contains description of work at work package level. Further, from high level point of view, Activity List focuses on your schedule activities (i.e. on the “tasks”) while the WBS Dictionary focuses on describing your deliverables (the “scope”).
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 162.
Incorrect
Here in this scenario, Team member wants to review the description of scope of work assigned to him, which means he has to review work package level information. Some may get confused between option B and D, Activity Lists may relate the work package, but they do not contain the detailed description of the work package. The WBS dictionary is a document that provides detailed deliverable, activity, and scheduling information about each component in the WBS. It also contains description of work at work package level. Further, from high level point of view, Activity List focuses on your schedule activities (i.e. on the “tasks”) while the WBS Dictionary focuses on describing your deliverables (the “scope”).
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 162.
Unattempted
Here in this scenario, Team member wants to review the description of scope of work assigned to him, which means he has to review work package level information. Some may get confused between option B and D, Activity Lists may relate the work package, but they do not contain the detailed description of the work package. The WBS dictionary is a document that provides detailed deliverable, activity, and scheduling information about each component in the WBS. It also contains description of work at work package level. Further, from high level point of view, Activity List focuses on your schedule activities (i.e. on the “tasks”) while the WBS Dictionary focuses on describing your deliverables (the “scope”).
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 162.
Question 2 of 75
2. Question
Arun is a Project Manager of Telecom equipment manufacturing project. The project is risk prone in few areas and running behind schedule. The project still has few open risks which are not yet handled. The corresponding SPI and CPI values are 0.81 and 1.15. The project Manager decides to bring the schedule back on track and complete the project in next 45 days as one of competitors has a plan to launch a similar product in next two months.
What is the best course of action in the given scenario?
Correct
The question states that the project is running behind schedule but within budget and the project manager has to complete the project soon to remain competitive in the market. Since the project is already risk prone, Fast tracking is not advisable in the current situation. As per the situation stated above crashing is the best solution. Crashing is a schedule compression technique that shortens the project schedule without affecting the project scope. Approving overtime, bringing in additional resources and paying to expedite delivery activities are valid examples of crashing. Further, as the project still under budget, the application of crashing technique wont hamper the project budget to a great extent.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 215.
Incorrect
The question states that the project is running behind schedule but within budget and the project manager has to complete the project soon to remain competitive in the market. Since the project is already risk prone, Fast tracking is not advisable in the current situation. As per the situation stated above crashing is the best solution. Crashing is a schedule compression technique that shortens the project schedule without affecting the project scope. Approving overtime, bringing in additional resources and paying to expedite delivery activities are valid examples of crashing. Further, as the project still under budget, the application of crashing technique wont hamper the project budget to a great extent.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 215.
Unattempted
The question states that the project is running behind schedule but within budget and the project manager has to complete the project soon to remain competitive in the market. Since the project is already risk prone, Fast tracking is not advisable in the current situation. As per the situation stated above crashing is the best solution. Crashing is a schedule compression technique that shortens the project schedule without affecting the project scope. Approving overtime, bringing in additional resources and paying to expedite delivery activities are valid examples of crashing. Further, as the project still under budget, the application of crashing technique wont hamper the project budget to a great extent.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 215.
Question 3 of 75
3. Question
You are a project manager of a website development project. Project team has done initial stakeholder analysis and grouped all stakeholders according to their level of authority, and level of concern.
Which of the following engagement strategies should be applicable for end-users who are responsible for handling day-to-day operational activities?
Correct
The question implies that the Project Team has categorized the identified stakeholders using Power/Interest grid. Business operational end-users are those people who usually handle day-to-day operational activities of a company. They may not be powerful, but may have high interest on the project, as they are one who will use the website when it gets developed. In Power-Interest grid, they fall under: – Low Power/High Interest category. It’s the responsibility of the project team to keep these people adequately informed, talk to them from time to time to ensure that there no major issues cropping up. These people can often be very helpful, especially with the details of your intervention. So, among all options provided, B is the correct answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 512.
Incorrect
The question implies that the Project Team has categorized the identified stakeholders using Power/Interest grid. Business operational end-users are those people who usually handle day-to-day operational activities of a company. They may not be powerful, but may have high interest on the project, as they are one who will use the website when it gets developed. In Power-Interest grid, they fall under: – Low Power/High Interest category. It’s the responsibility of the project team to keep these people adequately informed, talk to them from time to time to ensure that there no major issues cropping up. These people can often be very helpful, especially with the details of your intervention. So, among all options provided, B is the correct answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 512.
Unattempted
The question implies that the Project Team has categorized the identified stakeholders using Power/Interest grid. Business operational end-users are those people who usually handle day-to-day operational activities of a company. They may not be powerful, but may have high interest on the project, as they are one who will use the website when it gets developed. In Power-Interest grid, they fall under: – Low Power/High Interest category. It’s the responsibility of the project team to keep these people adequately informed, talk to them from time to time to ensure that there no major issues cropping up. These people can often be very helpful, especially with the details of your intervention. So, among all options provided, B is the correct answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 512.
Question 4 of 75
4. Question
The Project manager of a large project is conducting a kick-off meeting to ensure that stakeholders clearly understand project goals, objectives, benefits, and risks for the project, as well as their roles and responsibilities.
The Kick-off meetings in large projects can be held in support of which of the following processes?
Correct
In large projects, kick-off meeting take place in the Executing Process Group. A kick-off meeting can be held in support of the Manage Stakeholder Engagement process to foster the appropriate level of stakeholder involvement in the project.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 86,528.
Incorrect
In large projects, kick-off meeting take place in the Executing Process Group. A kick-off meeting can be held in support of the Manage Stakeholder Engagement process to foster the appropriate level of stakeholder involvement in the project.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 86,528.
Unattempted
In large projects, kick-off meeting take place in the Executing Process Group. A kick-off meeting can be held in support of the Manage Stakeholder Engagement process to foster the appropriate level of stakeholder involvement in the project.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 86,528.
Question 5 of 75
5. Question
The document that shows organization commitment to the project has been prepared. Portfolio Governing body chairperson and other authorized representatives are having a meeting to discuss and decide the outcome of the document that has been prepared. They are also reviewing the Cost-Benefit analysis, Feasibility study report, and other factors that justified the requirement of the project.
Which of the following documents has been prepared as per the scenario mentioned above?
Correct
As per the scenario stated above, Portfolio governing body is having a meeting to make approval decision of project charter. Project Charter shows organization commitment to the project and provides direct link between the project and the strategic objectives of the organization.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 75-78.
Incorrect
As per the scenario stated above, Portfolio governing body is having a meeting to make approval decision of project charter. Project Charter shows organization commitment to the project and provides direct link between the project and the strategic objectives of the organization.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 75-78.
Unattempted
As per the scenario stated above, Portfolio governing body is having a meeting to make approval decision of project charter. Project Charter shows organization commitment to the project and provides direct link between the project and the strategic objectives of the organization.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 75-78.
Question 6 of 75
6. Question
During Planning, the project management team decided not to change the project management plan for addressing a risk of low probability and high impact. Instead additional reserves are planned in case such situation occurs.
What response strategy has been planned in this scenario?
Correct
The scenario states that here Active Risk acceptance strategy has been adopted to handle the low probability and high impact risk. In this case, no response plan has been initiated and contingency reserve has been kept to handle the risk if it occurs.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 443.
Incorrect
The scenario states that here Active Risk acceptance strategy has been adopted to handle the low probability and high impact risk. In this case, no response plan has been initiated and contingency reserve has been kept to handle the risk if it occurs.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 443.
Unattempted
The scenario states that here Active Risk acceptance strategy has been adopted to handle the low probability and high impact risk. In this case, no response plan has been initiated and contingency reserve has been kept to handle the risk if it occurs.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 443.
Question 7 of 75
7. Question
Ryan is the recently joined Project Manager of a business complex IT project. After receiving detailed knowledge transfer from the outgoing senior project manager, he has started conducting team meeting and actively got involved in maintaining documents like communication management plan, stakeholder register, and few other necessary project documents. The outgoing project manager is closely observing all activities of Ryan and in time helping him with suggestions.
What Knowledge management technique has been followed in the above situation?
Correct
In case of Job Shadowing you follow an expert and gain knowledge from him or a group, whereas reverse shadowing is a situation where expert follows you and rectifies your way of work if required. The question states that the new Project Manager has started taking responsibilities, under the close observation of outgoing senior Project Manager which is similar to Reverse-KT situation. Knowledge fairs and cafés is creative knowledge sharing session among group of people of common interests, generally happens face-to-face. So, among all options provided C is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 103.
Incorrect
In case of Job Shadowing you follow an expert and gain knowledge from him or a group, whereas reverse shadowing is a situation where expert follows you and rectifies your way of work if required. The question states that the new Project Manager has started taking responsibilities, under the close observation of outgoing senior Project Manager which is similar to Reverse-KT situation. Knowledge fairs and cafés is creative knowledge sharing session among group of people of common interests, generally happens face-to-face. So, among all options provided C is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 103.
Unattempted
In case of Job Shadowing you follow an expert and gain knowledge from him or a group, whereas reverse shadowing is a situation where expert follows you and rectifies your way of work if required. The question states that the new Project Manager has started taking responsibilities, under the close observation of outgoing senior Project Manager which is similar to Reverse-KT situation. Knowledge fairs and cafés is creative knowledge sharing session among group of people of common interests, generally happens face-to-face. So, among all options provided C is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 103.
Question 8 of 75
8. Question
In a project, the Project performance appraisal gets carried out as a part of which of the following process groups?
Correct
In general, manage team process of the executing process group takes care of Project performance appraisal. In a Project Performance Appraisal team members get feedback from project work supervisors.
Incorrect
In general, manage team process of the executing process group takes care of Project performance appraisal. In a Project Performance Appraisal team members get feedback from project work supervisors.
Unattempted
In general, manage team process of the executing process group takes care of Project performance appraisal. In a Project Performance Appraisal team members get feedback from project work supervisors.
Question 9 of 75
9. Question
The Project work has been completed successfully and the customer has confirmed the formal acceptance of the product that has been delivered. Before releasing the entire team, the Project Manager engaged the team to document the final lessons learned, so that future projects can benefit out of it.
What should the Project Manager do next?
Correct
The question states that the Project Manager is involved in Close Project/Phase process. As per the given scenario, A and D are already completed. Celebration party can be organized any time, but option C, i.e. Task 6 for closing domain is very important task associated to closing. All project documents must be archived, so that they can be referred in future projects. So, among all options provided C is the best answer.
Process Domain V: Closing – Task 6
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 123.
Incorrect
The question states that the Project Manager is involved in Close Project/Phase process. As per the given scenario, A and D are already completed. Celebration party can be organized any time, but option C, i.e. Task 6 for closing domain is very important task associated to closing. All project documents must be archived, so that they can be referred in future projects. So, among all options provided C is the best answer.
