You have already completed the Test before. Hence you can not start it again.
Test is loading...
You must sign in or sign up to start the Test.
You have to finish following quiz, to start this Test:
Your results are here!! for" Project Management Professional (PMP) Practice Test 9 "
0 of 58 questions answered correctly
Your time:
Time has elapsed
Your Final Score is : 0
You have attempted : 0
Number of Correct Questions : 0 and scored 0
Number of Incorrect Questions : 0 and Negative marks 0
Average score
Your score
Project Management Professional (PMP)
You have attempted: 0
Number of Correct Questions: 0 and scored 0
Number of Incorrect Questions: 0 and Negative marks 0
You can review your answers by clicking view questions. Important Note : Open Reference Documentation Links in New Tab (Right Click and Open in New Tab).
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
Answered
Review
Question 1 of 58
1. Question
Match the following agile roles with their description.
Correct
A-5, B-1, C-2, D-4, E-3. This question describes the various titles project managers may have in different adaptive methodologie
Incorrect
A-5, B-1, C-2, D-4, E-3. This question describes the various titles project managers may have in different adaptive methodologie
Unattempted
A-5, B-1, C-2, D-4, E-3. This question describes the various titles project managers may have in different adaptive methodologie
Question 2 of 58
2. Question
A junior team member of your agile project wants to know under which of the following circumstances, an agile team can re-estimate the level or size of effort that is required to complete a user story during an iteration. Which of the following should be your answer?
Correct
The ideal days and the number of story points estimates the size and overall complexity of the considered user story. But they alone are not capable to estimate the time needed to make the user story completed. The required time depends on the size of a user story (estimated in form of ideal days and story points) and the velocity of the development team i.e how many story points on an average the team completes. In other terms, these story points are the effort required to complete a user story during an iteration and it should be re-estimated when the team thinks that the relative size of the user story has changed. If the relative size changes, the team can re-estimate the size of story points to have a better idea of the effort and work to be done to complete that user story.
Incorrect
The ideal days and the number of story points estimates the size and overall complexity of the considered user story. But they alone are not capable to estimate the time needed to make the user story completed. The required time depends on the size of a user story (estimated in form of ideal days and story points) and the velocity of the development team i.e how many story points on an average the team completes. In other terms, these story points are the effort required to complete a user story during an iteration and it should be re-estimated when the team thinks that the relative size of the user story has changed. If the relative size changes, the team can re-estimate the size of story points to have a better idea of the effort and work to be done to complete that user story.
Unattempted
The ideal days and the number of story points estimates the size and overall complexity of the considered user story. But they alone are not capable to estimate the time needed to make the user story completed. The required time depends on the size of a user story (estimated in form of ideal days and story points) and the velocity of the development team i.e how many story points on an average the team completes. In other terms, these story points are the effort required to complete a user story during an iteration and it should be re-estimated when the team thinks that the relative size of the user story has changed. If the relative size changes, the team can re-estimate the size of story points to have a better idea of the effort and work to be done to complete that user story.
Question 3 of 58
3. Question
The cost performance index (CPI) on the project is 1.13, and the benefit-cost ratio is 1.2. The project scope was created by the team and stakeholders, and requirements have been changing throughout the project. No matter what the project manager has tried to accomplish in managing the project, which of the following is he most likely to face in the future?
Correct
There are many pieces of data in this question that are distractions from the real issue. Though it is common to have to cut costs and add resources to a project, nothing in the question should lead you to think these will be required in this situation. Customers do not generally approve the project scope (what you are going to do to complete their requirements); instead, they approve the product scope (their requirements). Since requirements are used to measure the completion of the product of the project, not having complete requirements will make such measurement impossible.
Incorrect
There are many pieces of data in this question that are distractions from the real issue. Though it is common to have to cut costs and add resources to a project, nothing in the question should lead you to think these will be required in this situation. Customers do not generally approve the project scope (what you are going to do to complete their requirements); instead, they approve the product scope (their requirements). Since requirements are used to measure the completion of the product of the project, not having complete requirements will make such measurement impossible.
Unattempted
There are many pieces of data in this question that are distractions from the real issue. Though it is common to have to cut costs and add resources to a project, nothing in the question should lead you to think these will be required in this situation. Customers do not generally approve the project scope (what you are going to do to complete their requirements); instead, they approve the product scope (their requirements). Since requirements are used to measure the completion of the product of the project, not having complete requirements will make such measurement impossible.
Question 4 of 58
4. Question
You are managing a large interior design project, when two team members come to you with a conflict. The senior designer has identified an important project risk, you have a subcontractor that may not deliver on time. Another senior designer doesn’t believe that the risk is likely to happen; however, you consult the lessons learned from previous projects and discover that subcontractors failed to deliver their work on two previous projects. You decide that the risk is too big and you terminate the contract with the subcontractor, and instead hired additional freelance designers to build the work. Both team members agree that this has eliminated the risk. Which of the following best describes this scenario?
Correct
The best thing that you can do with a risk is avoid it – if you can prevent it from happening, it definitely won’t hurt your project. The easiest way to avoid a risk is to cut it out of your project entirely; in this case, getting rid of the subcontractor avoids the risk.
Incorrect
The best thing that you can do with a risk is avoid it – if you can prevent it from happening, it definitely won’t hurt your project. The easiest way to avoid a risk is to cut it out of your project entirely; in this case, getting rid of the subcontractor avoids the risk.
Unattempted
The best thing that you can do with a risk is avoid it – if you can prevent it from happening, it definitely won’t hurt your project. The easiest way to avoid a risk is to cut it out of your project entirely; in this case, getting rid of the subcontractor avoids the risk.
Question 5 of 58
5. Question
You are managing an accounting project for your organization, and the project was initiated in the last month and is expected to be finished in 12 months. New CFO is hired at your company and he will be affected by all accounting projects in your company. What’s the best thing for you to do?
Correct
Since the CFO is affected by your project, that means he’s a stakeholder. The best thing you can do in this situation is get the new stakeholder’s opinion incorporated in the project up front. It’s important that all of the project stakeholders understand the needs and objectives that the project is meant to address. The worst case is to have the stakeholder’s opinion incorporated at the end of the project — that could mean a lot of re-work or even an entirely unacceptable product.
Incorrect
Since the CFO is affected by your project, that means he’s a stakeholder. The best thing you can do in this situation is get the new stakeholder’s opinion incorporated in the project up front. It’s important that all of the project stakeholders understand the needs and objectives that the project is meant to address. The worst case is to have the stakeholder’s opinion incorporated at the end of the project — that could mean a lot of re-work or even an entirely unacceptable product.
Unattempted
Since the CFO is affected by your project, that means he’s a stakeholder. The best thing you can do in this situation is get the new stakeholder’s opinion incorporated in the project up front. It’s important that all of the project stakeholders understand the needs and objectives that the project is meant to address. The worst case is to have the stakeholder’s opinion incorporated at the end of the project — that could mean a lot of re-work or even an entirely unacceptable product.
Question 6 of 58
6. Question
In iteration-based agile, the product owner often works with the team to prepare some stories for the upcoming iteration during one or more sessions in the middle of the iteration. The purpose of these meetings is to refine enough stories so the team understands what the stories are and how large the stories are in relation to each other. Which of the following represents this meeting?