Process Domain V: Closing – Task 6
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 123.
Unattempted
The question states that the Project Manager is involved in Close Project/Phase process. As per the given scenario, A and D are already completed. Celebration party can be organized any time, but option C, i.e. Task 6 for closing domain is very important task associated to closing. All project documents must be archived, so that they can be referred in future projects. So, among all options provided C is the best answer.
Process Domain V: Closing – Task 6
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 123.
Question 10 of 75
10. Question
As a Project Manager of a mid-sized adaptive software development project, you are using a tool to determine how much work is remaining to be done in the current iteration.
What tool has been referred over here?
Correct
The question states that the Project Manager is analyzing schedule control. Run Chart evaluates how a process is running, So D is not true. Why-why diagram is mainly a tool for RCA, so C is not applicable here. A burndown chart shows how much work is remaining to be done, whereas a burnup chart shows how much work has been completed, and the total amount of work. So, among all options provided, A is right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 226.
Incorrect
The question states that the Project Manager is analyzing schedule control. Run Chart evaluates how a process is running, So D is not true. Why-why diagram is mainly a tool for RCA, so C is not applicable here. A burndown chart shows how much work is remaining to be done, whereas a burnup chart shows how much work has been completed, and the total amount of work. So, among all options provided, A is right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 226.
Unattempted
The question states that the Project Manager is analyzing schedule control. Run Chart evaluates how a process is running, So D is not true. Why-why diagram is mainly a tool for RCA, so C is not applicable here. A burndown chart shows how much work is remaining to be done, whereas a burnup chart shows how much work has been completed, and the total amount of work. So, among all options provided, A is right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 226.
Question 11 of 75
11. Question
Ryan is a Project Manager of a company which has been awarded a project that involves renovation of a building of a Chemical plant. There are lot of toxic and radioactive wastes inside the building.
What is the best approach the Project Manager can take to transfer the risk?
Correct
Transfer involves shifting of ownership of a threat to a third party to manage the risk and bear the impact, if the threat occurs. The question states that, the project manager has to find a best approach that involves transference of pure risk that is currently part of the project. Among all the given options “Hiring an outside organization” to do the work that involves pure risk is the best choice.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 443.
Incorrect
Transfer involves shifting of ownership of a threat to a third party to manage the risk and bear the impact, if the threat occurs. The question states that, the project manager has to find a best approach that involves transference of pure risk that is currently part of the project. Among all the given options “Hiring an outside organization” to do the work that involves pure risk is the best choice.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 443.
Unattempted
Transfer involves shifting of ownership of a threat to a third party to manage the risk and bear the impact, if the threat occurs. The question states that, the project manager has to find a best approach that involves transference of pure risk that is currently part of the project. Among all the given options “Hiring an outside organization” to do the work that involves pure risk is the best choice.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 443.
Question 12 of 75
12. Question
Hierarchical charts act as important data representation tool for planning resource management.
Which of the following is not an example of Hierarchical charts?
Correct
B, C, D are examples of Hierarchical Charts where positions and relationships are shown in graphical, top-down format. RACI chart is an example RAM (Responsibility assignment matrix) and is not an example of Hierarchical charts.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 316,317.
Incorrect
B, C, D are examples of Hierarchical Charts where positions and relationships are shown in graphical, top-down format. RACI chart is an example RAM (Responsibility assignment matrix) and is not an example of Hierarchical charts.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 316,317.
Unattempted
B, C, D are examples of Hierarchical Charts where positions and relationships are shown in graphical, top-down format. RACI chart is an example RAM (Responsibility assignment matrix) and is not an example of Hierarchical charts.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 316,317.
Question 13 of 75
13. Question
As a Project Manager of the seller organization, you are working with the team to build an actionable plan to interact effectively with stakeholders.
What can help you to assess the political climate as well as stakeholder risk appetites of the buyer organization?
Correct
The question implies that the Project Team is involved in Plan Stakeholder Engagement process. All the provided options are input to this process. But, it’s the EEF, that helps to determine the organizational culture, political climate, as well as stakeholder risk appetites.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 519.
Incorrect
The question implies that the Project Team is involved in Plan Stakeholder Engagement process. All the provided options are input to this process. But, it’s the EEF, that helps to determine the organizational culture, political climate, as well as stakeholder risk appetites.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 519.
Unattempted
The question implies that the Project Team is involved in Plan Stakeholder Engagement process. All the provided options are input to this process. But, it’s the EEF, that helps to determine the organizational culture, political climate, as well as stakeholder risk appetites.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 519.
Question 14 of 75
14. Question
Ryan is a Project Manager of a Software development project. During execution, a key stakeholder requests him for a scope change and asks about the correct change control process that should be followed throughout the project.
Which control document should the Project Manager refer to fetch this necessary information?
Correct
The Change Management plan provides the direction for managing the change control process and describes how the change requests throughout the project will be formally authorized and incorporated.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 88,116.
Incorrect
The Change Management plan provides the direction for managing the change control process and describes how the change requests throughout the project will be formally authorized and incorporated.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 88,116.
Unattempted
The Change Management plan provides the direction for managing the change control process and describes how the change requests throughout the project will be formally authorized and incorporated.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 88,116.
Question 15 of 75
15. Question
All of the following are input for Create WBS process except:
Correct
A, B, C are input to Create WBS process, where D is the output of the Create WBS process. So, D is the correct answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 156.
Incorrect
A, B, C are input to Create WBS process, where D is the output of the Create WBS process. So, D is the correct answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 156.
Unattempted
A, B, C are input to Create WBS process, where D is the output of the Create WBS process. So, D is the correct answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 156.
Question 16 of 75
16. Question
Ryan has been awarded as Project Manager of a new software development project. He decides to meet another Project Manager who has handled similar project in the past. But he finds out that the person whom he wants to meet has left the organization a month back.
What should Ryan do to gather necessary information of the past project?
Correct
Lessons learned is collected throughout the Life Cycle of the project. During closing, the final Lessons learned is collected and transferred to Lessons Learned repository so that future projects benefit out of it. So, here among all options provided, B is the best option in the current scenario.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 104, 128.
Incorrect
Lessons learned is collected throughout the Life Cycle of the project. During closing, the final Lessons learned is collected and transferred to Lessons Learned repository so that future projects benefit out of it. So, here among all options provided, B is the best option in the current scenario.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 104, 128.
Unattempted
Lessons learned is collected throughout the Life Cycle of the project. During closing, the final Lessons learned is collected and transferred to Lessons Learned repository so that future projects benefit out of it. So, here among all options provided, B is the best option in the current scenario.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 104, 128.
Question 17 of 75
17. Question
Arun is a directive PMO of an IT organization. Recent status report of various projects reveals that there are multiple projects where resources are over allocated. Since over allocation is against company policy, he immediately advises all the related project managers to remove over allocation by applying the best suited resource optimization technique even if the project schedule gets impacted.
What resource optimization technique is best suited in this scenario?
Correct
Resource leveling is a resource optimization technique in which start and finish dates are adjusted based on resource constraints. This technique can change the critical path and acts as an effective aid to control over-allocation. Resource smoothing is also a resource optimization tool, but it doesn’t change the project schedule, so D is not correct. Option A and B are examples of schedule compression techniques. So, among all options provided, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 211.
Incorrect
Resource leveling is a resource optimization technique in which start and finish dates are adjusted based on resource constraints. This technique can change the critical path and acts as an effective aid to control over-allocation. Resource smoothing is also a resource optimization tool, but it doesn’t change the project schedule, so D is not correct. Option A and B are examples of schedule compression techniques. So, among all options provided, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 211.
Unattempted
Resource leveling is a resource optimization technique in which start and finish dates are adjusted based on resource constraints. This technique can change the critical path and acts as an effective aid to control over-allocation. Resource smoothing is also a resource optimization tool, but it doesn’t change the project schedule, so D is not correct. Option A and B are examples of schedule compression techniques. So, among all options provided, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 211.
Question 18 of 75
18. Question
Ryan is a newly joined Project Manager of a construction project which is running behind schedule. The project has few ongoing issues with a preferred vendor who is responsible for supplying cements for the project. He decides to facilitate a meeting between Buyer and seller management team to resolve all misunderstandings and create a win-win solution.
What should he review to know the alternate dispute mechanisms applicable for the project?
Correct
Alternative Dispute Resolution (ADR) is the procedure for settling disputes without litigation. At project level, ADR mechanisms are generally defined in agreements in advance.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 489.
Incorrect
Alternative Dispute Resolution (ADR) is the procedure for settling disputes without litigation. At project level, ADR mechanisms are generally defined in agreements in advance.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 489.
Unattempted
Alternative Dispute Resolution (ADR) is the procedure for settling disputes without litigation. At project level, ADR mechanisms are generally defined in agreements in advance.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 489.
Question 19 of 75
19. Question
The Project team decides to change the project management plan in order to eliminate a high probability threat.
Which process takes care of such actions?
Correct
The question talks about Risk avoidance strategy which can be applied for addressing high probability risks. Risk response planning are made during Plan Risk Responses process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 437,443.
Incorrect
The question talks about Risk avoidance strategy which can be applied for addressing high probability risks. Risk response planning are made during Plan Risk Responses process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 437,443.
Unattempted
The question talks about Risk avoidance strategy which can be applied for addressing high probability risks. Risk response planning are made during Plan Risk Responses process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 437,443.
Question 20 of 75
20. Question
Statistical Sampling is a data gathering tool that involves choosing a part of a population of interest for inspection. The sample size and frequency of measurement of the tool are determined as a part of which of the following processes?
Correct
Statistical Sampling is a tool that control quality process uses to test a sample population for inspection. The size and the frequency measurements are determined during Plan Quality Management Process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 303.
Incorrect
Statistical Sampling is a tool that control quality process uses to test a sample population for inspection. The size and the frequency measurements are determined during Plan Quality Management Process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 303.
Unattempted
Statistical Sampling is a tool that control quality process uses to test a sample population for inspection. The size and the frequency measurements are determined during Plan Quality Management Process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 303.
Question 21 of 75
21. Question
Ryan is a Project Manager of a research and development project which has team in 4 different countries. The project uses videoconferencing facility to address team meetings.
Here videoconferencing is an example of:
Correct
Interactive communication happens between two or more parties for performing a multi-directional exchange of information in real time. Videoconferencing is a good example for Interactive communication.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 374.
Incorrect
Interactive communication happens between two or more parties for performing a multi-directional exchange of information in real time. Videoconferencing is a good example for Interactive communication.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 374.
Unattempted
Interactive communication happens between two or more parties for performing a multi-directional exchange of information in real time. Videoconferencing is a good example for Interactive communication.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 374.
Question 22 of 75
22. Question
Ryan is a Project Manager of a software development project which is divided into four phases. Phase 1 of the project didn’t go well as 60% of the deliverables were not accepted by the customer. In a retrospective meeting, Director of the IT department asks the project manager to furnish all the reasons that resulted in customer non-acceptance of the verified deliverables.
What needs to be reviewed to know which deliverables were not accepted by customer and the reasons behind such non-acceptance?
Correct
The situation states that 60% of the deliverables are not accepted by customer during last inspection. Work Performance Information, also an output for validate scope process includes information about project progress, such as which deliverables have been accepted and which have not been accepted, along with the reasons behind acceptance and non-acceptance. So, among all options provided, D is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 166.
Incorrect
The situation states that 60% of the deliverables are not accepted by customer during last inspection. Work Performance Information, also an output for validate scope process includes information about project progress, such as which deliverables have been accepted and which have not been accepted, along with the reasons behind acceptance and non-acceptance. So, among all options provided, D is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 166.
Unattempted
The situation states that 60% of the deliverables are not accepted by customer during last inspection. Work Performance Information, also an output for validate scope process includes information about project progress, such as which deliverables have been accepted and which have not been accepted, along with the reasons behind acceptance and non-acceptance. So, among all options provided, D is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 166.
Question 23 of 75
23. Question
Ryan is a Project Manager of a construction project. The Project Management team is currently engaged in a meeting to decide whether the work related to build two swimming pools in a posh residential complex area will be managed in-house or will be outsourced to a preferred seller.
Which of the following processes the project management team is currently engaged in?
Correct
The situation states that the project management team is currently involved in Plan Procurement Management process and the data analysis tool: – Make-or-buy analysis is being used in this scenario to come up with a Make-or-buy decision, one key output for Plan Procurement Management process. Make-or-buy analysis generally determines whether work will be accomplished by the team or would be outsourced.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 466, 473, 479.
Incorrect
The situation states that the project management team is currently involved in Plan Procurement Management process and the data analysis tool: – Make-or-buy analysis is being used in this scenario to come up with a Make-or-buy decision, one key output for Plan Procurement Management process. Make-or-buy analysis generally determines whether work will be accomplished by the team or would be outsourced.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 466, 473, 479.
Unattempted
The situation states that the project management team is currently involved in Plan Procurement Management process and the data analysis tool: – Make-or-buy analysis is being used in this scenario to come up with a Make-or-buy decision, one key output for Plan Procurement Management process. Make-or-buy analysis generally determines whether work will be accomplished by the team or would be outsourced.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 466, 473, 479.
Question 24 of 75
24. Question
You are a project manager of a software development project of a matrix organization, which is currently in execution. Functional manager has decided to remove two key resources from your project who are currently assigned to critical path tasks.
What should you do as a Project Manager?
Correct
In Project Management, negotiation is a popular tool for reaching consensus on project needs. Here the Project Manager needs to apply his interpersonal skill by negotiating with the Functional Manager and try to reach a win-win result. B is incorrect because in Matrix organization, Functional Manager plays the role of resource manager. Option A or D can only be considered if option C fails. So, among all options provided, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 341, 357.
Incorrect
In Project Management, negotiation is a popular tool for reaching consensus on project needs. Here the Project Manager needs to apply his interpersonal skill by negotiating with the Functional Manager and try to reach a win-win result. B is incorrect because in Matrix organization, Functional Manager plays the role of resource manager. Option A or D can only be considered if option C fails. So, among all options provided, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 341, 357.
Unattempted
In Project Management, negotiation is a popular tool for reaching consensus on project needs. Here the Project Manager needs to apply his interpersonal skill by negotiating with the Functional Manager and try to reach a win-win result. B is incorrect because in Matrix organization, Functional Manager plays the role of resource manager. Option A or D can only be considered if option C fails. So, among all options provided, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 341, 357.
Question 25 of 75
25. Question
The CCB has to take a decision on a change request related to scope change. The Change request got evolved during the mid of the project due to upcoming change in Government regulation. If the scope change gets implemented, 90% of the management reserve will get exhausted.
What is the best decision the CCB can take in the given scenario?
Correct
Here in this situation the scope change needs to be implemented as the CR evolved out of change in government regulation. So, option C is wrong. Project Manager has no authority to change the Management reserve, so A is also not applicable. D is also wrong, because it’s never wise to wait for the government regulation getting implemented. Project Sponsor is an individual with overall accountability of the project and is responsible for fund allocation and maintenance. Among all options provided B is the best answer, as it’s the Project Sponsor who can take the best decision here.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 120.
Incorrect
Here in this situation the scope change needs to be implemented as the CR evolved out of change in government regulation. So, option C is wrong. Project Manager has no authority to change the Management reserve, so A is also not applicable. D is also wrong, because it’s never wise to wait for the government regulation getting implemented. Project Sponsor is an individual with overall accountability of the project and is responsible for fund allocation and maintenance. Among all options provided B is the best answer, as it’s the Project Sponsor who can take the best decision here.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 120.
Unattempted
Here in this situation the scope change needs to be implemented as the CR evolved out of change in government regulation. So, option C is wrong. Project Manager has no authority to change the Management reserve, so A is also not applicable. D is also wrong, because it’s never wise to wait for the government regulation getting implemented. Project Sponsor is an individual with overall accountability of the project and is responsible for fund allocation and maintenance. Among all options provided B is the best answer, as it’s the Project Sponsor who can take the best decision here.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s)- 120.
Question 26 of 75
26. Question
The Control Procurement process receives a very important input from the Direct and Manage Project Work process. Which one of the following acts as the valid input for the process?
Correct
Work performance data, generated by Direct and Manage Project Work process contains information related to activity duration, delivery status, start and end dates of scheduled activities which may act as an important input for the Control Procurements process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 493, 95.
Incorrect
Work performance data, generated by Direct and Manage Project Work process contains information related to activity duration, delivery status, start and end dates of scheduled activities which may act as an important input for the Control Procurements process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 493, 95.
Unattempted
Work performance data, generated by Direct and Manage Project Work process contains information related to activity duration, delivery status, start and end dates of scheduled activities which may act as an important input for the Control Procurements process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 493, 95.
Question 27 of 75
27. Question
The Control chart acts as an important tool in determination of stability of a process. It’s an example of which of the following Tools and techniques?
Correct
The Control chart is an example of Data Representation technique used to Control Quality process to determine its stability.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 304.
Incorrect
The Control chart is an example of Data Representation technique used to Control Quality process to determine its stability.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 304.
Unattempted
The Control chart is an example of Data Representation technique used to Control Quality process to determine its stability.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 304.
Question 28 of 75
28. Question
Simulation is an important technique used in the Perform Quantitative Risk Analysis process. It’s an example of which of the following tools and techniques?
Correct
Simulation is a Data Analysis technique that explores the impact of variances on deliverables or outcomes during a given project. Variances constitute a wide variety of unforeseen and unexpected events that may delay or impact the timeliness of deliverables. In Perform Quantitative Risk Analysis process, Simulations are typically performed using a Monte Carlo analysis.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 433.
Incorrect
Simulation is a Data Analysis technique that explores the impact of variances on deliverables or outcomes during a given project. Variances constitute a wide variety of unforeseen and unexpected events that may delay or impact the timeliness of deliverables. In Perform Quantitative Risk Analysis process, Simulations are typically performed using a Monte Carlo analysis.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 433.
Unattempted
Simulation is a Data Analysis technique that explores the impact of variances on deliverables or outcomes during a given project. Variances constitute a wide variety of unforeseen and unexpected events that may delay or impact the timeliness of deliverables. In Perform Quantitative Risk Analysis process, Simulations are typically performed using a Monte Carlo analysis.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 433.
Question 29 of 75
29. Question
The Project Manager is making sure that that the work performed to deliver a product has been completed as defined in project Management Plan.
What part of the project management process group is getting carried out in the given situation?
Correct
During closing, the project manager reviews the Project Management Plan to ensure all project work is completed and the project has met its objectives.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 123.
Incorrect
During closing, the project manager reviews the Project Management Plan to ensure all project work is completed and the project has met its objectives.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 123.
Unattempted
During closing, the project manager reviews the Project Management Plan to ensure all project work is completed and the project has met its objectives.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 123.
Question 30 of 75
30. Question
The Control schedule process gives an important output that acts as an input for Monitor and Control Project Work process.
What output of Control Schedule process is referred in this scenario?
Correct
Work performance information is a summarized or analyzed version of work performance data. Most of the processes in the Monitoring and Controlling Process Group have Work Performance Information as outputs, and it becomes inputs to the Monitor and Control Project Work process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 222-223, 228.
Incorrect
Work performance information is a summarized or analyzed version of work performance data. Most of the processes in the Monitoring and Controlling Process Group have Work Performance Information as outputs, and it becomes inputs to the Monitor and Control Project Work process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 222-223, 228.
Unattempted
Work performance information is a summarized or analyzed version of work performance data. Most of the processes in the Monitoring and Controlling Process Group have Work Performance Information as outputs, and it becomes inputs to the Monitor and Control Project Work process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 222-223, 228.
Question 31 of 75
31. Question
As a Project Manager, you are holding team building activities for your project team. Which process is getting performed in this scenario?
Correct
Organizing Team building activities is an effective aid for building high performance team, which happen during Develop team process. In Develop Team process, the project manager tries to improve overall team environment to enhance project performance. So, among all options provided, A is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 337.
Incorrect
Organizing Team building activities is an effective aid for building high performance team, which happen during Develop team process. In Develop Team process, the project manager tries to improve overall team environment to enhance project performance. So, among all options provided, A is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 337.
Unattempted
Organizing Team building activities is an effective aid for building high performance team, which happen during Develop team process. In Develop Team process, the project manager tries to improve overall team environment to enhance project performance. So, among all options provided, A is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 337.
Question 32 of 75
32. Question
The Project team is currently engaged in Quality planning. They are using several tools to come up with a proper Quality Management Plan.
Which of the following is not a tool or technique of the Plan Quality Management process?
Correct
A, B, D are not correct because they are defined tools and techniques used for Quality Planning. A quality metric specifically describes a project or product attribute and how the Control Quality process will verify compliance to it. Quality metrics are outputs from the Plan Quality Management process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 281 – 284.
Incorrect
A, B, D are not correct because they are defined tools and techniques used for Quality Planning. A quality metric specifically describes a project or product attribute and how the Control Quality process will verify compliance to it. Quality metrics are outputs from the Plan Quality Management process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 281 – 284.
Unattempted
A, B, D are not correct because they are defined tools and techniques used for Quality Planning. A quality metric specifically describes a project or product attribute and how the Control Quality process will verify compliance to it. Quality metrics are outputs from the Plan Quality Management process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 281 – 284.