Correct
In iteration-based agile, the product owner often works with the team to prepare some stories for the upcoming iteration during one or more sessions in the middle of the iteration. The purpose of these meetings is to refine enough stories so the team understands what the stories are and how large the stories are in relation to each other. This meeting is called backlog refinement or backlog grooming[Practice Guide, 1st edition, page 52].
Incorrect
In iteration-based agile, the product owner often works with the team to prepare some stories for the upcoming iteration during one or more sessions in the middle of the iteration. The purpose of these meetings is to refine enough stories so the team understands what the stories are and how large the stories are in relation to each other. This meeting is called backlog refinement or backlog grooming[Practice Guide, 1st edition, page 52].
Unattempted
In iteration-based agile, the product owner often works with the team to prepare some stories for the upcoming iteration during one or more sessions in the middle of the iteration. The purpose of these meetings is to refine enough stories so the team understands what the stories are and how large the stories are in relation to each other. This meeting is called backlog refinement or backlog grooming[Practice Guide, 1st edition, page 52].
Question 7 of 58
7. Question
As part of your efforts in the initiation phase of your project, which of the following activities can be done in order to validate project alignment with organizational strategy and expected business value?
Correct
As a professional project manager, you should conduct benefit analysis with relevant stakeholders to validate project alignment with organizational strategy and expected business value.
Incorrect
As a professional project manager, you should conduct benefit analysis with relevant stakeholders to validate project alignment with organizational strategy and expected business value.
Unattempted
As a professional project manager, you should conduct benefit analysis with relevant stakeholders to validate project alignment with organizational strategy and expected business value.
Question 8 of 58
8. Question
You are the project manager for heavy equipment spare parts company, and your company was assigned for the production of 20,000 parts for a large heavy equipment factory, this will involve the design and production. During the course of the project, as you review a quality control statistics chart that examines every unit produced for the month, you notice several cases were a specific component of the spare part is expanding with too much and is falling outside the upper control limit. Which quality control tools are you using?
Correct
Control charts graphically display the interaction of process variables on a process, the control chart have three lines: Mean line, upper control line and lower control line.
Incorrect
Control charts graphically display the interaction of process variables on a process, the control chart have three lines: Mean line, upper control line and lower control line.
Unattempted
Control charts graphically display the interaction of process variables on a process, the control chart have three lines: Mean line, upper control line and lower control line.
Question 9 of 58
9. Question
One of the ways PMOs are evolving into agile centers of excellence is through a category called “Organizational Learning.” This category notes that the agile PMO is responsible for capturing lessons learned. What other tasks does the center of excellence provide? (Choose three.)
Correct
Documenting the coordination and communication among and between the agile teams is one of the aspects of the “Managing Multiple Projects” category, and Documenting the training courses that were taken by stakeholders and team members is one of the aspects of the “Managing Stakeholders” category for agile centers of excellence.
Incorrect
Documenting the coordination and communication among and between the agile teams is one of the aspects of the “Managing Multiple Projects” category, and Documenting the training courses that were taken by stakeholders and team members is one of the aspects of the “Managing Stakeholders” category for agile centers of excellence.
Unattempted
Documenting the coordination and communication among and between the agile teams is one of the aspects of the “Managing Multiple Projects” category, and Documenting the training courses that were taken by stakeholders and team members is one of the aspects of the “Managing Stakeholders” category for agile centers of excellence.
Question 10 of 58
10. Question
You work for a contractor in a project that is not considered to be strategic for the company. Although the project is not the company’s top priority, you have managed to secure many of the company’s top resources to work in your project. At today’s company level meeting, you find out that your company has won a very large, strategic project. As a professional project manager, what should you do first?
Correct
It is always better to evaluate before you take any action. You need to know if your project is going to be affected before taking action. You don’t need to fast track the project before you fully understand the situation.
Incorrect
It is always better to evaluate before you take any action. You need to know if your project is going to be affected before taking action. You don’t need to fast track the project before you fully understand the situation.
Unattempted
It is always better to evaluate before you take any action. You need to know if your project is going to be affected before taking action. You don’t need to fast track the project before you fully understand the situation.
Question 11 of 58
11. Question
Based on the network diagram shown below, what is the duration of the near critical path?
Correct
The three paths durations are: A-B-E-F-G= 18, A-C-F-G= 13, A-D-F-G= 16. The near critical path is the longest path in duration after the critical path.
Incorrect
The three paths durations are: A-B-E-F-G= 18, A-C-F-G= 13, A-D-F-G= 16. The near critical path is the longest path in duration after the critical path.
Unattempted
The three paths durations are: A-B-E-F-G= 18, A-C-F-G= 13, A-D-F-G= 16. The near critical path is the longest path in duration after the critical path.
Question 12 of 58
12. Question
You are a project manager working on a new web development and design project. Part of this project entails a complex coding job. You contracted out the production of this code. Now all of the work of the project is done, the stakeholders are satisfied with the results, and you’re in the process of closing out the project. Which of the following project ending has this project experienced?
Correct
This project ended due to extinction because the project was completed successfully and to the satisfaction of the stakeholders.
Incorrect
This project ended due to extinction because the project was completed successfully and to the satisfaction of the stakeholders.
Unattempted
This project ended due to extinction because the project was completed successfully and to the satisfaction of the stakeholders.
Question 13 of 58
13. Question
You are managing a mega construction project, when you find out that an engineering team whom you were supposed to have access to has been reassigned to another project within the organization. What is the first thing that you should do as a professional project manager?
Correct
If a resource is not available to you, it doesn’t matter what’s in your project charter or what your sponsors and stakeholders want. You need to figure out how to move forward from here, and the first step in doing that is evaluating the impact that this new problem will have on your project.
Incorrect
If a resource is not available to you, it doesn’t matter what’s in your project charter or what your sponsors and stakeholders want. You need to figure out how to move forward from here, and the first step in doing that is evaluating the impact that this new problem will have on your project.
Unattempted
If a resource is not available to you, it doesn’t matter what’s in your project charter or what your sponsors and stakeholders want. You need to figure out how to move forward from here, and the first step in doing that is evaluating the impact that this new problem will have on your project.
Question 14 of 58
14. Question
_____________ can be defined as a technique to operate Scrum at scale for multiple teams working on the same product, coordinating discussions of progress on their inter-dependencies, and focusing on how to integrate the delivery of software, especially in areas of overlap.
Correct
Scrum of Scrums: A technique to operate Scrum at scale for multiple teams working on the same product, coordinating discussions of progress on their interdependencies, and focusing on how to integrate the delivery of software, especially in areas of overlap. [Practice Guide, 1st edition, page 154].
Incorrect
Scrum of Scrums: A technique to operate Scrum at scale for multiple teams working on the same product, coordinating discussions of progress on their interdependencies, and focusing on how to integrate the delivery of software, especially in areas of overlap. [Practice Guide, 1st edition, page 154].