Question 33 of 75
33. Question
As a Project Manager, you are estimating the type and quantities of materials, and suppliers necessary to perform project work.
What enterprise environmental factors can influence your estimation process?
Correct
The scenario states that the Project Manager is performing Estimate Activity Resources process and EEF is a valid input to the process. D is an example of OPA, so D is not correct. A, C are examples of EEF but they are used as input for Estimate Activity Durations process, not the Estimate Activity Resources process. So, A, C are also incorrect. B is an example of EEF (enterprise environmental factors) which is used as input for Estimate Activity Resources process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 323.
Incorrect
The scenario states that the Project Manager is performing Estimate Activity Resources process and EEF is a valid input to the process. D is an example of OPA, so D is not correct. A, C are examples of EEF but they are used as input for Estimate Activity Durations process, not the Estimate Activity Resources process. So, A, C are also incorrect. B is an example of EEF (enterprise environmental factors) which is used as input for Estimate Activity Resources process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 323.
Unattempted
The scenario states that the Project Manager is performing Estimate Activity Resources process and EEF is a valid input to the process. D is an example of OPA, so D is not correct. A, C are examples of EEF but they are used as input for Estimate Activity Durations process, not the Estimate Activity Resources process. So, A, C are also incorrect. B is an example of EEF (enterprise environmental factors) which is used as input for Estimate Activity Resources process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 323.
Question 34 of 75
34. Question
Which of the following techniques can be used during closing to improve the metrics of the organization by comparing the end result with what was initially planned?
Correct
Here the question states about the data analysis technique called Variance Analysis which helps to compare plan Vs. Actual results. Among all options provided, D is the correct answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 127.
Incorrect
Here the question states about the data analysis technique called Variance Analysis which helps to compare plan Vs. Actual results. Among all options provided, D is the correct answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 127.
Unattempted
Here the question states about the data analysis technique called Variance Analysis which helps to compare plan Vs. Actual results. Among all options provided, D is the correct answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 127.
Question 35 of 75
35. Question
Ryan is a project manager of IT development project. Currently he is involved in the preparation of the Cost Management Plan.
Which of the following techniques can help in the preparation of the Cost Management Plan?
Correct
The situation states that the Project Manager is involved in Plan Cost Management process. A and D are not correct as both the techniques are used in Estimate Costs process, not Plan Cost Management process. C is wrong, because it’s used as technique for Control Costs process. B is a valid technique used in Plan Cost management process to review strategic funding options and consideration of ways to acquire project resources such as making, purchasing, renting, or leasing. So, among all options provided B is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 238.
Incorrect
The situation states that the Project Manager is involved in Plan Cost Management process. A and D are not correct as both the techniques are used in Estimate Costs process, not Plan Cost Management process. C is wrong, because it’s used as technique for Control Costs process. B is a valid technique used in Plan Cost management process to review strategic funding options and consideration of ways to acquire project resources such as making, purchasing, renting, or leasing. So, among all options provided B is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 238.
Unattempted
The situation states that the Project Manager is involved in Plan Cost Management process. A and D are not correct as both the techniques are used in Estimate Costs process, not Plan Cost Management process. C is wrong, because it’s used as technique for Control Costs process. B is a valid technique used in Plan Cost management process to review strategic funding options and consideration of ways to acquire project resources such as making, purchasing, renting, or leasing. So, among all options provided B is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 238.
Question 36 of 75
36. Question
One of your Project deliverable is ready for customer inspection. Which of the following acts as a key input for the process in relation to Customer inspection?
Correct
Customer inspection of Project deliverables is a part of Validate scope process.
In this very process, Customer inspects the deliverable(s), that is verified by QC team in Control Quality process. In most frequent situation, QC team checks the correctness of the deliverable implemented in recent Direct and Mange Project work process, and marks them as Verified deliverable(s) if all conditions are satisfied. This Verified deliverable(s) acts as an input for Validate Scope process for customer inspection, followed by formal acceptance by customer. Options A and D are not correct because they are output to the Validate Scope process. B is not a valid input for the validate scope process. So among all options provided, C is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 163, 165.
Incorrect
Customer inspection of Project deliverables is a part of Validate scope process.
In this very process, Customer inspects the deliverable(s), that is verified by QC team in Control Quality process. In most frequent situation, QC team checks the correctness of the deliverable implemented in recent Direct and Mange Project work process, and marks them as Verified deliverable(s) if all conditions are satisfied. This Verified deliverable(s) acts as an input for Validate Scope process for customer inspection, followed by formal acceptance by customer. Options A and D are not correct because they are output to the Validate Scope process. B is not a valid input for the validate scope process. So among all options provided, C is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 163, 165.
Unattempted
Customer inspection of Project deliverables is a part of Validate scope process.
In this very process, Customer inspects the deliverable(s), that is verified by QC team in Control Quality process. In most frequent situation, QC team checks the correctness of the deliverable implemented in recent Direct and Mange Project work process, and marks them as Verified deliverable(s) if all conditions are satisfied. This Verified deliverable(s) acts as an input for Validate Scope process for customer inspection, followed by formal acceptance by customer. Options A and D are not correct because they are output to the Validate Scope process. B is not a valid input for the validate scope process. So among all options provided, C is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 163, 165.
Question 37 of 75
37. Question
During planning, the Project Manager and the team are involved in the process of identifying and documenting relationships among the project activities. With the help of a software they are connecting each activity, other than the first and the last one to at least one predecessor and successor activity with an appropriate logical relationship.
Which process is getting performed in this scenario?
Correct
As per the given scenario, the project team is involved in Sequence Activities process where activities are sequenced and proper logical relationships among activities are established to define the logical sequence of work in order to obtain greatest efficiency.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 187, 188.
Incorrect
As per the given scenario, the project team is involved in Sequence Activities process where activities are sequenced and proper logical relationships among activities are established to define the logical sequence of work in order to obtain greatest efficiency.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 187, 188.
Unattempted
As per the given scenario, the project team is involved in Sequence Activities process where activities are sequenced and proper logical relationships among activities are established to define the logical sequence of work in order to obtain greatest efficiency.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 187, 188.
Question 38 of 75
38. Question
As a Project Manager, Ryan is engaged in the development of the Risk Management Plan.
What tools and technique can help him to determine the risk appetite of Project Stakeholders?
Correct
The scenario states that the Project Manager is currently involved in Plan Risk Management process. Options A and C are not correct, because they are used as Tools and Techniques for Identify Risks process. Stakeholder Register is an example for project document, it’s not a Tools and Techniques. So, option D is also not correct. Stakeholder Analysis is a valid Data Analysis technique used in Plan Risk Management Process in order to determine the risk appetite of the project stakeholders. So, among all options provided, Option B is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 401,404.
Incorrect
The scenario states that the Project Manager is currently involved in Plan Risk Management process. Options A and C are not correct, because they are used as Tools and Techniques for Identify Risks process. Stakeholder Register is an example for project document, it’s not a Tools and Techniques. So, option D is also not correct. Stakeholder Analysis is a valid Data Analysis technique used in Plan Risk Management Process in order to determine the risk appetite of the project stakeholders. So, among all options provided, Option B is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 401,404.
Unattempted
The scenario states that the Project Manager is currently involved in Plan Risk Management process. Options A and C are not correct, because they are used as Tools and Techniques for Identify Risks process. Stakeholder Register is an example for project document, it’s not a Tools and Techniques. So, option D is also not correct. Stakeholder Analysis is a valid Data Analysis technique used in Plan Risk Management Process in order to determine the risk appetite of the project stakeholders. So, among all options provided, Option B is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 401,404.
Question 39 of 75
39. Question
Which of the following techniques can be used during closing to evaluate the satisfaction of the stakeholders , gather lessons learned, and to celebrate success?
Correct
During Closing, Meetings can be used to confirm that the deliverables have been accepted, to validate that the exit criteria is met, to evaluate the satisfaction of the stakeholders, gather lessons learned, and to celebrate success. Typically, the types of meetings happen during Closing are: – Close-Out reporting meetings, Customer wrap-up meetings, Lessons learned meetings, and celebration meetings. So , among all options provided, D is the correct answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 127.
Incorrect
During Closing, Meetings can be used to confirm that the deliverables have been accepted, to validate that the exit criteria is met, to evaluate the satisfaction of the stakeholders, gather lessons learned, and to celebrate success. Typically, the types of meetings happen during Closing are: – Close-Out reporting meetings, Customer wrap-up meetings, Lessons learned meetings, and celebration meetings. So , among all options provided, D is the correct answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 127.
Unattempted
During Closing, Meetings can be used to confirm that the deliverables have been accepted, to validate that the exit criteria is met, to evaluate the satisfaction of the stakeholders, gather lessons learned, and to celebrate success. Typically, the types of meetings happen during Closing are: – Close-Out reporting meetings, Customer wrap-up meetings, Lessons learned meetings, and celebration meetings. So , among all options provided, D is the correct answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 127.
Question 40 of 75
40. Question
In an Internal project initiated by a car manufacturing company, several Subject Matter Experts have gathered to decide the outcome of a deliverable in regard to its formal acceptance. Ultimately a decision making technique that is also been used in requirement gathering as well as making decisions on Change Request has been applied to reach a consensus.
What decision making technique has been used in the given scenario?
Correct
The question here talks about Validate Scope process and several experts have to decide the Formal acceptance of a deliverable. Voting is a decision making technique which is widely used in this process to reach a decision or judgement.
B is a technique used in validate scope process but it’s not a Decision Making technique. So, B is not correct. C is again not a decision making technique, so C is also not correct. D is an example decision making technique but generally not used in Validate Scope process. Further in “Autocratic decision making”, one individual takes a decision, but here the question clearly stated about reaching consensus or agreement by applying a decision making technique. So, D is also in correct.
Voting is a decision making technique that is applied, to reach a consensus. Other than Validate scope process, it’s also used in Collect Requirement and Perform Integrated Change Control processes as stated in the question. Therefore, among all options provided, A is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 163, 166, 113,138.
Incorrect
The question here talks about Validate Scope process and several experts have to decide the Formal acceptance of a deliverable. Voting is a decision making technique which is widely used in this process to reach a decision or judgement.
B is a technique used in validate scope process but it’s not a Decision Making technique. So, B is not correct. C is again not a decision making technique, so C is also not correct. D is an example decision making technique but generally not used in Validate Scope process. Further in “Autocratic decision making”, one individual takes a decision, but here the question clearly stated about reaching consensus or agreement by applying a decision making technique. So, D is also in correct.
Voting is a decision making technique that is applied, to reach a consensus. Other than Validate scope process, it’s also used in Collect Requirement and Perform Integrated Change Control processes as stated in the question. Therefore, among all options provided, A is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 163, 166, 113,138.
Unattempted
The question here talks about Validate Scope process and several experts have to decide the Formal acceptance of a deliverable. Voting is a decision making technique which is widely used in this process to reach a decision or judgement.
B is a technique used in validate scope process but it’s not a Decision Making technique. So, B is not correct. C is again not a decision making technique, so C is also not correct. D is an example decision making technique but generally not used in Validate Scope process. Further in “Autocratic decision making”, one individual takes a decision, but here the question clearly stated about reaching consensus or agreement by applying a decision making technique. So, D is also in correct.
Voting is a decision making technique that is applied, to reach a consensus. Other than Validate scope process, it’s also used in Collect Requirement and Perform Integrated Change Control processes as stated in the question. Therefore, among all options provided, A is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 163, 166, 113,138.
Question 41 of 75
41. Question
Your project is near completion and the entire Project Team is involved in a process that involves the confirmation of the formal acceptance of the final product.
Which of the following is not an input of the process mentioned in the above scenario?
Correct
The question here talks about Close project or phase process. A, B, D are valid input to the process. EEF is not an input to the Close Project or Phase process. So, among all options provided C is the correct answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 121.
Incorrect
The question here talks about Close project or phase process. A, B, D are valid input to the process. EEF is not an input to the Close Project or Phase process. So, among all options provided C is the correct answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 121.
Unattempted
The question here talks about Close project or phase process. A, B, D are valid input to the process. EEF is not an input to the Close Project or Phase process. So, among all options provided C is the correct answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 121.
Question 42 of 75
42. Question
Arun is the sponsor of a software development project. He has involved few experts in the preparation of Project Charter.
Which of the following is an example of tools and technique that can be used in the process of developing the Project Charter?
Correct
The scenario states that Arun, the sponsor has involved few experts in Develop Project Charter process. The Develop Project Charter is the process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. This process has four tools and techniques: Expert Judgement, Data Gathering, Interpersonal and Team skills (Conflict management, facilitation, etc.), Meetings.
A and B are not examples of Tools and Techniques, so they are not correct. C is a tools and technique but not used in Develop Project Charter process. Conflict management is an example of interpersonal and team skills technique used in the Develop Project Charter process. Conflict management can be helpful in bringing stakeholders into alignment on various elements of the charter. So , among all options provided D is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 75,80.
Incorrect
The scenario states that Arun, the sponsor has involved few experts in Develop Project Charter process. The Develop Project Charter is the process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. This process has four tools and techniques: Expert Judgement, Data Gathering, Interpersonal and Team skills (Conflict management, facilitation, etc.), Meetings.
A and B are not examples of Tools and Techniques, so they are not correct. C is a tools and technique but not used in Develop Project Charter process. Conflict management is an example of interpersonal and team skills technique used in the Develop Project Charter process. Conflict management can be helpful in bringing stakeholders into alignment on various elements of the charter. So , among all options provided D is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 75,80.
Unattempted
The scenario states that Arun, the sponsor has involved few experts in Develop Project Charter process. The Develop Project Charter is the process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. This process has four tools and techniques: Expert Judgement, Data Gathering, Interpersonal and Team skills (Conflict management, facilitation, etc.), Meetings.
A and B are not examples of Tools and Techniques, so they are not correct. C is a tools and technique but not used in Develop Project Charter process. Conflict management is an example of interpersonal and team skills technique used in the Develop Project Charter process. Conflict management can be helpful in bringing stakeholders into alignment on various elements of the charter. So , among all options provided D is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 75,80.
Question 43 of 75
43. Question
You are looking for information on personnel rates, travel costs, and other costs that are needed to estimate the overall project budget.
Where is the best place to find this information?
Correct
The scenario suggests you are carrying out the Determine Budget process. Basis of Estimates is an input to the process but it contains supporting details of cost estimates. It generally specifies any basic assumptions dealing with inclusion or exclusion of indirect or other costs in the project budget, so A is not correct. B is not an input for Determine Budget process, so B is not correct. D is an input for the Determine Budget process, but Cost Management Plan describes how the project cost will be structured in the project budget. So, D is also wrong. Based on elimination rule, C is the right answer. Further, the Resource Management Plan which is a valid input to the process, provides information on rates (personnel and other resources), estimation of travel costs, and other foreseen costs that are necessary to estimate the overall project budget. Therefore among all options provided, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 250.
Incorrect
The scenario suggests you are carrying out the Determine Budget process. Basis of Estimates is an input to the process but it contains supporting details of cost estimates. It generally specifies any basic assumptions dealing with inclusion or exclusion of indirect or other costs in the project budget, so A is not correct. B is not an input for Determine Budget process, so B is not correct. D is an input for the Determine Budget process, but Cost Management Plan describes how the project cost will be structured in the project budget. So, D is also wrong. Based on elimination rule, C is the right answer. Further, the Resource Management Plan which is a valid input to the process, provides information on rates (personnel and other resources), estimation of travel costs, and other foreseen costs that are necessary to estimate the overall project budget. Therefore among all options provided, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 250.
Unattempted
The scenario suggests you are carrying out the Determine Budget process. Basis of Estimates is an input to the process but it contains supporting details of cost estimates. It generally specifies any basic assumptions dealing with inclusion or exclusion of indirect or other costs in the project budget, so A is not correct. B is not an input for Determine Budget process, so B is not correct. D is an input for the Determine Budget process, but Cost Management Plan describes how the project cost will be structured in the project budget. So, D is also wrong. Based on elimination rule, C is the right answer. Further, the Resource Management Plan which is a valid input to the process, provides information on rates (personnel and other resources), estimation of travel costs, and other foreseen costs that are necessary to estimate the overall project budget. Therefore among all options provided, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 250.
Question 44 of 75
44. Question
The Checklists are important tools used in Quality Management. Checklists are examples of which of the following tools and techniques?
Correct
Checklists are examples of data gathering technique that is generally used to check if a list of requirements has been satisfied.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 288, 292.
Incorrect
Checklists are examples of data gathering technique that is generally used to check if a list of requirements has been satisfied.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 288, 292.
Unattempted
Checklists are examples of data gathering technique that is generally used to check if a list of requirements has been satisfied.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 288, 292.
Question 45 of 75
45. Question
The technology and functional experts of an IT organization have gathered to come up with a procurement strategy and bid documents for company’s Next Gen IT innovation project. Procurement strategy and Bid documents are created as a part of which of the following processes?
Correct
Procurement Strategy and Bid documents are output for Plan Procurement Management process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 466, 476,477.
Incorrect
Procurement Strategy and Bid documents are output for Plan Procurement Management process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 466, 476,477.
Unattempted
Procurement Strategy and Bid documents are output for Plan Procurement Management process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 466, 476,477.
Question 46 of 75
46. Question
Expert Judgement is an example of Important Tools and Techniques used in Project Management. Expert judgment is a tool and technique used in all of the following processes except:
Correct
A, B, C are not correct. In Implement Risk responses process, experts with specialized knowledge are sometimes required to validate or modify risk responses if needed. Expert Judgement is used in Conduct Procurements to evaluate proposals. In Identify Stakeholder process, it is used to ensure all stakeholders have been identified, listed, and assessed appropriately.
By following elimination rule, D is the right answer. Further, Manage Communications is part of the Executing Process Group. As per PMBOK6, expert judgment is not required while managing communications.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 378.
Incorrect
A, B, C are not correct. In Implement Risk responses process, experts with specialized knowledge are sometimes required to validate or modify risk responses if needed. Expert Judgement is used in Conduct Procurements to evaluate proposals. In Identify Stakeholder process, it is used to ensure all stakeholders have been identified, listed, and assessed appropriately.
By following elimination rule, D is the right answer. Further, Manage Communications is part of the Executing Process Group. As per PMBOK6, expert judgment is not required while managing communications.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 378.
Unattempted
A, B, C are not correct. In Implement Risk responses process, experts with specialized knowledge are sometimes required to validate or modify risk responses if needed. Expert Judgement is used in Conduct Procurements to evaluate proposals. In Identify Stakeholder process, it is used to ensure all stakeholders have been identified, listed, and assessed appropriately.
By following elimination rule, D is the right answer. Further, Manage Communications is part of the Executing Process Group. As per PMBOK6, expert judgment is not required while managing communications.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 378.
Question 47 of 75
47. Question
The Control Quality process uses several tools and techniques to ensure the project outputs are complete, correct, and meet customer expectations.
Which of the following is not an example of tools and techniques used in used in control quality process?
Correct
A , C, D are tools and techniques used in Control quality process. B is an example of a technique used in Manage Quality process. Among all options provided, B is right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 295, 298.
Incorrect
A , C, D are tools and techniques used in Control quality process. B is an example of a technique used in Manage Quality process. Among all options provided, B is right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 295, 298.
Unattempted
A , C, D are tools and techniques used in Control quality process. B is an example of a technique used in Manage Quality process. Among all options provided, B is right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 295, 298.
Question 48 of 75
48. Question
The Organization Process Assets play a huge role in influencing the management of a project. Organization Process Assets may get updated as an output in which of the following processes?
Correct
In most of the processes, Organization Process Assets(OPA) acts as an input. But there are few processes where OPA gets updated as an output, Manage Project Knowledge is one of them. Other processes where OPA gets updated as an output are: – Manage Communication, Acquire Resources, Develop Team, Monitor Risks, Plan Procurement Management, Control Procurements, Close project/phase.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 98.
Incorrect
In most of the processes, Organization Process Assets(OPA) acts as an input. But there are few processes where OPA gets updated as an output, Manage Project Knowledge is one of them. Other processes where OPA gets updated as an output are: – Manage Communication, Acquire Resources, Develop Team, Monitor Risks, Plan Procurement Management, Control Procurements, Close project/phase.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 98.
Unattempted
In most of the processes, Organization Process Assets(OPA) acts as an input. But there are few processes where OPA gets updated as an output, Manage Project Knowledge is one of them. Other processes where OPA gets updated as an output are: – Manage Communication, Acquire Resources, Develop Team, Monitor Risks, Plan Procurement Management, Control Procurements, Close project/phase.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 98.
Question 49 of 75
49. Question
During inspection, the customer asks the Project Manager if the software that the project has developed so far conforms to all the requirements.
What should be used to measure completion of the product scope?
Correct
The given scenario indicates that the Validate Scope process is getting conducted to measure completion of the product scope.
The completion of the project scope is measured against the components of the project management plan, i.e. scope baseline. Completion of the product scope is measured against the product requirements documentation, which also serves as an input to the validate scope process. So, among all options provided B is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 131,165.
Incorrect
The given scenario indicates that the Validate Scope process is getting conducted to measure completion of the product scope.
The completion of the project scope is measured against the components of the project management plan, i.e. scope baseline. Completion of the product scope is measured against the product requirements documentation, which also serves as an input to the validate scope process. So, among all options provided B is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 131,165.