Unattempted
Scrum of Scrums: A technique to operate Scrum at scale for multiple teams working on the same product, coordinating discussions of progress on their interdependencies, and focusing on how to integrate the delivery of software, especially in areas of overlap. [Practice Guide, 1st edition, page 154].
Question 15 of 58
15. Question
Shadi is an experienced software developer who is appraised and respected for his experience as well as excellence in the quality of deliverables he produce. Ruthless testing is one of the secrets of the agile capability of Shadi and Shadi’s team. Which is the following is a valid statement with respect to ruthless testing?
Correct
The experience has demonstrated that the main difference between the immature and mature agile team lies in terms of their commitment to ruthless testing. Ruthless testing ensures that the quality of the product remains high throughout the development process. It is always ideal for a team to come closer to running tested features (RTF) in each and every iteration. The teams embracing the ruthless testing are found to be highly efficient and productive.[Agile Practice Guide, 1st edition, Page 56]
Incorrect
The experience has demonstrated that the main difference between the immature and mature agile team lies in terms of their commitment to ruthless testing. Ruthless testing ensures that the quality of the product remains high throughout the development process. It is always ideal for a team to come closer to running tested features (RTF) in each and every iteration. The teams embracing the ruthless testing are found to be highly efficient and productive.[Agile Practice Guide, 1st edition, Page 56]
Unattempted
The experience has demonstrated that the main difference between the immature and mature agile team lies in terms of their commitment to ruthless testing. Ruthless testing ensures that the quality of the product remains high throughout the development process. It is always ideal for a team to come closer to running tested features (RTF) in each and every iteration. The teams embracing the ruthless testing are found to be highly efficient and productive.[Agile Practice Guide, 1st edition, Page 56]
Question 16 of 58
16. Question
You are a project manager for a large Software Consulting Services firm. You’re working with a major retailer that offers its products online. The company is interested in knowing customer characteristics, the amounts of first-time orders, and similar information. As a potential bidder for this project, you worked on the RFP response and submitted the proposal. When the selection committee received the RFP responses from all the vendors bidding on this project, they used a weighted system in combination with a seller rating system to make a selection. Which of the following are true? (Choose three.)
Correct
The complexity of the contract will determine how extensive the contract negotiations will be, not the procurement officers. Weighted systems are a type of proposal evaluation technique. Seller rating systems should not be used as the sole evaluation technique when evaluating and selecting vendors. They should be combined with other techniques.
Incorrect
The complexity of the contract will determine how extensive the contract negotiations will be, not the procurement officers. Weighted systems are a type of proposal evaluation technique. Seller rating systems should not be used as the sole evaluation technique when evaluating and selecting vendors. They should be combined with other techniques.
Unattempted
The complexity of the contract will determine how extensive the contract negotiations will be, not the procurement officers. Weighted systems are a type of proposal evaluation technique. Seller rating systems should not be used as the sole evaluation technique when evaluating and selecting vendors. They should be combined with other techniques.
Question 17 of 58
17. Question
A project management office (PMO) held a weekly staff meeting for project managers to remain up to date on interdependent projects. During this meeting, Shadi shared that his project had closed, and he had moved on to another assignment. Sami immediately expressed concern about the news, since his own project was dependent on ongoing support that should have gone live for the system that was deployed through Shadi’s now closed project. He explained that he had not heard of this milestone occurring. In this context, what closure step did Shadi miss?
Correct
While any one of the administrative closure tasks listed may have been missed by Shadi, it is clear that she did not finalize the transition of the project’s end result to ongoing operations. This would have occurred through the implementation of ongoing support for the new system deployed.
Incorrect
While any one of the administrative closure tasks listed may have been missed by Shadi, it is clear that she did not finalize the transition of the project’s end result to ongoing operations. This would have occurred through the implementation of ongoing support for the new system deployed.
Unattempted
While any one of the administrative closure tasks listed may have been missed by Shadi, it is clear that she did not finalize the transition of the project’s end result to ongoing operations. This would have occurred through the implementation of ongoing support for the new system deployed.
Question 18 of 58
18. Question
The head of Human Resources has requested a new timesheets tracking product for their workshop workers. The business value for this project is improving payroll accuracy. The workers are threatening a strike because of the antiquated system in place now. The current system has ancient time clocks that rarely work, causing the workers to revert to paper timecards. This creates multiple errors in overtime pay and shift differential pay. Which of the following is true regarding this scenario? (Choose three.)
Correct
The project manager is responsible for understanding the urgency required to deliver the business value of the project. The project sponsor defines the urgency, but the project manager is responsible for delivering the project according to the urgency driving the business value. Urgency is subjective and is defined by the project sponsor.
Incorrect
The project manager is responsible for understanding the urgency required to deliver the business value of the project. The project sponsor defines the urgency, but the project manager is responsible for delivering the project according to the urgency driving the business value. Urgency is subjective and is defined by the project sponsor.
Unattempted
The project manager is responsible for understanding the urgency required to deliver the business value of the project. The project sponsor defines the urgency, but the project manager is responsible for delivering the project according to the urgency driving the business value. Urgency is subjective and is defined by the project sponsor.
Question 19 of 58
19. Question
As per the burn up chart shown below, what happened at day 7?
Correct
2 points were removed from the scope on day 7, bringing the total in the backlog to 30 points.
Incorrect
2 points were removed from the scope on day 7, bringing the total in the backlog to 30 points.
Unattempted
2 points were removed from the scope on day 7, bringing the total in the backlog to 30 points.
Question 20 of 58
20. Question
You are the project manager of software company involved in creating an anti-virus software product. You are in execution phase of the project when you realize that a requirement was not included in the project. This is due to an omission in defining the scope baseline of the project. What should you do?
Correct
Analysis of scope performance can result in a change request to the scope baseline or other components of the project management plan.
Incorrect
Analysis of scope performance can result in a change request to the scope baseline or other components of the project management plan.
Unattempted
Analysis of scope performance can result in a change request to the scope baseline or other components of the project management plan.
Question 21 of 58
21. Question
You are working on a project where the requirements and scope are well defined, but you know there will be changes when performing the work of the project. Your stakeholders will need to provide continuous feedback during the development stages of this project. Which of the following are true when determining the deliverables for the project? (Choose three.)
Correct
The project scope statement further elaborates the project deliverables and documents the product scope description, acceptance criteria, and project exclusions. It serves as a basis for future project decisions. It is an agreement between the project team and the customer on the precise work of the project. This question describes a hybrid approach so you could use either a project scope statement or a product backlog to compile user stories, which are the deliverables and requirements for the project.
Incorrect
The project scope statement further elaborates the project deliverables and documents the product scope description, acceptance criteria, and project exclusions. It serves as a basis for future project decisions. It is an agreement between the project team and the customer on the precise work of the project. This question describes a hybrid approach so you could use either a project scope statement or a product backlog to compile user stories, which are the deliverables and requirements for the project.
Unattempted
The project scope statement further elaborates the project deliverables and documents the product scope description, acceptance criteria, and project exclusions. It serves as a basis for future project decisions. It is an agreement between the project team and the customer on the precise work of the project. This question describes a hybrid approach so you could use either a project scope statement or a product backlog to compile user stories, which are the deliverables and requirements for the project.