Unattempted
The given scenario indicates that the Validate Scope process is getting conducted to measure completion of the product scope.
The completion of the project scope is measured against the components of the project management plan, i.e. scope baseline. Completion of the product scope is measured against the product requirements documentation, which also serves as an input to the validate scope process. So, among all options provided B is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 131,165.
Question 50 of 75
50. Question
Meetings are used as a tool and technique in many project management processes. Which of the processes below do not use meetings as a tool or technique?
Correct
Options A, B, C uses meeting as a technique. Meetings are not among the tools and techniques explicitly listed for the Define Scope process. So, among all options, option D is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 150,692.
Incorrect
Options A, B, C uses meeting as a technique. Meetings are not among the tools and techniques explicitly listed for the Define Scope process. So, among all options, option D is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 150,692.
Unattempted
Options A, B, C uses meeting as a technique. Meetings are not among the tools and techniques explicitly listed for the Define Scope process. So, among all options, option D is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 150,692.
Question 51 of 75
51. Question
The Project Team is currently engaged in using an iterative planning technique in which they are doing detailed planning for work to be accomplished in near term, but for future work they are only doing high level planning.
What process is getting executed in the current scenario?
Correct
The scenario states that the project team is currently engaged in applying Rolling Wave planning technique where work to be done in near term is planned in detail, whereas the work to be done in future is planned at higher level. Further this technique is effectively used in Define Activities process for planning the work to be accomplished. So, among all options available, option A is the right choice.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 185.
Incorrect
The scenario states that the project team is currently engaged in applying Rolling Wave planning technique where work to be done in near term is planned in detail, whereas the work to be done in future is planned at higher level. Further this technique is effectively used in Define Activities process for planning the work to be accomplished. So, among all options available, option A is the right choice.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 185.
Unattempted
The scenario states that the project team is currently engaged in applying Rolling Wave planning technique where work to be done in near term is planned in detail, whereas the work to be done in future is planned at higher level. Further this technique is effectively used in Define Activities process for planning the work to be accomplished. So, among all options available, option A is the right choice.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 185.
Question 52 of 75
52. Question
You are a new Project Manager who has joined during the mid of execution. You want to review the planned training strategies for all your team members.
What should you refer to fetch this information?
Correct
Here in this scenario, Resource Management Plan should be referred as Training strategies for team members are recorded in Resource Management Plan.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 319.
Incorrect
Here in this scenario, Resource Management Plan should be referred as Training strategies for team members are recorded in Resource Management Plan.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 319.
Unattempted
Here in this scenario, Resource Management Plan should be referred as Training strategies for team members are recorded in Resource Management Plan.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 319.
Question 53 of 75
53. Question
As a Project Manager, you are engaged in the process of communicating and working with stakeholders to meet their needs, expectations, and foster appropriate stakeholder involvement.
What should you refer to determine the methods, format, and technologies to be used for stakeholder communication?
Correct
The scenario states that the Project Manager is involved in Manage Stakeholder Engagement Process. All 4 given options are input to the process. But it’s the communications management plan , that provides all the communications details for stakeholder engagement that includes methods, formats, and technologies to be used for stakeholder communication. So, among all options provided C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 523, 525.
Incorrect
The scenario states that the Project Manager is involved in Manage Stakeholder Engagement Process. All 4 given options are input to the process. But it’s the communications management plan , that provides all the communications details for stakeholder engagement that includes methods, formats, and technologies to be used for stakeholder communication. So, among all options provided C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 523, 525.
Unattempted
The scenario states that the Project Manager is involved in Manage Stakeholder Engagement Process. All 4 given options are input to the process. But it’s the communications management plan , that provides all the communications details for stakeholder engagement that includes methods, formats, and technologies to be used for stakeholder communication. So, among all options provided C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 523, 525.
Question 54 of 75
54. Question
Which of the following components of the project management plan is an input to the Plan Risk Management process?
Correct
All Components of the Project Management Plan are inputs to the Plan Risk Management Process. Information in the various project management plan components might influence the Plan Risk Management process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 401-403.
Incorrect
All Components of the Project Management Plan are inputs to the Plan Risk Management Process. Information in the various project management plan components might influence the Plan Risk Management process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 401-403.
Unattempted
All Components of the Project Management Plan are inputs to the Plan Risk Management Process. Information in the various project management plan components might influence the Plan Risk Management process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 401-403.
Question 55 of 75
55. Question
The following process ensures that the project stays aligned with the business needs and also helps in comparison of the actual project performance against the project management plan.
What process is referred in the given scenario?
Correct
B is not correct, because Perform Integrated Change Control process manages the change requests raised across the life cycle of the project. C is incorrect because the control scope process only manages the changes to the scope baseline, it doesn’t compare project performance against the project management plan. D is incorrect because Define Scope is a process of Planning process group which mainly deals with project inclusions and exclusions. So, by applying elimination technique, A is the right answer. Further, Monitor and Control Project Work is the process of tracking, reviewing, the overall project progress to meet the performance objectives defined in the Project Management Plan. This is accomplished by comparing actual project performance against the Project Management Plan on a regular basis. So, among all options provided, option A is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 222-223, 228.
Incorrect
B is not correct, because Perform Integrated Change Control process manages the change requests raised across the life cycle of the project. C is incorrect because the control scope process only manages the changes to the scope baseline, it doesn’t compare project performance against the project management plan. D is incorrect because Define Scope is a process of Planning process group which mainly deals with project inclusions and exclusions. So, by applying elimination technique, A is the right answer. Further, Monitor and Control Project Work is the process of tracking, reviewing, the overall project progress to meet the performance objectives defined in the Project Management Plan. This is accomplished by comparing actual project performance against the Project Management Plan on a regular basis. So, among all options provided, option A is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 222-223, 228.
Unattempted
B is not correct, because Perform Integrated Change Control process manages the change requests raised across the life cycle of the project. C is incorrect because the control scope process only manages the changes to the scope baseline, it doesn’t compare project performance against the project management plan. D is incorrect because Define Scope is a process of Planning process group which mainly deals with project inclusions and exclusions. So, by applying elimination technique, A is the right answer. Further, Monitor and Control Project Work is the process of tracking, reviewing, the overall project progress to meet the performance objectives defined in the Project Management Plan. This is accomplished by comparing actual project performance against the Project Management Plan on a regular basis. So, among all options provided, option A is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 222-223, 228.
Question 56 of 75
56. Question
As a Project Manager, you are in process of developing the approved version of the time-phased project budget. Which of the following acts as an important output to the process?
Correct
The scenario states that the Project Manager is performing the Determine Budget process. The major output for the process is cost baseline, which is not there in option. Other than cost baseline, project funding requirements, project document updates (cost estimates, project schedule, risk register) are other outputs.
Option A is an input to Determine Budget process, so A is not correct. Option B is a technique used in the Determine Budget process, and it’s not an output. Cost Management Plan is not updated as a part of Determine budget process, so D is also not correct. Project funding requirements include total funding requirements and periodic funding requirements (e.g., Quarterly, annually) and acts as a valid output for Determine Budget process. So, among all options, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 248, 256.
Incorrect
The scenario states that the Project Manager is performing the Determine Budget process. The major output for the process is cost baseline, which is not there in option. Other than cost baseline, project funding requirements, project document updates (cost estimates, project schedule, risk register) are other outputs.
Option A is an input to Determine Budget process, so A is not correct. Option B is a technique used in the Determine Budget process, and it’s not an output. Cost Management Plan is not updated as a part of Determine budget process, so D is also not correct. Project funding requirements include total funding requirements and periodic funding requirements (e.g., Quarterly, annually) and acts as a valid output for Determine Budget process. So, among all options, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 248, 256.
Unattempted
The scenario states that the Project Manager is performing the Determine Budget process. The major output for the process is cost baseline, which is not there in option. Other than cost baseline, project funding requirements, project document updates (cost estimates, project schedule, risk register) are other outputs.
Option A is an input to Determine Budget process, so A is not correct. Option B is a technique used in the Determine Budget process, and it’s not an output. Cost Management Plan is not updated as a part of Determine budget process, so D is also not correct. Project funding requirements include total funding requirements and periodic funding requirements (e.g., Quarterly, annually) and acts as a valid output for Determine Budget process. So, among all options, C is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 248, 256.
Question 57 of 75
57. Question
Your project has successfully moved to the Closing phase. You want to know who will sign off the project.
What needs to be reviewed here?
Correct
In this scenario, the Project Charter should be reviewed to know the approval requirements, and who will sign off the project. Some may get confused with agreements i.e. option C, but Agreements takes care of contract closure, not project closure.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 124.
Incorrect
In this scenario, the Project Charter should be reviewed to know the approval requirements, and who will sign off the project. Some may get confused with agreements i.e. option C, but Agreements takes care of contract closure, not project closure.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 124.
Unattempted
In this scenario, the Project Charter should be reviewed to know the approval requirements, and who will sign off the project. Some may get confused with agreements i.e. option C, but Agreements takes care of contract closure, not project closure.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 124.
Question 58 of 75
58. Question
Networking is an example of an interpersonal and team skills that creates the conditions for project team to share knowledge among one another.
Which of the following processes uses networking as tools and technique?
Correct
Networking is an example of tool and technique used in processes like Manage Project Knowledge, Manage Communications, Monitor Stakeholder Engagement , that creates the condition to share tacit and explicit knowledge for stakeholders in an informal fashion.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 98, 104.
Incorrect
Networking is an example of tool and technique used in processes like Manage Project Knowledge, Manage Communications, Monitor Stakeholder Engagement , that creates the condition to share tacit and explicit knowledge for stakeholders in an informal fashion.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 98, 104.
Unattempted
Networking is an example of tool and technique used in processes like Manage Project Knowledge, Manage Communications, Monitor Stakeholder Engagement , that creates the condition to share tacit and explicit knowledge for stakeholders in an informal fashion.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 98, 104.
Question 59 of 75
59. Question
Project KPIs are measurable indicators that help to track the performance of project.
Which of the following processes generates KPIs for the first time?
Correct
KPIs are example for Work Performance Data(WPD) which is generated as an output for Direct and Manage Project work process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 90, 95.
Incorrect
KPIs are example for Work Performance Data(WPD) which is generated as an output for Direct and Manage Project work process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 90, 95.
Unattempted
KPIs are example for Work Performance Data(WPD) which is generated as an output for Direct and Manage Project work process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 90, 95.
Question 60 of 75
60. Question
An unknown-unknown risk has occurred. The Project Team has planned a workaround. Workaround gets implemented as a part of which of the following processes?
Correct
Some may get confused with C, but Implement Risk responses are for Known-Unknown risks. Workaround is planned when an unknown risk occurs in the project. They are identified as a part of Monitor Risks process, where the project team, post identification raises a change request (also a valid output for the process) that gets processed for review and disposition through Perform Integrated Change Control process and ultimately when approved gets implemented as a part of the Direct and Manage Project Work process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 457.