Question 22 of 58
22. Question
You are managing a software development project. You are partway through the project, and your team has just delivered a preliminary version of part of the software. You are holding a weekly status meeting, when one of the team members points out that an important stakeholder is running into a problem with one of the features of the current software. The team member feels that there is a risk that the stakeholder will ask for a change in that feature, even though that change would be out of scope of the current release – and if the stakeholder requests that change, there is a high probability that the change control board would approve the change. What is the best action to take next?
Correct
Your risk register is one of the most important project management tools that you have – that’s why you review it and go over your risks at every meeting. Any time you come across a new risk, the first thing you should do is document it in the risk register. It’s really easy to lose track of risks, especially when you’re running a big project. By adding every risk to the register, you make sure that you don’t forget about any of them. So once you’ve identified the risk, what’s the next step? You analyze the impact and probability of the risk! That’s what the Qualitative Risk Analysis processes for. You shouldn’t take any other action until you’ve analyzed the risk. The reason is that it might turn out that the risk is very unlikely, and there might be another risk with a higher probability and larger impact that deserves your attention.
Incorrect
Your risk register is one of the most important project management tools that you have – that’s why you review it and go over your risks at every meeting. Any time you come across a new risk, the first thing you should do is document it in the risk register. It’s really easy to lose track of risks, especially when you’re running a big project. By adding every risk to the register, you make sure that you don’t forget about any of them. So once you’ve identified the risk, what’s the next step? You analyze the impact and probability of the risk! That’s what the Qualitative Risk Analysis processes for. You shouldn’t take any other action until you’ve analyzed the risk. The reason is that it might turn out that the risk is very unlikely, and there might be another risk with a higher probability and larger impact that deserves your attention.
Unattempted
Your risk register is one of the most important project management tools that you have – that’s why you review it and go over your risks at every meeting. Any time you come across a new risk, the first thing you should do is document it in the risk register. It’s really easy to lose track of risks, especially when you’re running a big project. By adding every risk to the register, you make sure that you don’t forget about any of them. So once you’ve identified the risk, what’s the next step? You analyze the impact and probability of the risk! That’s what the Qualitative Risk Analysis processes for. You shouldn’t take any other action until you’ve analyzed the risk. The reason is that it might turn out that the risk is very unlikely, and there might be another risk with a higher probability and larger impact that deserves your attention.
Question 23 of 58
23. Question
While you are planning for the project communications, you created the stakeholders engagement assessment matrix, and you included four of the key stakeholders which you want to manage closely during your project life. One of your team members reported the updated stakeholder engagement assessment matrix as shown below, and states that an urgent meeting should be arranged with ________ to address issues with his/her engagement.
Correct
Dina was planned to be in the directive level when this matrix was created, currently she is in the resistant level. So, as a proactive project manager, you should directly schedule a meeting with Dina to address her concerns.
Incorrect
Dina was planned to be in the directive level when this matrix was created, currently she is in the resistant level. So, as a proactive project manager, you should directly schedule a meeting with Dina to address her concerns.
Unattempted
Dina was planned to be in the directive level when this matrix was created, currently she is in the resistant level. So, as a proactive project manager, you should directly schedule a meeting with Dina to address her concerns.
Question 24 of 58
24. Question
In your project, you recently observed conflict among team members. You would like to see that all team members work towards one goal which is successful completion of the project. A conflict handling method that emphasizes similarities rather than differences as means to solve a problem can also be referred to as which of the following?
Correct
Withdrawal: Retreating or withdrawal from a potential disagreement. Smoothing: De-emphasizing or avoiding areas of differences and emphasizing areas of agreement. Compromising: Bargaining and searching for solutions that bring some degree of satisfaction to the parties in a dispute, characterized by a give and take attitude. Forcing: Exerting one viewpoint at the potential expense of another, often characterized by competitiveness and a win-lose situation. Confrontation: Facing the conflict directly, which involves a problem solving approach, whereby affected parties work through their disagreements.
Incorrect
Withdrawal: Retreating or withdrawal from a potential disagreement. Smoothing: De-emphasizing or avoiding areas of differences and emphasizing areas of agreement. Compromising: Bargaining and searching for solutions that bring some degree of satisfaction to the parties in a dispute, characterized by a give and take attitude. Forcing: Exerting one viewpoint at the potential expense of another, often characterized by competitiveness and a win-lose situation. Confrontation: Facing the conflict directly, which involves a problem solving approach, whereby affected parties work through their disagreements.
Unattempted
Withdrawal: Retreating or withdrawal from a potential disagreement. Smoothing: De-emphasizing or avoiding areas of differences and emphasizing areas of agreement. Compromising: Bargaining and searching for solutions that bring some degree of satisfaction to the parties in a dispute, characterized by a give and take attitude. Forcing: Exerting one viewpoint at the potential expense of another, often characterized by competitiveness and a win-lose situation. Confrontation: Facing the conflict directly, which involves a problem solving approach, whereby affected parties work through their disagreements.
Question 25 of 58
25. Question
Yara is managing a software development project for her company, and she is now recruiting her project team and did various interviews and has shortlisted potential candidates, now according to the communications management plan of the project, she has to submit the candidates list to the client for approval, then she can formally hire the approved candidates for the project. In this context, the submission of the list to the client will go through __________ process.
Correct
Manage communications is the process of distributing project information in accordance to the communications management plan, interviews are part of the acquire resources process.
Incorrect
Manage communications is the process of distributing project information in accordance to the communications management plan, interviews are part of the acquire resources process.
Unattempted
Manage communications is the process of distributing project information in accordance to the communications management plan, interviews are part of the acquire resources process.
Question 26 of 58
26. Question
Shadi is the senior project manager of the largest project within his organization. He sits down with Sami, the junior project manager, to discuss resources utilization on the project. He expresses concern after recently hearing that resources have been unavailable as planned. Sami admits that this has been the case and that it has set the project back unexpectedly. What action should Sami take to remedy the situation?
Correct
When performing the control resources process, data analysis may be used to evaluate what alternatives exist to completing activities with resources, such as alternate resources. Data analysis also includes performing cost-benefit analysis, performance reviews, and trend analysis.
Incorrect
When performing the control resources process, data analysis may be used to evaluate what alternatives exist to completing activities with resources, such as alternate resources. Data analysis also includes performing cost-benefit analysis, performance reviews, and trend analysis.
Unattempted
When performing the control resources process, data analysis may be used to evaluate what alternatives exist to completing activities with resources, such as alternate resources. Data analysis also includes performing cost-benefit analysis, performance reviews, and trend analysis.
Question 27 of 58
27. Question
You are working in the PMO of your organization, and as a part of your routine job, you attended a status meeting of a critical project running within your organization. During this meeting, the project manager presented sensitive information related to the project. However, this information was not intended to be available to the audience. As a PMO member, you want to investigate and know what went wrong in the project resulting in the project manager communicating sensitive information to the wrong audience. In this described situation, the ______________ process was done incorrectly.
Correct
Deciding what information is relevant to the audience is part of the plan communications management, improper communications planning lead to such delays in message delivery.
Incorrect
Deciding what information is relevant to the audience is part of the plan communications management, improper communications planning lead to such delays in message delivery.
Unattempted
Deciding what information is relevant to the audience is part of the plan communications management, improper communications planning lead to such delays in message delivery.
Question 28 of 58
28. Question
An agile team is working on a complex application development project. In the retrospective meeting, the team has identified the delay in the testing of a user story many times, due to non-availability of a developer who could run database queries. The team leader finds that it would be beneficial if a few team members acquire basic database skills. It will make them write and run database queries independently by themselves and then complete the testing. What should the team lead do the next?
Correct
Agile environment focuses on providing a learning environment to its team members so that they can improve their skills and work as a generalizing specialist. As an agile practitioner, it is important to improve the skills regularly and test the acquired skills as well. In the current scenario, the team leader should provide an opportunity to his team members to improve their database query skills by arranging good database training. It will make team members capable to run queries and test user stories without any delay in testing. It is also an objective of generalizing specialist where developers can act as testers and testers can act as developers as well.
Incorrect
Agile environment focuses on providing a learning environment to its team members so that they can improve their skills and work as a generalizing specialist. As an agile practitioner, it is important to improve the skills regularly and test the acquired skills as well. In the current scenario, the team leader should provide an opportunity to his team members to improve their database query skills by arranging good database training. It will make team members capable to run queries and test user stories without any delay in testing. It is also an objective of generalizing specialist where developers can act as testers and testers can act as developers as well.
Unattempted
Agile environment focuses on providing a learning environment to its team members so that they can improve their skills and work as a generalizing specialist. As an agile practitioner, it is important to improve the skills regularly and test the acquired skills as well. In the current scenario, the team leader should provide an opportunity to his team members to improve their database query skills by arranging good database training. It will make team members capable to run queries and test user stories without any delay in testing. It is also an objective of generalizing specialist where developers can act as testers and testers can act as developers as well.
Question 29 of 58
29. Question
You are attending a project status update meeting at the organization level. All attendees receive a dashboard of cost metrics of each project, and each project manager is presenting the status of his project. The metrics of one project shows a BAC of $120,000, AC of $99,000 and an EAC of $125,000. However, the project manager states that the ETC will be $20,000. What should you do?
Correct
As the ETC is being calculated and reported, that means the EAC= AC+ETC, so there is an calculation error. As per the PMI code of ethics, you should report any mistake you observe to the appropriate management.
Incorrect
As the ETC is being calculated and reported, that means the EAC= AC+ETC, so there is an calculation error. As per the PMI code of ethics, you should report any mistake you observe to the appropriate management.
Unattempted
As the ETC is being calculated and reported, that means the EAC= AC+ETC, so there is an calculation error. As per the PMI code of ethics, you should report any mistake you observe to the appropriate management.
Question 30 of 58
30. Question
You are the project manager of the most critical project of your organization. When you planned the project, the organization delegation of authority matrix which is part of the enterprise environmental factors included a policy that all changes that cost over $100,000 need to be approved by the managing director, but smaller changes could be paid for by a management contingency fund. One of your stakeholders submitted a change request that requires a $120,000. Your company has an outsourcing effort, and you believe that a small change to the way the change is requested could allow you to take advantage of it and cut your costs in half. What is the best way to handle this situation?
Correct
When your company has a policy, you need to follow it and not try to work around it. As stated in the delegation of authority matrix, you need to get the managing director approval on the change.
Incorrect
When your company has a policy, you need to follow it and not try to work around it. As stated in the delegation of authority matrix, you need to get the managing director approval on the change.
Unattempted
When your company has a policy, you need to follow it and not try to work around it. As stated in the delegation of authority matrix, you need to get the managing director approval on the change.
Question 31 of 58
31. Question
Dima is a project manager who is deep into project execution. Currently, she is working on increasing stakeholders involvement and interaction within the project, and utilizing the stakeholder engagement plan for guidance. What is the likely result of Dima’s efforts?
Correct
Change requests may occur as a result of performing the manage stakeholder engagement process. The purpose of this process is to cultivate appropriate engagement and interaction among stakeholders of the project. As a result of these activities, change requests to project or product scope may arise.
Incorrect
Change requests may occur as a result of performing the manage stakeholder engagement process. The purpose of this process is to cultivate appropriate engagement and interaction among stakeholders of the project. As a result of these activities, change requests to project or product scope may arise.
Unattempted
Change requests may occur as a result of performing the manage stakeholder engagement process. The purpose of this process is to cultivate appropriate engagement and interaction among stakeholders of the project. As a result of these activities, change requests to project or product scope may arise.
Question 32 of 58
32. Question
You are working on a project for your organization. The objective is to develop a new software that will provide users with the ability to track business expenses and mileage that will automatically populate an expense report at the conclusion of the business trip. You are using skills that help you determine business needs, that help you document and manage stakeholder requirements, and you encourage stakeholders to be forthcoming with requirements. Your role also includes facilitating the implementation of these requirements into the final product, service, or result of the project. In this situation, which of the following options is true?
Correct
The question describes business analysis skills, and these are applied and used by a business analyst.
Incorrect
The question describes business analysis skills, and these are applied and used by a business analyst.
Unattempted
The question describes business analysis skills, and these are applied and used by a business analyst.
Question 33 of 58
33. Question
You have been hired as a consultant by a large IT firm. You have been asked to develop a standardized project management approach for the organization. You are currently considering the entire continuum of project management which is Agile on one end and waterfall on the other. Before you can decide which model to select, you need to conduct which of the following techniques?
Correct
The first thing you need to do is conduct the organization’s culture assessment. Impact assessment should be conducted only once the new approach has been selected and approved. Root cause and feasibility analysis are irrelevant to the problem at hand and are rather related to issues and individual projects respectively. [Agile Practice Guide, 1st edition, Page 75]
Incorrect
The first thing you need to do is conduct the organization’s culture assessment. Impact assessment should be conducted only once the new approach has been selected and approved. Root cause and feasibility analysis are irrelevant to the problem at hand and are rather related to issues and individual projects respectively. [Agile Practice Guide, 1st edition, Page 75]
Unattempted
The first thing you need to do is conduct the organization’s culture assessment. Impact assessment should be conducted only once the new approach has been selected and approved. Root cause and feasibility analysis are irrelevant to the problem at hand and are rather related to issues and individual projects respectively. [Agile Practice Guide, 1st edition, Page 75]
Question 34 of 58
34. Question
You are done with risk analysis for your project, and you ended these efforts by defining the need of $280,000 contingency reserves and a guess on management reserves of $50,000. While managing the project risks responses implementation, a team member notified you that two risks which were expected to impact the project with an extra cost of $100,000 and $50,000 are no longer valid, as these risks were related to delay in material which arrived to site already. Another unidentified risk occurred in the past month and impacted the project through outsourcing a third party for 5 working days with a daily rate of $2,000. Given that the likelihood of the two risks was 10%, and 20% respectively, and that you need to update the reserves report. What are the remaining contingency reserves on your project?