**Workaround is not part of PMBOK6, but we must remember PMP exam is beyond PMBOK. It availabe in Rita and other Project Management books.
Incorrect
Some may get confused with C, but Implement Risk responses are for Known-Unknown risks. Workaround is planned when an unknown risk occurs in the project. They are identified as a part of Monitor Risks process, where the project team, post identification raises a change request (also a valid output for the process) that gets processed for review and disposition through Perform Integrated Change Control process and ultimately when approved gets implemented as a part of the Direct and Manage Project Work process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 457.
**Workaround is not part of PMBOK6, but we must remember PMP exam is beyond PMBOK. It availabe in Rita and other Project Management books.
Unattempted
Some may get confused with C, but Implement Risk responses are for Known-Unknown risks. Workaround is planned when an unknown risk occurs in the project. They are identified as a part of Monitor Risks process, where the project team, post identification raises a change request (also a valid output for the process) that gets processed for review and disposition through Perform Integrated Change Control process and ultimately when approved gets implemented as a part of the Direct and Manage Project Work process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 457.
**Workaround is not part of PMBOK6, but we must remember PMP exam is beyond PMBOK. It availabe in Rita and other Project Management books.
Question 61 of 75
61. Question
Quality Function Deployment (QFD) is a technique popularly used in manufacturing industries to determine critical characteristics for new product development.
QFD is an example of which of following types of tools and technique?
Correct
Quality Function Deployment (QFD) is a Facilitation technique widely used in Manufacturing industry that helps to determine critical characteristics of a new product. QFD starts by collecting customer needs, also known as Voice of the Customer. These needs are then objectively sorted and prioritized, and goals are set for achieving them.
QFD, that falls under Facilitation technique category is an example of Interpersonal and Team Skills technique used during Collect Requirements process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 145.
Incorrect
Quality Function Deployment (QFD) is a Facilitation technique widely used in Manufacturing industry that helps to determine critical characteristics of a new product. QFD starts by collecting customer needs, also known as Voice of the Customer. These needs are then objectively sorted and prioritized, and goals are set for achieving them.
QFD, that falls under Facilitation technique category is an example of Interpersonal and Team Skills technique used during Collect Requirements process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 145.
Unattempted
Quality Function Deployment (QFD) is a Facilitation technique widely used in Manufacturing industry that helps to determine critical characteristics of a new product. QFD starts by collecting customer needs, also known as Voice of the Customer. These needs are then objectively sorted and prioritized, and goals are set for achieving them.
QFD, that falls under Facilitation technique category is an example of Interpersonal and Team Skills technique used during Collect Requirements process.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 145.
Question 62 of 75
62. Question
Which of the following Data Representation tools and techniques is used in both Plan Stakeholder Engagement as well as Monitor Stakeholder Engagement process?
Correct
Mind Mapping is an example of Data Representation tools and Technique used Plan Stakeholder Engagement process, but not in Monitor Stakeholder Engagement process, so A is not correct. Multi-criteria Decision Analysis is an example decision analysis tools and techniques which is used in Monitor Stakeholder Engagement process, but not Plan Stakeholder Engagement process, so B is also not correct. Presentations are example communication skills used in Monitor Stakeholder Engagement process, but not Plan Stakeholder Engagement process, so C is not correct. Stakeholder Engagement Assessment Matrix is an example of Data Representation technique used in both Plan Stakeholder Engagement as well as Monitor Stakeholder Engagement process.
So, among all options, Option D is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 516, 530.
Incorrect
Mind Mapping is an example of Data Representation tools and Technique used Plan Stakeholder Engagement process, but not in Monitor Stakeholder Engagement process, so A is not correct. Multi-criteria Decision Analysis is an example decision analysis tools and techniques which is used in Monitor Stakeholder Engagement process, but not Plan Stakeholder Engagement process, so B is also not correct. Presentations are example communication skills used in Monitor Stakeholder Engagement process, but not Plan Stakeholder Engagement process, so C is not correct. Stakeholder Engagement Assessment Matrix is an example of Data Representation technique used in both Plan Stakeholder Engagement as well as Monitor Stakeholder Engagement process.
So, among all options, Option D is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 516, 530.
Unattempted
Mind Mapping is an example of Data Representation tools and Technique used Plan Stakeholder Engagement process, but not in Monitor Stakeholder Engagement process, so A is not correct. Multi-criteria Decision Analysis is an example decision analysis tools and techniques which is used in Monitor Stakeholder Engagement process, but not Plan Stakeholder Engagement process, so B is also not correct. Presentations are example communication skills used in Monitor Stakeholder Engagement process, but not Plan Stakeholder Engagement process, so C is not correct. Stakeholder Engagement Assessment Matrix is an example of Data Representation technique used in both Plan Stakeholder Engagement as well as Monitor Stakeholder Engagement process.
So, among all options, Option D is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 516, 530.
Question 63 of 75
63. Question
Performance Measurement Baseline, the additional component for Project Management Plan is an integrated scope-schedule-cost plan for the project work against which project execution is compared to measure and manage performance.
Performance Measurement Baseline acts as an input to which of the following processes?
Correct
Performance Measurement Baseline is an additional component for the Project Management Plan. Its returned as an output for Develop Project Management Plan process, So B is not the right answer. C and D doesn’t have Performance Measurement Baseline as input or output, so C and D are incorrect. Performance Measurement Baseline acts as a valid input for Control Scope process. In Control Scope process, when Earned Value analysis is used, Performance Measurement Baseline is compared to actual results to determine if a change, corrective action or preventive action is necessary. So, among all options provided A is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 169.
Incorrect
Performance Measurement Baseline is an additional component for the Project Management Plan. Its returned as an output for Develop Project Management Plan process, So B is not the right answer. C and D doesn’t have Performance Measurement Baseline as input or output, so C and D are incorrect. Performance Measurement Baseline acts as a valid input for Control Scope process. In Control Scope process, when Earned Value analysis is used, Performance Measurement Baseline is compared to actual results to determine if a change, corrective action or preventive action is necessary. So, among all options provided A is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 169.
Unattempted
Performance Measurement Baseline is an additional component for the Project Management Plan. Its returned as an output for Develop Project Management Plan process, So B is not the right answer. C and D doesn’t have Performance Measurement Baseline as input or output, so C and D are incorrect. Performance Measurement Baseline acts as a valid input for Control Scope process. In Control Scope process, when Earned Value analysis is used, Performance Measurement Baseline is compared to actual results to determine if a change, corrective action or preventive action is necessary. So, among all options provided A is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 169.
Question 64 of 75
64. Question
Which of the following is NOT an example for tools or techniques used in the Conduct Procurements process?
Correct
A, B, D are valid examples of Tools and Techniques in conduct procurement process. Source Selection Criteria (Procurement Documentation) describe how bidder proposals will be evaluated. It’s an input to the Conduct Procurement process, and does not belong to Tools and Techniques category.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 482,485.
Incorrect
A, B, D are valid examples of Tools and Techniques in conduct procurement process. Source Selection Criteria (Procurement Documentation) describe how bidder proposals will be evaluated. It’s an input to the Conduct Procurement process, and does not belong to Tools and Techniques category.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 482,485.
Unattempted
A, B, D are valid examples of Tools and Techniques in conduct procurement process. Source Selection Criteria (Procurement Documentation) describe how bidder proposals will be evaluated. It’s an input to the Conduct Procurement process, and does not belong to Tools and Techniques category.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 482,485.
Question 65 of 75
65. Question
A Change Request for modification of Procurement Statement of Work has been approved by following defined Change Control process. The approved Change Request generated by the Perform Integrated Change Control process in this situation becomes input to which of the following processes?
Correct
Approved Change Requests generated by Perform Integrated Change Control process becomes input to Direct and Manage Project Work, Control Quality and Control Procurements processes. Option A and C are not correct because these processes don’t have Approved Change Request as input. Though Control Quality process has Approved Change request as input but Approved Change Requests for Control Quality process only gets affected by actions like defect repair, preventive or corrective actions, and it never includes any requests in relation to modification of contracts or related contractual documents. Approved change requests such as modifications to the contract or the procurement statement of work would affect the Control Procurements process and it also acts as valid input to the process. So, among all options provided D is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 492,496.
Incorrect
Approved Change Requests generated by Perform Integrated Change Control process becomes input to Direct and Manage Project Work, Control Quality and Control Procurements processes. Option A and C are not correct because these processes don’t have Approved Change Request as input. Though Control Quality process has Approved Change request as input but Approved Change Requests for Control Quality process only gets affected by actions like defect repair, preventive or corrective actions, and it never includes any requests in relation to modification of contracts or related contractual documents. Approved change requests such as modifications to the contract or the procurement statement of work would affect the Control Procurements process and it also acts as valid input to the process. So, among all options provided D is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 492,496.
Unattempted
Approved Change Requests generated by Perform Integrated Change Control process becomes input to Direct and Manage Project Work, Control Quality and Control Procurements processes. Option A and C are not correct because these processes don’t have Approved Change Request as input. Though Control Quality process has Approved Change request as input but Approved Change Requests for Control Quality process only gets affected by actions like defect repair, preventive or corrective actions, and it never includes any requests in relation to modification of contracts or related contractual documents. Approved change requests such as modifications to the contract or the procurement statement of work would affect the Control Procurements process and it also acts as valid input to the process. So, among all options provided D is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 492,496.
Question 66 of 75
66. Question
Entire Project Management Team is attending a workshop conducted by a trained moderator to rank most useful ideas for further brainstorming or for prioritization.
What tools and techniques has been referred in this scenario?
Correct
Nominal group technique is part of the Interpersonal and team skills category of technique. It is a technique that enhances brainstorming with a voting process used to rank the most useful ideas for further brainstorming or for prioritization. It is a structured form of brainstorming that involves the entire group of stakeholders participating in requirement gathering ( Collect Requirements) process .
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 144.
Incorrect
Nominal group technique is part of the Interpersonal and team skills category of technique. It is a technique that enhances brainstorming with a voting process used to rank the most useful ideas for further brainstorming or for prioritization. It is a structured form of brainstorming that involves the entire group of stakeholders participating in requirement gathering ( Collect Requirements) process .
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 144.
Unattempted
Nominal group technique is part of the Interpersonal and team skills category of technique. It is a technique that enhances brainstorming with a voting process used to rank the most useful ideas for further brainstorming or for prioritization. It is a structured form of brainstorming that involves the entire group of stakeholders participating in requirement gathering ( Collect Requirements) process .
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 144.
Question 67 of 75
67. Question
CCB has approved 4, deferred 2, and rejected 3 change requests. As a result of this, which of the following gets updated in the next step to record all these CCB decisions?