Correct
The unidentified risk occurred will be covered by management reserves and not contingency reserves, as management reserves are dedicated for unknown unknowns, the contingency reserves remaining will be: 280,000 – ((10%*100,000)+(20%*50,000))= $260,000. As risks were outdated, you will deduct the reserves associated with these risks from the total reserves of the project.
Incorrect
The unidentified risk occurred will be covered by management reserves and not contingency reserves, as management reserves are dedicated for unknown unknowns, the contingency reserves remaining will be: 280,000 – ((10%*100,000)+(20%*50,000))= $260,000. As risks were outdated, you will deduct the reserves associated with these risks from the total reserves of the project.
Unattempted
The unidentified risk occurred will be covered by management reserves and not contingency reserves, as management reserves are dedicated for unknown unknowns, the contingency reserves remaining will be: 280,000 – ((10%*100,000)+(20%*50,000))= $260,000. As risks were outdated, you will deduct the reserves associated with these risks from the total reserves of the project.
Question 35 of 58
35. Question
You are a project manager who works for a startup software development firm that is creating medical monitoring software that doctors will use to diagnose and treat patients. Patients will have a small device implanted in their chest that will communicate with an app. The information from the device will also be wirelessly communicated to the medical facility where more in-depth analysis can be conducted. This is a large software development project and you will use the feature-driven development (FDD) methodology to conduct this project. Which of the following are true regarding FDD? (Choose two.)
Correct
This methodology uses a top-down approach to decision making. Constraint driven and prioritizes scope describes the Dynamic Systems Development Method (DSDM).
Incorrect
This methodology uses a top-down approach to decision making. Constraint driven and prioritizes scope describes the Dynamic Systems Development Method (DSDM).
Unattempted
This methodology uses a top-down approach to decision making. Constraint driven and prioritizes scope describes the Dynamic Systems Development Method (DSDM).
Question 36 of 58
36. Question
As part of the procurement process, the procuring organization elected to have an estimate of costs prepared by a professional third party estimator out of the organization, the estimator came up with an estimate of $800,000. However, the cost estimates prepared by prospective sellers were in the range of $450,000, how can this be best interpreted?
Correct
When prospective sellers bids are significantly different from the estimates prepared by the professional estimator, it likely means that the procurement statement of work was deficient or it was misunderstood by the sellers.
Incorrect
When prospective sellers bids are significantly different from the estimates prepared by the professional estimator, it likely means that the procurement statement of work was deficient or it was misunderstood by the sellers.
Unattempted
When prospective sellers bids are significantly different from the estimates prepared by the professional estimator, it likely means that the procurement statement of work was deficient or it was misunderstood by the sellers.
Question 37 of 58
37. Question
You are done with the numerical risk analysis process of your project, and the results are shown in table below. Given that today is May,1st,2019, and you are updating the reserves report of your project, what are the remaining schedule contingency reserves at the moment?
Correct
As per the table, Risks A, and B are no longer valid in May,2019, they are outdated. So the only schedule contingency reserve is for Risk D= 3*.25= 0.75 week.
Incorrect
As per the table, Risks A, and B are no longer valid in May,2019, they are outdated. So the only schedule contingency reserve is for Risk D= 3*.25= 0.75 week.
Unattempted
As per the table, Risks A, and B are no longer valid in May,2019, they are outdated. So the only schedule contingency reserve is for Risk D= 3*.25= 0.75 week.
Question 38 of 58
38. Question
You are working as a research assistant studying the growth of a virus under different environmental conditions. Based on your experiments, you conclude that the longevity of the virus increases as the temperature increases. What type of diagram can you use to illustrate your observation?
Correct
A scatter diagram shows the relationship between two variables. It will be very useful to represent the relationship between the longevity and the temperature.
Incorrect
A scatter diagram shows the relationship between two variables. It will be very useful to represent the relationship between the longevity and the temperature.
Unattempted
A scatter diagram shows the relationship between two variables. It will be very useful to represent the relationship between the longevity and the temperature.
Question 39 of 58
39. Question
A project manager is preparing to lead a project status meeting, and the project is currently 75% complete and is reaching the most critical point. Since the project sponsor is planning on attending the meeting, the project manager decides to update the earned value calculations to present the latest performance updates in terms that the sponsor will want to see. The budget at completion (BAC) is set at $550,000, and the current estimate at completion (EAC) is at $525,000. What variance at completion (VAC) value will the project manager communicate to the sponsor?
Correct
To calculate variance at completion, subtract the estimate at completion from the budget at completion (BAC – EAC): $550,000 – $525,000 = $25,000.
Incorrect
To calculate variance at completion, subtract the estimate at completion from the budget at completion (BAC – EAC): $550,000 – $525,000 = $25,000.
Unattempted
To calculate variance at completion, subtract the estimate at completion from the budget at completion (BAC – EAC): $550,000 – $525,000 = $25,000.
Question 40 of 58
40. Question
You were halfway through your project when the product owner left the company. The new product owner has been assigned to the project but he came from a different part of the business. You were reviewing the product backlog with the new product owner when he requested to reprioritize some of the backlog items. What should you do?
Correct
The product owner is the owner of the product backlog and is ultimately accountable for the outcome of the project. At this stage, it is critical for you to review the entire backlog with the new product owner and ensure that they agree with the current ranking of stories. [Agile Practice Guide, 1st edition, Page 41]
Incorrect
The product owner is the owner of the product backlog and is ultimately accountable for the outcome of the project. At this stage, it is critical for you to review the entire backlog with the new product owner and ensure that they agree with the current ranking of stories. [Agile Practice Guide, 1st edition, Page 41]
Unattempted
The product owner is the owner of the product backlog and is ultimately accountable for the outcome of the project. At this stage, it is critical for you to review the entire backlog with the new product owner and ensure that they agree with the current ranking of stories. [Agile Practice Guide, 1st edition, Page 41]
Question 41 of 58
41. Question
Recently, there have been quality related problems in your project and your sponsor has asked you to work on improving the quality parameters. In this context, which of the following statements about the quality parameters is not correct?
Correct
One of the fundamental tenets of modern quality management states that quality is planned, designed and build in-not inspected in. Cost of preventing mistakes is generally much lower than cost of correcting them when they are found during inspection.
Incorrect
One of the fundamental tenets of modern quality management states that quality is planned, designed and build in-not inspected in. Cost of preventing mistakes is generally much lower than cost of correcting them when they are found during inspection.
Unattempted
One of the fundamental tenets of modern quality management states that quality is planned, designed and build in-not inspected in. Cost of preventing mistakes is generally much lower than cost of correcting them when they are found during inspection.
Question 42 of 58
42. Question
On demand scheduling is one of the techniques used in agile projects while performing schedule management activities. This type of scheduling techniques relies on which of the following?
Correct
On demand scheduling doesn’t rely a schedule that was developed previously for the development of project increments, but rather pulls work from a backlog or intermediate queue of work to be done immediately on resources to be available.
Incorrect
On demand scheduling doesn’t rely a schedule that was developed previously for the development of project increments, but rather pulls work from a backlog or intermediate queue of work to be done immediately on resources to be available.
Unattempted
On demand scheduling doesn’t rely a schedule that was developed previously for the development of project increments, but rather pulls work from a backlog or intermediate queue of work to be done immediately on resources to be available.