Correct
The disposition of all Change Requests are recorded in the Change log as a part of project document update. Change Log is also an example for a project document that maintains the status of all change request. So, among all options, A is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 120.
Incorrect
The disposition of all Change Requests are recorded in the Change log as a part of project document update. Change Log is also an example for a project document that maintains the status of all change request. So, among all options, A is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 120.
Unattempted
The disposition of all Change Requests are recorded in the Change log as a part of project document update. Change Log is also an example for a project document that maintains the status of all change request. So, among all options, A is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 120.
Question 68 of 75
68. Question
Decomposition is a popular technique used for dividing and subdividing the project scope and project deliverables into smaller, and more manageable parts.
Decomposition is used as tool and technique in which of the two processes?
Correct
Decomposition is explicitly listed as a tools and techniques for both the Create WBS and the Define Activities processes. So, among all option C is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 156,185.
Incorrect
Decomposition is explicitly listed as a tools and techniques for both the Create WBS and the Define Activities processes. So, among all option C is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 156,185.
Unattempted
Decomposition is explicitly listed as a tools and techniques for both the Create WBS and the Define Activities processes. So, among all option C is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 156,185.
Question 69 of 75
69. Question
The following technique is used in both Plan Communication Management as well as Monitor Stakeholder Engagement processes to understand the strategies of the organization, know who wields power and influence, and to develop a communication strategy.
What tool and technique is mentioned in the given scenario?
Correct
A is not correct, because Networking is used as technique in Monitor Stakeholder Engagement process but not used in Plan Communication Management process. Communication styles assessment and Expert judgement are used in Plan Communications Management process but not in Monitor Stakeholder Engagement process, so both C and D are also not correct. By following elimination rule, and PMBOK 6; B is the right answer as Political awareness is used in both Plan Communication Management as well as Monitor Stakeholder Engagement processes. Political awareness helps the project manager to develop communication strategies to connect with stakeholders by understanding who wields power and influence in the required field.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 366,530, 534.
Incorrect
A is not correct, because Networking is used as technique in Monitor Stakeholder Engagement process but not used in Plan Communication Management process. Communication styles assessment and Expert judgement are used in Plan Communications Management process but not in Monitor Stakeholder Engagement process, so both C and D are also not correct. By following elimination rule, and PMBOK 6; B is the right answer as Political awareness is used in both Plan Communication Management as well as Monitor Stakeholder Engagement processes. Political awareness helps the project manager to develop communication strategies to connect with stakeholders by understanding who wields power and influence in the required field.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 366,530, 534.
Unattempted
A is not correct, because Networking is used as technique in Monitor Stakeholder Engagement process but not used in Plan Communication Management process. Communication styles assessment and Expert judgement are used in Plan Communications Management process but not in Monitor Stakeholder Engagement process, so both C and D are also not correct. By following elimination rule, and PMBOK 6; B is the right answer as Political awareness is used in both Plan Communication Management as well as Monitor Stakeholder Engagement processes. Political awareness helps the project manager to develop communication strategies to connect with stakeholders by understanding who wields power and influence in the required field.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 366,530, 534.
Question 70 of 75
70. Question
A Project Manager of a large project goes for a long sabbatical leave just a week before Project kick-off meeting. Ryan is the new Project Manager who has joined as his replacement. As a newly joined Project Manager, he wants to know what development approach has been decided to follow in the project.
What should Ryan refer to fetch this necessary information?
Correct
Here in the scenario, the newly joined Project Manager should review the Project Management Plan. Development approach is the additional component for Project Management Plan that defines whether predictive, Iterative, agile, or a hybrid model or development approach or model should be used.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 88.
Incorrect
Here in the scenario, the newly joined Project Manager should review the Project Management Plan. Development approach is the additional component for Project Management Plan that defines whether predictive, Iterative, agile, or a hybrid model or development approach or model should be used.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 88.
Unattempted
Here in the scenario, the newly joined Project Manager should review the Project Management Plan. Development approach is the additional component for Project Management Plan that defines whether predictive, Iterative, agile, or a hybrid model or development approach or model should be used.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 88.
Question 71 of 75
71. Question
Ground rules set the expected behaviors of the project team members, with regard to stakeholder engagement.
Which of the following processes define Ground rules?
Correct
The Ground rules are defined in the Team Charter which is an output for Plan Resource Management Process. So, among all options, D is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 312, 320, 528.
Incorrect
The Ground rules are defined in the Team Charter which is an output for Plan Resource Management Process. So, among all options, D is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 312, 320, 528.
Unattempted
The Ground rules are defined in the Team Charter which is an output for Plan Resource Management Process. So, among all options, D is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 312, 320, 528.
Question 72 of 75
72. Question
Ryan is a Project Manager of complex engineering project. He along with all risk owners have just completed an important risk management process and updated Risk register with information on agreed-upon risk response strategies, triggers, warning signs of risk occurrence, residual risks that are expected to remain because they are deliberately accepted.
What risk management process has been concluded in the given scenario?
Correct
The situation states that the project manager as well as the risk owners has just concluded the Plan Risk Responses process. Risk Register gets updated as a valid output for Plan Risk Response process with information like agreed-upon response strategies, triggers, warning signs of risk occurrence, residual risks that are expected to remain because they are deliberately accepted, etc.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 448.
Incorrect
The situation states that the project manager as well as the risk owners has just concluded the Plan Risk Responses process. Risk Register gets updated as a valid output for Plan Risk Response process with information like agreed-upon response strategies, triggers, warning signs of risk occurrence, residual risks that are expected to remain because they are deliberately accepted, etc.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 448.
Unattempted
The situation states that the project manager as well as the risk owners has just concluded the Plan Risk Responses process. Risk Register gets updated as a valid output for Plan Risk Response process with information like agreed-upon response strategies, triggers, warning signs of risk occurrence, residual risks that are expected to remain because they are deliberately accepted, etc.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 448.
Question 73 of 75
73. Question
Ryan is the Project Manager of a construction company. Currently he is engaged in the first iteration of the Identify Stakeholder process for a new road construction project of his company.
What can help him with the initial list of stakeholders who may get positively or negatively affected by the project?
Correct
In the first iteration of the Identify Stakeholder process, Business case and the Benefit Management Plan are sources of information about project’s stakeholders. A is not correct because the project charter may help in the identification of key stakeholder list,this information too project charter receives from Business case. To be more precise, question asked about stakeholders not key stakeholders. C is incorrect, because Project Management Plan is not yet created in this stage. Some may get confused between B and D, as both the options are close. Benefit Management Plan emphasizes on those stakeholders who will benefit from the delivery of the outcomes of the project. Business case helps with initial list of stakeholders affected by the project (both positively and negatively, in most possible scenarios). So, among all options B is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 509.
Incorrect
In the first iteration of the Identify Stakeholder process, Business case and the Benefit Management Plan are sources of information about project’s stakeholders. A is not correct because the project charter may help in the identification of key stakeholder list,this information too project charter receives from Business case. To be more precise, question asked about stakeholders not key stakeholders. C is incorrect, because Project Management Plan is not yet created in this stage. Some may get confused between B and D, as both the options are close. Benefit Management Plan emphasizes on those stakeholders who will benefit from the delivery of the outcomes of the project. Business case helps with initial list of stakeholders affected by the project (both positively and negatively, in most possible scenarios). So, among all options B is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 509.
Unattempted
In the first iteration of the Identify Stakeholder process, Business case and the Benefit Management Plan are sources of information about project’s stakeholders. A is not correct because the project charter may help in the identification of key stakeholder list,this information too project charter receives from Business case. To be more precise, question asked about stakeholders not key stakeholders. C is incorrect, because Project Management Plan is not yet created in this stage. Some may get confused between B and D, as both the options are close. Benefit Management Plan emphasizes on those stakeholders who will benefit from the delivery of the outcomes of the project. Business case helps with initial list of stakeholders affected by the project (both positively and negatively, in most possible scenarios). So, among all options B is the best answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 509.
Question 74 of 75
74. Question
One of the output from Control Quality process gives an important input to the Manage Quality process that represents documented results of Control Quality activities.
What has been referred in the given scenario?
Correct
A is the output for Manage Quality process, it’s not the input. So A is not correct. Work Performance Information is neither input or output to the Manage Quality process, though it’s a valid output for Control Quality process. So, B is also not correct. D is an input for Manage Quality process, but not an output for Control Quality process. Therefore, D is also not correct. Based on elimination rule, C is right answer. Further Quality Control Measurements is a valid output for Control Quality process that represents documented results of Control Quality activities. It acts as a valid input for Manage Quality process to analyze and evaluate the quality of the processes and deliverables of the project against the standards of the performing organization or the requirements specified. So, considering all options, option C is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 288, 291, 298, 305.
Incorrect
A is the output for Manage Quality process, it’s not the input. So A is not correct. Work Performance Information is neither input or output to the Manage Quality process, though it’s a valid output for Control Quality process. So, B is also not correct. D is an input for Manage Quality process, but not an output for Control Quality process. Therefore, D is also not correct. Based on elimination rule, C is right answer. Further Quality Control Measurements is a valid output for Control Quality process that represents documented results of Control Quality activities. It acts as a valid input for Manage Quality process to analyze and evaluate the quality of the processes and deliverables of the project against the standards of the performing organization or the requirements specified. So, considering all options, option C is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 288, 291, 298, 305.
Unattempted
A is the output for Manage Quality process, it’s not the input. So A is not correct. Work Performance Information is neither input or output to the Manage Quality process, though it’s a valid output for Control Quality process. So, B is also not correct. D is an input for Manage Quality process, but not an output for Control Quality process. Therefore, D is also not correct. Based on elimination rule, C is right answer. Further Quality Control Measurements is a valid output for Control Quality process that represents documented results of Control Quality activities. It acts as a valid input for Manage Quality process to analyze and evaluate the quality of the processes and deliverables of the project against the standards of the performing organization or the requirements specified. So, considering all options, option C is the right answer.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 288, 291, 298, 305.
Question 75 of 75
75. Question
During closing what would help to measure whether the benefits of the project were achieved as planned?
Correct
Benefit Management Plan is a type of Business document that describes how and when the benefits of the project will be delivered, and describes the mechanism that should be in place to measure those benefits. During Closing, its reviewed to measure whether the benefits of the project were achieved as planned.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 125.
Incorrect
Benefit Management Plan is a type of Business document that describes how and when the benefits of the project will be delivered, and describes the mechanism that should be in place to measure those benefits. During Closing, its reviewed to measure whether the benefits of the project were achieved as planned.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 125.
Unattempted
Benefit Management Plan is a type of Business document that describes how and when the benefits of the project will be delivered, and describes the mechanism that should be in place to measure those benefits. During Closing, its reviewed to measure whether the benefits of the project were achieved as planned.
(PMBOK Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) – 125.
X