Question 43 of 58
43. Question
Middle path of your construction project, your senior cost controller informed you that the project cost performance is not going well as planned, and the project is over budget. Therefor, you requested her to reestimate the project cost, and she found that the remaining budget on the project will not be sufficient, and this will require an update on the cost baseline. In this situation, what should you do as the project manager?
Correct
You cannot just update the cost baseline immediately, this update requires you to issue a change request.
Incorrect
You cannot just update the cost baseline immediately, this update requires you to issue a change request.
Unattempted
You cannot just update the cost baseline immediately, this update requires you to issue a change request.
Question 44 of 58
44. Question
You are taking over a project manager who recently left the company. The prior project manager completed the project scope statement and scope management plan for this project. In your interviews with some key team members, you conclude which of the following? (Choose two.)
Correct
The scope management plan describes how project scope will be defined and validated, how the scope statement will be developed, how the WBS will be created and defined, and how project scope will be managed and controlled. Project scope is measured against the project management plan, whereas product scope is measured against the product requirements. It is based on the approved project scope. The project scope management plan defines, maintains, and manages the scope of the project.
Incorrect
The scope management plan describes how project scope will be defined and validated, how the scope statement will be developed, how the WBS will be created and defined, and how project scope will be managed and controlled. Project scope is measured against the project management plan, whereas product scope is measured against the product requirements. It is based on the approved project scope. The project scope management plan defines, maintains, and manages the scope of the project.
Unattempted
The scope management plan describes how project scope will be defined and validated, how the scope statement will be developed, how the WBS will be created and defined, and how project scope will be managed and controlled. Project scope is measured against the project management plan, whereas product scope is measured against the product requirements. It is based on the approved project scope. The project scope management plan defines, maintains, and manages the scope of the project.
Question 45 of 58
45. Question
Yousef is managing a large construction project of establishing the new underground metro lines in Cairo, and the four years project is halfway done. The project overall involves 32 suppliers, 8 sub-contractors, and 300 team members. The organization CEO will be visiting the project next week, and she wants to see where the project stands and what was accomplished tell now. In this situation, the _________ is the most helpful to present for the CEO.
Correct
In this case, the most useful to use is the progress report, it shows what has been accomplished tell now in a high level approach.
Incorrect
In this case, the most useful to use is the progress report, it shows what has been accomplished tell now in a high level approach.
Unattempted
In this case, the most useful to use is the progress report, it shows what has been accomplished tell now in a high level approach.
Question 46 of 58
46. Question
You have just become the project manager for a project which is running in the execution phase. During your first week of the job, you receive multiple requests from different stakeholders asking for project reports in various formats and such requests overwhelm you. In this situation, what should you do first?
Correct
First you should determine those requests are legitimate or not, the communications management plan documents stakeholders communication requirements and so it should be the first to do.
Incorrect
First you should determine those requests are legitimate or not, the communications management plan documents stakeholders communication requirements and so it should be the first to do.
Unattempted
First you should determine those requests are legitimate or not, the communications management plan documents stakeholders communication requirements and so it should be the first to do.
Question 47 of 58
47. Question
While performing scope control process, you ensure that all requested changes and recommended corrective actions are processed through the perform integrated change control process. In this context, if a change is requested, what should the project manager do first?
Correct
The project manager should always try to first evaluate the change and try to prevent unwarranted changes, which can adversely impact the project scope.
Incorrect
The project manager should always try to first evaluate the change and try to prevent unwarranted changes, which can adversely impact the project scope.
Unattempted
The project manager should always try to first evaluate the change and try to prevent unwarranted changes, which can adversely impact the project scope.
Question 48 of 58
48. Question
You have contracted a vendor to perform your project. Your vendor has complained to you that your stakeholders are difficult to work with and their expectations are unreasonable. Your vendor has also missed some requirements, which you discovered when you examined one portion of the finished product. Which of the following are true regarding this situation? (Choose three.)
Correct
It is the project manager’s responsibility to manage stakeholder expectations regarding project goals. The vendor may assist with this, but the responsibility for this rests with the project manager. Inspections are structured reviews of the work performed by the contractor, and audits are structured reviews of the procurement process.
Incorrect
It is the project manager’s responsibility to manage stakeholder expectations regarding project goals. The vendor may assist with this, but the responsibility for this rests with the project manager. Inspections are structured reviews of the work performed by the contractor, and audits are structured reviews of the procurement process.
Unattempted
It is the project manager’s responsibility to manage stakeholder expectations regarding project goals. The vendor may assist with this, but the responsibility for this rests with the project manager. Inspections are structured reviews of the work performed by the contractor, and audits are structured reviews of the procurement process.
Question 49 of 58
49. Question
One of the key stakeholders on a scrum software development project discovers a new requirement and approaches one of the team members to build it. The team member builds a prototype for the stakeholder, who is able to start using it immediately. Sami the product owner discovers this and demands that the team member include him in any future decisions, but the team member feels this is the most efficient way to work. Sami and team member approach Shadi who is the scrum master to resolve the conflict. What should Shadi do?
Correct
This is a case where Sami the product owner is right, and the team member is doing something that is potentially dangerous, The reason that Scrum teams have a product owner role is so that someone can stay on top of all stakeholder communications. There’s nothing wrong with team members working directly with stakeholders, but they should never cut the product owner out of the discussion.
Incorrect
This is a case where Sami the product owner is right, and the team member is doing something that is potentially dangerous, The reason that Scrum teams have a product owner role is so that someone can stay on top of all stakeholder communications. There’s nothing wrong with team members working directly with stakeholders, but they should never cut the product owner out of the discussion.
Unattempted
This is a case where Sami the product owner is right, and the team member is doing something that is potentially dangerous, The reason that Scrum teams have a product owner role is so that someone can stay on top of all stakeholder communications. There’s nothing wrong with team members working directly with stakeholders, but they should never cut the product owner out of the discussion.
Question 50 of 58
50. Question
The director of customer service has expressed concern over a project in which you’re involved. His specific concern is that if the project is implemented as planned, he’ll have to purchase additional equipment to staff his customer service center. The cost was not taken into consideration in the project budget. The project sponsor insists that the project must go forward as originally planned or the customer will suffer. Which of the following are true? (Choose two.)
Correct
Conflicts between stakeholders should always be resolved in favor of the customer. This question emphasizes the importance of identifying your stakeholders and their needs as early as possible in the project.
Incorrect
Conflicts between stakeholders should always be resolved in favor of the customer. This question emphasizes the importance of identifying your stakeholders and their needs as early as possible in the project.
Unattempted
Conflicts between stakeholders should always be resolved in favor of the customer. This question emphasizes the importance of identifying your stakeholders and their needs as early as possible in the project.
Question 51 of 58
51. Question
Tasks A, B, C, and D are on the critical path of a project, and all the tasks are estimated to require similar efforts of 5 days each and cost of $5,000 per task. At the end of the day 11, Task A and Task B are complete, Task C is 50% complete and $13,000 has already been spent. You know that current variances are atypical, i.e. similar variances will not occur in future. What is the cost performance index (CPI) for the project?
Correct
Earned value (EV)= the sum of the approved cost estimates for activities completed during a given period= estimated cost of work that is completed after day 11= $5,000+$5,000+$2,500=$12,500 (because Task A, Task B are complete, Task C is 50% complete). Actual cost (AC)= actual cost of work completed=$13,000. Cost performance index (CPI)= EV/AC=$12,500/$13,000=0.96
Incorrect
Earned value (EV)= the sum of the approved cost estimates for activities completed during a given period= estimated cost of work that is completed after day 11= $5,000+$5,000+$2,500=$12,500 (because Task A, Task B are complete, Task C is 50% complete). Actual cost (AC)= actual cost of work completed=$13,000. Cost performance index (CPI)= EV/AC=$12,500/$13,000=0.96
Unattempted
Earned value (EV)= the sum of the approved cost estimates for activities completed during a given period= estimated cost of work that is completed after day 11= $5,000+$5,000+$2,500=$12,500 (because Task A, Task B are complete, Task C is 50% complete). Actual cost (AC)= actual cost of work completed=$13,000. Cost performance index (CPI)= EV/AC=$12,500/$13,000=0.96
Question 52 of 58
52. Question
You’re managing a new outlet store construction project. You created a stakeholder register and stakeholder engagement plan, and now the team is implementing the work as per the project management plan. You’ve been managing the work, and now you’re looking at the work performance data to keep your stakeholders informed of the status of the project. You’ve discovered a change in the way your stakeholders look at the budget for your project. Which of the following best describes the next thing you should do?
Correct
When you look at work performance data and discover a new stakeholder requirement, you’re doing the monitor stakeholder engagement process. Some of the outputs of that process are change requests, project document updates, and project management plan updates.
Incorrect
When you look at work performance data and discover a new stakeholder requirement, you’re doing the monitor stakeholder engagement process. Some of the outputs of that process are change requests, project document updates, and project management plan updates.
Unattempted
When you look at work performance data and discover a new stakeholder requirement, you’re doing the monitor stakeholder engagement process. Some of the outputs of that process are change requests, project document updates, and project management plan updates.
Question 53 of 58
53. Question
Sami is very busy managing the project stakeholders at the final phases. He is trying to close out the project that he is leading, and there are many items to be addressed. Considering Sami’s priorities, and from the list of the four options below, what is the most important that Sami should do?
Correct
All the options are good advice to Sami, however, the best answer is to confirm that all project work has been completed and objectives met. That captures the goal of this process.
Incorrect
All the options are good advice to Sami, however, the best answer is to confirm that all project work has been completed and objectives met. That captures the goal of this process.
Unattempted
All the options are good advice to Sami, however, the best answer is to confirm that all project work has been completed and objectives met. That captures the goal of this process.
Question 54 of 58
54. Question
Match the following scaling agile frameworks with their description.
Correct
A-1, B-5, C-4, D-2, E-3. Scaling agile frameworks is a technique used to scale agile practices to the organization and incorporate multiple teams using agile methodologies.
Incorrect
A-1, B-5, C-4, D-2, E-3. Scaling agile frameworks is a technique used to scale agile practices to the organization and incorporate multiple teams using agile methodologies.
Unattempted
A-1, B-5, C-4, D-2, E-3. Scaling agile frameworks is a technique used to scale agile practices to the organization and incorporate multiple teams using agile methodologies.
Question 55 of 58
55. Question
Middle path of your agile project, and as part of an iteration planning meeting, a team member states that it is difficult to estimate the actual work needed to complete a task because of the involvement of new technology that the team is not familiar with. Also, in case of failure of the approach, this technology can result in potential risk to the project. In this case, the team should _________ to determine this unknown impact.
Correct
Spikes are helpful for learning purposes and are generally used in circumstances like acceptance criteria definition, estimating and understanding the flow, and applicability of ideas or actions. Generally in the cases, as given in the question, new technology should be investigated with the help of spikes that makes the team capable of identifying the possible issues at earlier stages which otherwise could consume the significant time of the team and lead to project failure. [Agile Practice Guide, 1st edition, Page 56]
Incorrect
Spikes are helpful for learning purposes and are generally used in circumstances like acceptance criteria definition, estimating and understanding the flow, and applicability of ideas or actions. Generally in the cases, as given in the question, new technology should be investigated with the help of spikes that makes the team capable of identifying the possible issues at earlier stages which otherwise could consume the significant time of the team and lead to project failure. [Agile Practice Guide, 1st edition, Page 56]
Unattempted
Spikes are helpful for learning purposes and are generally used in circumstances like acceptance criteria definition, estimating and understanding the flow, and applicability of ideas or actions. Generally in the cases, as given in the question, new technology should be investigated with the help of spikes that makes the team capable of identifying the possible issues at earlier stages which otherwise could consume the significant time of the team and lead to project failure. [Agile Practice Guide, 1st edition, Page 56]
Question 56 of 58
56. Question
As an agile practitioner, another agile leader in the organization comes to you for an advise. He is having trouble getting his team to take ownership of the project and get comfortable selecting the work to be done. He keeps finding himself making the decisions and directing their work. What do you advise him to do?
Correct
In this situation, the team leader should assume a coaching role to help the team members get to the point where they are comfortable selecting their own work. This will include meeting team members a half-step ahead, guaranteeing safety, partnering with their managers, and building positive regard.
Incorrect
In this situation, the team leader should assume a coaching role to help the team members get to the point where they are comfortable selecting their own work. This will include meeting team members a half-step ahead, guaranteeing safety, partnering with their managers, and building positive regard.
Unattempted
In this situation, the team leader should assume a coaching role to help the team members get to the point where they are comfortable selecting their own work. This will include meeting team members a half-step ahead, guaranteeing safety, partnering with their managers, and building positive regard.
Question 57 of 58
57. Question
You are managing a software development project, and during the last status meeting, the project team provided you with the earned value report showing the project is progressing well. At the end of the meeting, you just learned that a new regulatory requirement will cause a change in one of the project’s performance specifications. To ensure that this change is incorporated into the project management plan, what should be you first action?
Correct
The change request should detail the nature of the change and its effect on the project. Documentation is critical to provide a record of the change and who approved it, in case differences of opinion arise later. A change request is an output from the direct and manages project work process and an input to the perform integrated change control process.
Incorrect
The change request should detail the nature of the change and its effect on the project. Documentation is critical to provide a record of the change and who approved it, in case differences of opinion arise later. A change request is an output from the direct and manages project work process and an input to the perform integrated change control process.
Unattempted
The change request should detail the nature of the change and its effect on the project. Documentation is critical to provide a record of the change and who approved it, in case differences of opinion arise later. A change request is an output from the direct and manages project work process and an input to the perform integrated change control process.
Question 58 of 58
58. Question
Match the following characteristics of development life cycles to their description.
Correct
A-2, B-5, C-1, D-4, E-3. Each methodology has its own focus, benefits, and planning methods.
Incorrect
A-2, B-5, C-1, D-4, E-3. Each methodology has its own focus, benefits, and planning methods.
Unattempted
A-2, B-5, C-1, D-4, E-3. Each methodology has its own focus, benefits, and planning methods.